应急水源地(金龙湖大坝)工程施工组织设计
目录
一、 工程概况 . ........................................................................................................................................... 1
1. 规模 . ............................................................................................................ 错误!未定义书签。 2. 说明简述 . ....................................................................................................................................... 5
2.1、坝体布置 ........................................................................................................................... 5 2.2、坝顶高程及坝顶结构 ....................................................................................................... 5 2.3、坝坡及护坡 ....................................................................................................................... 5 2.4、坝体结构 ........................................................................................................................... 6 2.5、基础防渗 ........................................................................................................................... 6 2.6、基础处理 ........................................................................................................................... 6 3. 主要工程量 . ................................................................................................................................... 6 二、 施工组织计划 . ................................................................................................................................... 7
1. 项目管理网络 . ............................................................................................................................. 7 1.1. 各职能办公室组成: ............................................................................................................... 7 1.2. 项目管理组织机构 ................................................................................................................... 8 1.3. 项目质量管理网络 ................................................................................................................... 9 1.4. 项目安全管理网络 ................................................................................................................. 10 1.5. 项目组织机构人员及分工 ..................................................................................................... 11 1.6. 工程机械设备组织 ................................................................................................................. 11
1.6.1. 机械设备的管理与调配 ............................................................................................. 11 1.6.2. 施工机械的合理配置 ................................................................................................. 12 1.7. 施工机械设备配置 ................................................................................................................. 12 1.8. 劳动力计划表.......................................................................................................................... 12 1.9. 施工总平面布置 ..................................................................................................................... 13 1.10. 施工区域划分 ....................................................................................................................... 13 1.11. 项目部及临舍布置 ............................................................................................................... 13 1.12. 施工道路 . ............................................................................................................................... 13 1.13. 施工用水用电概况 ............................................................................................................... 13
2. 工程进度计划及工期保证措施 ......................................................................................................... 14
2.1. 工程施工计划.......................................................................................................................... 14 2.2. 工期保证措施.......................................................................................................................... 14 2.3. 组织管理措施.......................................................................................................................... 14 2.4. 技术管理上的保证措施 ......................................................................................................... 15 3. 主要项目施工技术方案 ..................................................................................................................... 15
