边坡预应力锚索

云南糯扎渡水电站 右岸泄洪洞出口645m公边坡预应力锚索

安全施工组织设计

四川******工程公司糯扎渡水电站项目部

****年**月**日

项目经理:

审 核:

项目总工:

编 写:

目 录

1概述 .........................................................................................................................................................................1 1.1 地理位置及交通运输条件.............................................................................................................................1 1.2 工程设计布置....................................................................................................................................................1 2工程安全施工措施………………………………………………………………………………………………3

2.1安全方针 ……………………………………………………………………………………….3 2.2 安全目标 ...........................................................................................................................................................3 2.3 安全管理组织机构...........................................................................................................................................3

2.4 安全施工措施....................................................................................................................................................4 2.4.1 施工现场安全措施 .......................................................................................................................................4 2.4.2安全用电措施 .................................................................................................................................................4 2.4.3 高空作业安全措施 .......................................................................................................................................5 2.4.4 管架施工安全措施 .......................................................................................................................................6 2.4.5 施工机具的安全措施...................................................................................................................................6 2.4.6 生活区安全措施 ...........................................................................................................................................6 2.5 文明施工措施....................................................................................................................................................6

3 安全防护材料及费用计划………………………………………………………………………7

1概述

1.1 地理位置及交通运输条件

糯扎渡水电站是澜沧江中下游水电站梯级“两库八级”开发方案中的第二库第五级,坝址位于云南省思茅市思茅港镇与澜沧县雅口乡交界处。水库上游与大朝山水电站连接,下游尾水紧接景洪水电站库尾,是一座以发电为主,结合防洪、改善航运以及其他综合效益的特大型水电站。水库总库容237.03×108m³,总装机容量5850MW,最大坝高261.5m。施工区距思茅市约100km,有思茅市至澜沧县公路穿过施工区,攻工区交通条件方便。

工程施工位置位于右岸泄洪洞出口EL645公路边坡,边坡高程EL.705~EL.750,分为两个马道梯段,场地狭窄,最高排锚索高程为EL.750,相距坝顶公路高差71.5m,最低排锚索高程EL710,现边坡正在开挖中,下部未形成进入施工场地的施工道路,施工用设备、材料只能运输至坝顶公路.。到施工作业面,只能靠人力搬运。工作面高、陡,岩层破碎,制约因素多,安全隐患大,施工难度大。

1.2 工程设计布置

工程施工位置位于糯扎渡水电站右岸泄洪洞出口EL.645m公路边坡EL.705.00~EL.750.00高程区域。锚索设计分布于EL.710、EL.715、EL.720、EL.730、EL.735、EL.740、EL.745、EL.750高程。工程布置详见布置图。锚索设计参数见表1.3-1。

表1.3-1 右岸泄洪洞出口645m公路边坡锚索设计参数表

1

2

2 工程安全施工措施

2.1安全管理方针

各作业单位必须将“安全第一,预防为主”的方针贯彻执行到施工过程中的每一工序,做到生产必须安全,安全促进生产。加强安全教育、安全培训,提高全员的安全意识。

2.2 安全目标

杜绝人员、机械重大安全责任事故及其他安全责任事故的发生。

2.3 安全管理组织机构

根据工程施工的具体情况,为确保项目安全目标的实现,项目部组建以项目部经理为组长,生产副经理为副组长,工程部经理、专职安全员和工程队长为成员的安全生产领导小组,主要负责项目部安全生产管理。项目部设置专职安全员,各作业班组设置兼职安全员,具体负责安全预防、保证措施实施和监督。安全责任落实到班组和个人,确保项目的施工安全。安全管理体系如下(图2.2-1):

全领导小组组长

世光

安全领导小组副组长

张涌泉、来智勇

队辅生队浇注队机电班

图2.2-1 安全管理体系

2.4 安全施工措施

2.4.1 施工现场安全措施

1)根据施工现场的实际情况,从EL.821.5坝顶公路修筑施工便道至作业面,施工便道两侧采用管架安设安全防护栏杆和爬梯,以利于人员通行和材料搬运,以及危险状态时人员的安全撤离。