3.1. 施工测量 . ................................................................................................................................. 15 3.2. 测量前准备工作 ..................................................................................................................... 16 3.3. 大坝的定位及高程控制测量 ................................................................................................. 16 3.4. 横断面测量 . ............................................................................................................................. 16 3.5. 施工测量注意事项 ................................................................................................................. 16 3.6. 大坝施工方案.......................................................................................................................... 17
3.6.1. 坝基土石方开挖 ......................................................................................................... 17 3.6.2. 坝壳料选择 ................................................................................................................. 17 3.6.3. Ⅰ区坝壳砂砾料 ......................................................................................................... 17 3.6.4. Ⅱ区开挖利用料 ......................................................................................................... 18 3.6.5. 细砂垫层 ..................................................................................................................... 18 3.6.6. 坝体填筑 ..................................................................................................................... 18 3.6.7. 砂砾料开采及碾压试验 ............................................................................................. 18 3.6.8. 填筑要求 ..................................................................................................................... 19 3.6.9. 防渗土工膜工程 ......................................................................................................... 20 3.6.10. 复合土工膜技术要求 ............................................................................................... 20 3.6.11. 运输及储存 ............................................................................................................... 21 3.6.12. 接缝焊接 ................................................................................................................... 21 3.6.13. 铺设............................................................................................................................ 22 3.6.14. 焊缝质量检测 ........................................................................................................... 22 3.6.15. 完工验收 ................................................................................................................... 22 3.6.16. 防渗土工膜工程资料 ............................................................................................... 23 3.6.17. 盖板砼浇筑 ............................................................................................................... 23 3.6.18. 说明............................................................................................................................ 23 3.6.19. 止水、伸缩缝 ........................................................................................................... 23
3.6.20. 混凝土 ....................................................................................................................... 25 3.6.21. 帷幕灌浆工程 ........................................................................................................... 26 3.6.22. 防渗标准 ................................................................................................................... 27 3.6.23. 灌浆材料及技术参数 ............................................................................................... 27 3.6.24. 灌浆试验 ................................................................................................................... 27 3.6.25. 技术要求 ................................................................................................................... 28 3.6.26. 砌体工程 ................................................................................................................... 34 3.6.27. 砌石材料要求 ........................................................................................................... 34 3.6.28. 干砌石砌筑 ............................................................................................................... 34
4. 质量安全文明施工保证措施 ............................................................................................................. 34
4.1. 安全文明施工目标 ................................................................................................................. 34 4.2. 质量体系管理机构 ................................................................................................................. 35 4.3. 施工质量管理制度 ................................................................................................................. 35
4.3.1. 项目经理岗位职责 ..................................................................................................... 35 4.3.2. 项目副经理岗位职责 ................................................................................................. 36 4.3.3. 项目总工程师岗位职责 ............................................................................................. 36 4.3.4. 项目质量检查员岗位职责 ......................................................................................... 36 4.3.5. 项目资料员岗位职责 ................................................................................................. 36 4.3.6. 项目材料员岗位职责 ................................................................................................. 37 4.3.7. 质量检测能力及手段 ................................................................................................. 37 4.4. 施工物资保证措施 ................................................................................................................. 38 4.5. 施工队伍管理保证措施 ......................................................................................................... 38 4.6. 工程档案管理措施 ................................................................................................................. 39 4.7. 工程回访保修计划 ................................................................................................................. 39 4.8. 违约处罚措施.......................................................................................................................... 39 4.9. 安全、文明施工目标 ............................................................................................................. 40 4.10. 安全、文明施工管理机构: ............................................................................................... 40 4.11. 各级人员安全生产职责 ....................................................................................................... 40 4.12. 安全生产实施措施 ............................................................................................................... 42 4.13. 管理措施 . ............................................................................................................................... 43 4.14. 技术安全措施 ....................................................................................................................... 44
4.15. 夏季高温时期安全施工措施 ............................................................................................... 44 5. 企业使用劳务工工资发放到位的保证措施 ..................................................................................... 44
5.1. 劳务工工资发放到位承诺 ..................................................................................................... 44
5.2. 劳务工工资发放到位保证措施
-. 规模
一、工程概况
在主湖泊(L10)南部设计一座土工膜斜墙土石坝,做为其形成湖泊的挡水建筑物。坝顶长为893m ,坝顶宽为10m ,上下游坝坡均为1:5,最大坝高为12.7m 。湖泊总库容570万 m 3。
根据《水利水电工程等级划分及洪水标准》(SL 252-2000),按总库容划分,碾压式土石坝工程规模属小(1)型,工程等别为IV 等。
为了景观设计要求,坝轴线为非直线,根据《碾压式土石坝设计规范》(SL 274-2001)规定,设计地震烈度在VII 度以下时,坝轴线可选用非直线,故本阶段坝轴线设计成弧线。
1. 说明简述
2.1、坝体布置
土石坝位于主湖泊(L10)南部,坝顶长为893m ,为土工膜斜墙土石坝。坝轴线控制拐点坐标见设计图纸图号JLH.S-BG-01。
2.2、坝顶高程及坝顶结构
坝顶高程为341.50m ,最大坝高为13.2m ,坝顶主要宽度为10m ,坝顶设有观景平台,观景平台控制拐点坐标见设计图纸图号JLH.S-BG-01。
坝顶不设防浪墙,坝顶路面结构及护栏由景观统一设计。大坝两端与园区道路相接,结合部位处理见其他部分。
2.3、坝坡及护坡
上下游坝坡均为1:5,上游坝坡采用干砌块石护坡,护坡厚0.3m 。下游坝坡形式由景
观统一设计。
2.4、坝体结构
坝体自上游至下游依次为:300mm 厚块石护坡→500mm 厚砂砾料→50mm 厚细砂垫层→两布一膜→50mm 厚细砂垫层→Ⅰ区坝壳砂砾料→Ⅱ区利用料→贴坡排水体。
Ⅰ区与Ⅱ区填筑分界线设丙纶针刺无纺布一道,单位面积质量200g/m2,沿1:2折坡点向上铺设5m 。
2.5、基础防渗
大坝沿上游坝脚设单排帷幕,帷幕灌浆孔距2m ,帷幕灌浆深度达到q ≤5Lu 的埋深界线。灌浆孔顶部设2.0³0.8m (宽³厚)的砼盖板,坝体防渗土工膜通过5cm 宽扁钢、橡胶片用膨胀螺栓与砼盖板连接,使坝体与坝基防渗形成封闭整体。
砼盖板上回填1.5m 厚的粘土,粘土可采用库区开挖的泥岩。
2.6、基础处理
根据地质条件,坝断面范围内淤泥和腐植土等须全部清除干净,坝基清基至强风化下限基岩上,在坝基开挖时需预留30~50cm 厚的保护层,清基完成应尽快填筑砂砾料。以保证坝基不被快速风化。
坝壳建基面上有碍坝体填筑施工(有碍碾压机具行进到位或影响压实效果等)的陡坎、反坡、尖凸岩体及岩坎均应进行清理和削坡整治,使建基面大致平顺。
2. 主要工程量
本技术要求主要内容为坝体填筑工程、防渗土工膜工程、砌体工程、盖板砼浇筑工程、帷幕灌浆工程及土石方开挖工程。
主要工程量如下:
二、施工组织计划
1.项目管理网络
根据新疆****市金龙湖湖体工程 主湖泊(L10)大坝特点,我单位建立以项目经理为首的项目经理部,全权组织施工生产诸要素,对工程项目的工期、质量、安全、成本、合同等进行高效率、有计划的组织协调和管理。项目部下设质量办、技术办、材料设备供应办、经营办、HSE 和环境管理办公室、试验室、资料室、综合办等项目职能办公室。
1.1. 各职能办公室组成:
1. 生产技术办:设生产负责人、土建技术员、安装技术员、机械设备管理员、测量员
等。
2. 质量安全办:设质量员、调度员等。 3. 材料办:物资设备采购员、仓库管理员等。
4. 计划经营办:设计划统计员、预算员、合同管理员、会计、出纳等。 5. 综合办:食堂管理员、卫生员、保卫员等。 6. 资料室:资料员 7. 试验室:试验员
1.2. 项目管理组织机构
1.3. 项目质量管理网络
1.4. 项目安全管理网络
1.5. 项
1.6. 工程机械设备组织
1.6.1.
机械设备的管理与调配
本工程投入的机械设备均采用租赁为主,公司的机械设备为辅,由项目经理部统一指挥、调配使用,其中阶段性及加工性机械随工程进度情况逐步进出场;帷幕灌浆调用专业施工队进行施工。
1.6.2. 施工机械的合理配置
1.6.2.1. 土方施工机械的选择,本工程土方开挖及回填采用:反铲挖掘机、装载机、自
卸车、压路机、平地机、撒水车、打夯机械等。
1.6.2.2. 垂直运输机械选择,本工程砼均采用泵车输送。
1.7. 施工机械设备配置
施工主要机械设备表
1.8. 劳动力计划表
1.9. 施工总平面布置
工程位于****城区东南郊,东至东环路,南至石化大道,西、北至****河,地理坐标为北纬45°35′56″,东经84°54′54.9″,场地现状为戈壁滩, 施工队临时设施均设置在项目总部的后面,见施工总平面图。
1.10. 施工区域划分
本工程由于工期紧,工作面较大,为加快施工进度分为2个作业区,K0+00至K0+550为1个施工作业区,K0+550至K0+893为1个施工作业区. 每个作业区域从末尾两端同时施工作业.