2)施工现场的生活生产用房,变电房、发电房、空压房、临时油库等应符合防火,防洪、防风、防爆、防震的要求。

3)施工现场应设置安全警示标志,警示标志必须醒目、明了,并不得擅自拆除。

4)发电房、空压房等应采取必要的安全防护措施,严禁用易燃材料修建。

5)靠近公路和陡坡处的道路,应设置防护栏和明显警告标志。

2.4.2安全用电措施

1)加强对施工人员的安全用电教育。把安全用电、人人有责、自觉遵守安全用电规定落到实处,杜绝事故隐患。

2)电工在处理电气故障时,必须有一看护人员在场。

3)对施工场地的照明,机电线路应布设整齐,如与钢管接触应用绝缘物隔开,有条件要悬挂,并定期由专业人员检查、维护,施工人员严禁玩弄电器、线路,一旦发现施工场地机电线路有漏电、冒火等现象,应立即找电工处理,并应及时切断电源。

4)严禁用湿手摸带电设备,或用湿布擦拭。

5)发现电气火灾时,要立即拉断开关,切断电源,严禁带电泼水灭火。

6)发现有人触电,应赶快切断电源或用干燥木棒、竹竿将电线挑开,迅速使触电人脱离电源,并及时进行人工抢救。

7)场内架设的电线应绝缘良好,悬挂高度及线间距必须符合电业部门的安全规定。

8)不得将电线直接缠绕在钢筋,树木或脚手架上,现场临时线路架设,必须保证绝缘良好。

9)各种电气设备应配有专用开关并加装漏电保护装置,室外使用的开关、插座应外装防水箱并加锁,在操作处加设绝缘垫层。

10)在三相四线制中性点接地供电系统中,电器设备的金属外壳应做接零保护;

在非三相四线制供电系统中,电器设备的金属外壳应做接地保护,其接地电阻应小于4Ω,并不得在同一供电系统上有的接地,有的接零。

11)各种电气设备的检查维修,一般应停电作业;如必须带电作业时,应有可靠 的安全措施并派专人监护。

12)工地安装变压器必须符合电业部门要求,并设专人管理,施工用电要尽量保持三相平衡。

13)现场的变(配)电设备,必须有灭火器材和耐高压安全用具。非电工人员严禁接近带电设备。

14)检修电气设备时应按下列要求进行:

① 电气设备的检修必须由电工进行,其他人员不得任意操作;

② 工作中如遇停电应拉下开关、切断电源;检修结束须仔细检查各项设备的情况,没有异常,方可合闸。

③ 大型电气设备检修应在切断电源,设好防护后进行,并在开关处设置警示标牌,工作完成后方可拆除;如需进行送电试验时,必须在认真检查并与有关部门联系落实后,方可进行。

2.4.3 高空作业安全措施

1)排除作业面顶部活动危险物块,为防止意外物块侵入作业面,考虑在作业面顶层搭设安全防护顶棚。

2)高空作业设置可靠的安全网、栏杆、保险绳等。

3)立体交叉作业中,搭设牢固可靠的隔离层,严禁乱抛、乱扔工具或其他物体。

4)高架作业,必须系好安全绳,严禁违章操作。

5)上班时间内穿戴好安全防护用品(劳保鞋、工作服、安全帽、劳保手套、风镜)和上岗证。禁止非工作人员进入施工现场。

6)从事高架作业人员要定期检查,如有不宜登高的病症,不得从事高架作业。

7)班组人员在上岗前严禁酗酒,严禁带病上岗。

8)在施工过程中应精力集中,严禁打闹、开玩笑、打瞌睡,玩忽职守。

9)树立自保意识,防止受到他人伤害,同时也不伤害他人。

10)各班组准时交接班,严禁迟到、早退。

11)高架作业于地面联系,应有专人负责或配置通讯设备。

12)高边坡作业应在顶部设置挡墙或排水沟。

2.4.4 管架施工安全措施

1)架管、管卡质量必须有保证,满足规范要求,架管壁厚δ≮3.5mm。

2)管架必须稳定牢固,保证管架刚度,采用斜支撑、拉锚筋、剪刀架与主承载部位增加立柱密度相结合的措施,满足承载要求。在马道打设一排间距2×2m,深2.0m插筋,稳固底部脚手架;采用竹夹板在脚手架底部铺设高1m安全防护栏,防止施工掉物下坠,影响下部施工作业;在坡面打设φ25mm5×5m间距脚手架加固插筋,深1.5m,插筋与脚手架焊接加固。