1.11. 项目部及临舍布置
经过对本工程施工区域和周边的勘查、分析结果;为了解决项目办公及施工人员用水、用电、生活等临时设施均设置项目总部的后面,见施工总平面图
(其布置相见 “项目部平面布置图”)。
1.12. 施工道路
施工道路及施工临施所需的通行路面由施工单位自行修筑临时道路,以满足生产和生的需要。
1.13. 施工用水用电概况
1.13.1施工用水
施工临时用水方案经业主及监理批准后,已到供水部门办理了相关接入手续,按照临时用水方案接入.
1.13.2施工用电
施工临时用电(高压、低压)方案经业主及监理批准后,已到供水部门办理了相关接入手续,按照临时用电方案接入.
2. 工程进度计划及工期保证措施
2.1. 工程施工计划
详:施进度计划表
按照工程实际情况及业主要求,本工程于2014年8月3日开工,2014年10月15日竣工;为了加快施工进度每天必须施工作业20小时以上,分班作业。我方根据工程特点制定了工程完工的一个框架目标:
土石方开挖:2014.6.3至2014.6.20
大坝土方回填碾压:2014.6.20至2014.9.10 砼盖板:2014.6.20至2014.9.5 帷幕灌浆 :2014.6.28至2014.9.15 上游块石护坡:2014.9.25至2014.8.10 贴坡排水及排水沟 :2014.9.25至2014.8.10
2.2. 工期保证措施
2.2.1、增加机械设备.
2.2.2、施工施工作业人员及施工管理人员. 2.2.3、增加作业时间.
2.2.4、租赁设备采用现金结算方式,采用月结或日结方式.
2.2.5、准备大量资金,以保障机械设备的油料及施工人员的生活及办公需求.
2.3. 组织管理措施
4.2.1.1 将该工程列为公司的重点工程,从机械、设备、技术人员、劳动力、材料、资金等方面给以优先保证。
4.2.1.2 严格按照项目法管理,配备强有力的项目经理部人员,建立完善的管理体系,将进度计划分解到各部门,层层签订承包合同,责任落实到人。制定明确的工期奖罚制度,
使效益、分配与质量、安全、进度挂钩,激发职工的生产积极性。
4.2.1.3 按施工组织设计投入足够的人力、物力、财力,满足进度要求。
4.2.1.4 建立奖罚制度:对将工期提前的班组,给予一定的经济奖励;对将工期拖延的施工班组进行处罚或更换施工班组,做到工期与经济效益挂钩。
4.2.1.5 配合业主做好前期准备工作,工期保证从工程开工初期抓起。
4.2.1.6 在取得业主、监理、设计单位的支持下,积极推广新技术、新工艺,加快施工进度。
4.2.1.7 加强质量检查工作,做到隐蔽工程验收一次通过,尽量不要返工和返修,不因质量方面的原因而影响工期。
4.2.1.8 对进度、劳力、材料、投资等方面的信息进行信息化动态管理,以科学为依据,运用统筹方法、网络技术合理配置资源,优化、深化施工组织。
2.4. 技术管理上的保证措施
4.2.2.1 根据设计图纸、地质勘测报告和现场情况,编制周密、科学的施工组织设计,合理安排各主要施工工序,在确保关键线路工程的同时有效地组织均衡生产,提高效率,确保整个工程的施工进度。
4.2.2.2 加强施工过程中的计划管理及进度控制,根据批准后的施工组织、总工期、关键工期的要求,编制周密细致的月、旬、周的施工生产计划,以日保周,以周保旬,以旬保月,强调当日计划当日完成。同时,还要对照实际进度、客观条件,对计划进行分析、调整,不断完善管理,从而确保工程进度。
4.2.2.3 施工机具按施工组织计划按时进场,并配备足够的易损件和消耗材料,制定机械操作规程,严格管理,配备机修小组对机械进行保养和维修。同时在现场配备发电机组,以应付停电和高峰期供电所需。在必要时,要及时加大设备的投入。
4.2.2.4 根据施工安排,制订合理的用款计划和材料供应计划,避免停工待料的现象发生。
4.2.2.5 定期对工人进行技术培训,做好新进场工人和新工序工前的技术交底,提高工人的素质和技术水平,加快施工进度。
3. 主要项目施工技术方案
3.1. 施工测量
对设计提供的施工区各级控制网、坐标点、水准点进行对比测量复核,确保准确无误后,根据这些控制网点建立施工测量控制系统。各控制点选点应选在视野宽、地势高、不
应急水源地(金龙湖大坝)工程施工组织设计
目录
一、 工程概况 . ........................................................................................................................................... 1
1. 规模 . ............................................................................................................ 错误!未定义书签。 2. 说明简述 . ....................................................................................................................................... 5
2.1、坝体布置 ........................................................................................................................... 5 2.2、坝顶高程及坝顶结构 ....................................................................................................... 5 2.3、坝坡及护坡 ....................................................................................................................... 5 2.4、坝体结构 ........................................................................................................................... 6 2.5、基础防渗 ........................................................................................................................... 6 2.6、基础处理 ........................................................................................................................... 6 3. 主要工程量 . ................................................................................................................................... 6 二、 施工组织计划 . ................................................................................................................................... 7
1. 项目管理网络 . ............................................................................................................................. 7 1.1. 各职能办公室组成: ............................................................................................................... 7 1.2. 项目管理组织机构 ................................................................................................................... 8 1.3. 项目质量管理网络 ................................................................................................................... 9 1.4. 项目安全管理网络 ................................................................................................................. 10 1.5. 项目组织机构人员及分工 ..................................................................................................... 11 1.6. 工程机械设备组织 ................................................................................................................. 11