3)搭设管架平台所用木板厚度δ≮45mm。

4)管架平台上设置安全网、安全绳,木板不得漏铺。

5)管架上设置明显的安全标识。

2.4.5 施工机具的安全措施

1)在施工前,电源、风水、管路应畅通。所有施工机具应检修完好,并加强养护,严禁误操作,杜绝隐形事故的发生。

2)加强对高空作业施工场地(平台、脚手架)和通讯设施的安检工作。

3)机具吊运必须捆扎牢固、可靠,所用吊运设备必须运行正常。

4)施工平台转运设备时,必须加固受力脚架,仔细检查钢绳和葫芦,捆扎牢固,吊物时下层施工人员必须撤离到安全地带。

5)机械拆卸时,各管口、接头必须包扎好,连接时必须洗净后连接,安装到位。

6)加强对施工机具、材料的保护,防止损坏与丢失,做到合理、节约用料。

2.4.6 生活区安全措施

1)加强生活区的安全、防盗工作,保管好自己的财物,不拿别人的财物。

2)加强防火工作,严禁抽卧床烟和乱扔烟头。

3)严禁乱拉、乱接电线,严禁私自烧电炉。

4)做到团结友爱、语言文明、严禁打架、斗殴。

5)加强宣传、教育,做到行动文明、卫生文明,严禁随地大小便。

6)加强自身约束,爱护公共财物,维护公共卫生,节约能源。

2.5 文明施工措施

1)项目部各级管理人员及工程队管理、施工人员,必须按照现行国家技术规

云南糯扎渡水电站 右岸泄洪洞出口645m公边坡预应力锚索

安全施工组织设计

四川******工程公司糯扎渡水电站项目部

****年**月**日

项目经理:

审 核:

项目总工:

编 写:

目 录

1概述 .........................................................................................................................................................................1 1.1 地理位置及交通运输条件.............................................................................................................................1 1.2 工程设计布置....................................................................................................................................................1 2工程安全施工措施………………………………………………………………………………………………3

2.1安全方针 ……………………………………………………………………………………….3 2.2 安全目标 ...........................................................................................................................................................3 2.3 安全管理组织机构...........................................................................................................................................3

2.4 安全施工措施....................................................................................................................................................4 2.4.1 施工现场安全措施 .......................................................................................................................................4 2.4.2安全用电措施 .................................................................................................................................................4 2.4.3 高空作业安全措施 .......................................................................................................................................5 2.4.4 管架施工安全措施 .......................................................................................................................................6 2.4.5 施工机具的安全措施...................................................................................................................................6 2.4.6 生活区安全措施 ...........................................................................................................................................6 2.5 文明施工措施....................................................................................................................................................6

3 安全防护材料及费用计划………………………………………………………………………7

1概述

1.1 地理位置及交通运输条件

糯扎渡水电站是澜沧江中下游水电站梯级“两库八级”开发方案中的第二库第五级,坝址位于云南省思茅市思茅港镇与澜沧县雅口乡交界处。水库上游与大朝山水电站连接,下游尾水紧接景洪水电站库尾,是一座以发电为主,结合防洪、改善航运以及其他综合效益的特大型水电站。水库总库容237.03×108m³,总装机容量5850MW,最大坝高261.5m。施工区距思茅市约100km,有思茅市至澜沧县公路穿过施工区,攻工区交通条件方便。