1.6.1. 机械设备的管理与调配 ............................................................................................. 11 1.6.2. 施工机械的合理配置 ................................................................................................. 12 1.7. 施工机械设备配置 ................................................................................................................. 12 1.8. 劳动力计划表.......................................................................................................................... 12 1.9. 施工总平面布置 ..................................................................................................................... 13 1.10. 施工区域划分 ....................................................................................................................... 13 1.11. 项目部及临舍布置 ............................................................................................................... 13 1.12. 施工道路 . ............................................................................................................................... 13 1.13. 施工用水用电概况 ............................................................................................................... 13
2. 工程进度计划及工期保证措施 ......................................................................................................... 14
2.1. 工程施工计划.......................................................................................................................... 14 2.2. 工期保证措施.......................................................................................................................... 14 2.3. 组织管理措施.......................................................................................................................... 14 2.4. 技术管理上的保证措施 ......................................................................................................... 15 3. 主要项目施工技术方案 ..................................................................................................................... 15
3.1. 施工测量 . ................................................................................................................................. 15 3.2. 测量前准备工作 ..................................................................................................................... 16 3.3. 大坝的定位及高程控制测量 ................................................................................................. 16 3.4. 横断面测量 . ............................................................................................................................. 16 3.5. 施工测量注意事项 ................................................................................................................. 16 3.6. 大坝施工方案.......................................................................................................................... 17
3.6.1. 坝基土石方开挖 ......................................................................................................... 17 3.6.2. 坝壳料选择 ................................................................................................................. 17 3.6.3. Ⅰ区坝壳砂砾料 ......................................................................................................... 17 3.6.4. Ⅱ区开挖利用料 ......................................................................................................... 18 3.6.5. 细砂垫层 ..................................................................................................................... 18 3.6.6. 坝体填筑 ..................................................................................................................... 18 3.6.7. 砂砾料开采及碾压试验 ............................................................................................. 18 3.6.8. 填筑要求 ..................................................................................................................... 19 3.6.9. 防渗土工膜工程 ......................................................................................................... 20 3.6.10. 复合土工膜技术要求 ............................................................................................... 20 3.6.11. 运输及储存 ............................................................................................................... 21 3.6.12. 接缝焊接 ................................................................................................................... 21 3.6.13. 铺设............................................................................................................................ 22 3.6.14. 焊缝质量检测 ........................................................................................................... 22 3.6.15. 完工验收 ................................................................................................................... 22 3.6.16. 防渗土工膜工程资料 ............................................................................................... 23 3.6.17. 盖板砼浇筑 ............................................................................................................... 23 3.6.18. 说明............................................................................................................................ 23 3.6.19. 止水、伸缩缝 ........................................................................................................... 23