工程施工位置位于右岸泄洪洞出口EL645公路边坡,边坡高程EL.705~EL.750,分为两个马道梯段,场地狭窄,最高排锚索高程为EL.750,相距坝顶公路高差71.5m,最低排锚索高程EL710,现边坡正在开挖中,下部未形成进入施工场地的施工道路,施工用设备、材料只能运输至坝顶公路.。到施工作业面,只能靠人力搬运。工作面高、陡,岩层破碎,制约因素多,安全隐患大,施工难度大。

1.2 工程设计布置

工程施工位置位于糯扎渡水电站右岸泄洪洞出口EL.645m公路边坡EL.705.00~EL.750.00高程区域。锚索设计分布于EL.710、EL.715、EL.720、EL.730、EL.735、EL.740、EL.745、EL.750高程。工程布置详见布置图。锚索设计参数见表1.3-1。

表1.3-1 右岸泄洪洞出口645m公路边坡锚索设计参数表

1

2

2 工程安全施工措施

2.1安全管理方针

各作业单位必须将“安全第一,预防为主”的方针贯彻执行到施工过程中的每一工序,做到生产必须安全,安全促进生产。加强安全教育、安全培训,提高全员的安全意识。

2.2 安全目标

杜绝人员、机械重大安全责任事故及其他安全责任事故的发生。

2.3 安全管理组织机构

根据工程施工的具体情况,为确保项目安全目标的实现,项目部组建以项目部经理为组长,生产副经理为副组长,工程部经理、专职安全员和工程队长为成员的安全生产领导小组,主要负责项目部安全生产管理。项目部设置专职安全员,各作业班组设置兼职安全员,具体负责安全预防、保证措施实施和监督。安全责任落实到班组和个人,确保项目的施工安全。安全管理体系如下(图2.2-1):

全领导小组组长

世光

安全领导小组副组长

张涌泉、来智勇

队辅生队浇注队机电班

图2.2-1 安全管理体系

2.4 安全施工措施

2.4.1 施工现场安全措施

1)根据施工现场的实际情况,从EL.821.5坝顶公路修筑施工便道至作业面,施工便道两侧采用管架安设安全防护栏杆和爬梯,以利于人员通行和材料搬运,以及危险状态时人员的安全撤离。

2)施工现场的生活生产用房,变电房、发电房、空压房、临时油库等应符合防火,防洪、防风、防爆、防震的要求。

3)施工现场应设置安全警示标志,警示标志必须醒目、明了,并不得擅自拆除。

4)发电房、空压房等应采取必要的安全防护措施,严禁用易燃材料修建。

5)靠近公路和陡坡处的道路,应设置防护栏和明显警告标志。

2.4.2安全用电措施

1)加强对施工人员的安全用电教育。把安全用电、人人有责、自觉遵守安全用电规定落到实处,杜绝事故隐患。

2)电工在处理电气故障时,必须有一看护人员在场。

3)对施工场地的照明,机电线路应布设整齐,如与钢管接触应用绝缘物隔开,有条件要悬挂,并定期由专业人员检查、维护,施工人员严禁玩弄电器、线路,一旦发现施工场地机电线路有漏电、冒火等现象,应立即找电工处理,并应及时切断电源。

4)严禁用湿手摸带电设备,或用湿布擦拭。

5)发现电气火灾时,要立即拉断开关,切断电源,严禁带电泼水灭火。

6)发现有人触电,应赶快切断电源或用干燥木棒、竹竿将电线挑开,迅速使触电人脱离电源,并及时进行人工抢救。

7)场内架设的电线应绝缘良好,悬挂高度及线间距必须符合电业部门的安全规定。

8)不得将电线直接缠绕在钢筋,树木或脚手架上,现场临时线路架设,必须保证绝缘良好。

9)各种电气设备应配有专用开关并加装漏电保护装置,室外使用的开关、插座应外装防水箱并加锁,在操作处加设绝缘垫层。

10)在三相四线制中性点接地供电系统中,电器设备的金属外壳应做接零保护;

在非三相四线制供电系统中,电器设备的金属外壳应做接地保护,其接地电阻应小于4Ω,并不得在同一供电系统上有的接地,有的接零。

11)各种电气设备的检查维修,一般应停电作业;如必须带电作业时,应有可靠 的安全措施并派专人监护。

12)工地安装变压器必须符合电业部门要求,并设专人管理,施工用电要尽量保持三相平衡。

13)现场的变(配)电设备,必须有灭火器材和耐高压安全用具。非电工人员严禁接近带电设备。

14)检修电气设备时应按下列要求进行:

① 电气设备的检修必须由电工进行,其他人员不得任意操作;

② 工作中如遇停电应拉下开关、切断电源;检修结束须仔细检查各项设备的情况,没有异常,方可合闸。

③ 大型电气设备检修应在切断电源,设好防护后进行,并在开关处设置警示标牌,工作完成后方可拆除;如需进行送电试验时,必须在认真检查并与有关部门联系落实后,方可进行。

2.4.3 高空作业安全措施

1)排除作业面顶部活动危险物块,为防止意外物块侵入作业面,考虑在作业面顶层搭设安全防护顶棚。

2)高空作业设置可靠的安全网、栏杆、保险绳等。

3)立体交叉作业中,搭设牢固可靠的隔离层,严禁乱抛、乱扔工具或其他物体。

4)高架作业,必须系好安全绳,严禁违章操作。

5)上班时间内穿戴好安全防护用品(劳保鞋、工作服、安全帽、劳保手套、风镜)和上岗证。禁止非工作人员进入施工现场。

6)从事高架作业人员要定期检查,如有不宜登高的病症,不得从事高架作业。

7)班组人员在上岗前严禁酗酒,严禁带病上岗。

8)在施工过程中应精力集中,严禁打闹、开玩笑、打瞌睡,玩忽职守。

9)树立自保意识,防止受到他人伤害,同时也不伤害他人。

10)各班组准时交接班,严禁迟到、早退。

11)高架作业于地面联系,应有专人负责或配置通讯设备。

12)高边坡作业应在顶部设置挡墙或排水沟。

2.4.4 管架施工安全措施

1)架管、管卡质量必须有保证,满足规范要求,架管壁厚δ≮3.5mm。

2)管架必须稳定牢固,保证管架刚度,采用斜支撑、拉锚筋、剪刀架与主承载部位增加立柱密度相结合的措施,满足承载要求。在马道打设一排间距2×2m,深2.0m插筋,稳固底部脚手架;采用竹夹板在脚手架底部铺设高1m安全防护栏,防止施工掉物下坠,影响下部施工作业;在坡面打设φ25mm5×5m间距脚手架加固插筋,深1.5m,插筋与脚手架焊接加固。

3)搭设管架平台所用木板厚度δ≮45mm。

4)管架平台上设置安全网、安全绳,木板不得漏铺。

5)管架上设置明显的安全标识。

2.4.5 施工机具的安全措施

1)在施工前,电源、风水、管路应畅通。所有施工机具应检修完好,并加强养护,严禁误操作,杜绝隐形事故的发生。

2)加强对高空作业施工场地(平台、脚手架)和通讯设施的安检工作。

3)机具吊运必须捆扎牢固、可靠,所用吊运设备必须运行正常。

4)施工平台转运设备时,必须加固受力脚架,仔细检查钢绳和葫芦,捆扎牢固,吊物时下层施工人员必须撤离到安全地带。

5)机械拆卸时,各管口、接头必须包扎好,连接时必须洗净后连接,安装到位。

6)加强对施工机具、材料的保护,防止损坏与丢失,做到合理、节约用料。

2.4.6 生活区安全措施

1)加强生活区的安全、防盗工作,保管好自己的财物,不拿别人的财物。

2)加强防火工作,严禁抽卧床烟和乱扔烟头。

3)严禁乱拉、乱接电线,严禁私自烧电炉。

4)做到团结友爱、语言文明、严禁打架、斗殴。

5)加强宣传、教育,做到行动文明、卫生文明,严禁随地大小便。

6)加强自身约束,爱护公共财物,维护公共卫生,节约能源。

2.5 文明施工措施

1)项目部各级管理人员及工程队管理、施工人员,必须按照现行国家技术规


相关文章

  • 浅谈预应力锚索地梁在高边坡治理中的应用
  • [文章编号]:1672-4011(2006)04-0113-03 浅谈预应力锚索地梁在高边坡治理中的应用 纪增财 (广东省清远市公路勘察规划设计院,511515) [摘 要]:本文以京珠高速公路两处不稳定高边坡治理工程为例,介绍一种新型抗滑 ...查看


  • 高边坡预应力锚索框架支护施工工法
  • 高边坡预应力锚索框架支护施工工法 1.前言 预应力锚索框架是随着锚固技术发展起来的,并广泛应用于公路.铁路.水利等工程高边坡和建筑工程基坑防护的加固工程中.本工法主要介绍了高速公路高边坡整治工程中预应力锚索的应用,阐明预应力锚索在边坡加固中 ...查看


  • 预应力锚索加固高边坡施工技术
  • 预应力锚索加固高边坡施工技术 摘 要:预应力锚固技术以其技术先进.经济合理.安全适用等优点,在世界各国得到了越来越广泛的应用.结合牛毛坞镇项目工程实例,详细介绍锚索的施工方法和施工工艺. 关键词:边坡加固:预应力锚索:施工 Abstract ...查看


  • 预应力锚索受力分析及设计计算实例
  • &68& 第36卷第36期 2010年12月 山 西建筑 Vo.l36No.36 Dec. 2010SHANXI ARCHITECTURE 文章编号:1009 6825(2010)36 0068 03 预应力锚索受力分析及设 ...查看


  • 预应力锚索张拉方案
  • K172+300~K172+650左侧 边坡预应力锚索张拉方案 编制: 审核: 审批: K172+300~K172+650段 左侧边坡预应力锚索锁定张拉方案 1.工程概况及设计方案 K172+300-K172+650左侧,该边坡高约41米, ...查看


  • 浅谈边坡加固与防护技术
  • 浅谈边坡加固与防护技术 田亮亮 摘要:从国内外的发展现状来看,边坡加固的方法有很多种,主要有护脚墙.抗滑柱.抗滑墙.压浆锚柱.预应力锚索.排水固结等.每种方法都针对不同类型的边坡进行加固,但是在实际工程中,如何因地制宜的利用好这些边坡加固技 ...查看


  • 边坡开挖及支护施工技术要求
  • 中国水电顾问集团成都院 四川大渡河黄金坪水电站 引水发电及泄洪(放空)系统 边坡开挖支护施工技术要求 中国水电顾问集团成都勘测设计研究院 2010年08月 院 长:郑声安 总工程师:王仁坤 项目经理:何顺宾 项目总工:伍小玉 审 查: 蒲晓 ...查看


  • 预应力锚索张拉伸长量的控制方法
  • 25m预应力锚索张拉伸长量的控制 25m预应力锚索张拉伸长量的控制 (中铁十一局集团第四工程有限公司 刘继伟) 关键词:预应力 伸长量 摘 要:预应力锚索框架支护,是一种新型的抗滑结构.它将高边坡病害防治与坡面柔性防护有机地结合在一起,既达 ...查看


  • 预应力锚索
  • 编号:隧-021 锚索框架梁施工 技术交底 编制:施工技术部 中铁十六局集团沪昆客专长昆湖南段第二项目分部 二0一一年七月 技 术 交 底 书 第1页 共11页 预应力锚索框架梁技术交底书 1工法特点 其主要施工环节有三个:一是锚孔成孔,锚 ...查看


  • 岩体与锚固体间粘结强度的确定
  • 第22卷第4期 2001年12月 岩土 力学 Vd.22No.4 RockandSoftMechanics 文章编号:1000一7598一(2001)04-0470-04 岩体与锚固体间粘结强度的确定 张发明"2,陈祖煜2,刘 宁 ...查看