3.6.20. 混凝土 ....................................................................................................................... 25 3.6.21. 帷幕灌浆工程 ........................................................................................................... 26 3.6.22. 防渗标准 ................................................................................................................... 27 3.6.23. 灌浆材料及技术参数 ............................................................................................... 27 3.6.24. 灌浆试验 ................................................................................................................... 27 3.6.25. 技术要求 ................................................................................................................... 28 3.6.26. 砌体工程 ................................................................................................................... 34 3.6.27. 砌石材料要求 ........................................................................................................... 34 3.6.28. 干砌石砌筑 ............................................................................................................... 34
4. 质量安全文明施工保证措施 ............................................................................................................. 34
4.1. 安全文明施工目标 ................................................................................................................. 34 4.2. 质量体系管理机构 ................................................................................................................. 35 4.3. 施工质量管理制度 ................................................................................................................. 35
4.3.1. 项目经理岗位职责 ..................................................................................................... 35 4.3.2. 项目副经理岗位职责 ................................................................................................. 36 4.3.3. 项目总工程师岗位职责 ............................................................................................. 36 4.3.4. 项目质量检查员岗位职责 ......................................................................................... 36 4.3.5. 项目资料员岗位职责 ................................................................................................. 36 4.3.6. 项目材料员岗位职责 ................................................................................................. 37 4.3.7. 质量检测能力及手段 ................................................................................................. 37 4.4. 施工物资保证措施 ................................................................................................................. 38 4.5. 施工队伍管理保证措施 ......................................................................................................... 38 4.6. 工程档案管理措施 ................................................................................................................. 39 4.7. 工程回访保修计划 ................................................................................................................. 39 4.8. 违约处罚措施.......................................................................................................................... 39 4.9. 安全、文明施工目标 ............................................................................................................. 40 4.10. 安全、文明施工管理机构: ............................................................................................... 40 4.11. 各级人员安全生产职责 ....................................................................................................... 40 4.12. 安全生产实施措施 ............................................................................................................... 42 4.13. 管理措施 . ............................................................................................................................... 43 4.14. 技术安全措施 ....................................................................................................................... 44
4.15. 夏季高温时期安全施工措施 ............................................................................................... 44 5. 企业使用劳务工工资发放到位的保证措施 ..................................................................................... 44
5.1. 劳务工工资发放到位承诺 ..................................................................................................... 44
5.2. 劳务工工资发放到位保证措施
-. 规模
一、工程概况
在主湖泊(L10)南部设计一座土工膜斜墙土石坝,做为其形成湖泊的挡水建筑物。坝顶长为893m ,坝顶宽为10m ,上下游坝坡均为1:5,最大坝高为12.7m 。湖泊总库容570万 m 3。
根据《水利水电工程等级划分及洪水标准》(SL 252-2000),按总库容划分,碾压式土石坝工程规模属小(1)型,工程等别为IV 等。
为了景观设计要求,坝轴线为非直线,根据《碾压式土石坝设计规范》(SL 274-2001)规定,设计地震烈度在VII 度以下时,坝轴线可选用非直线,故本阶段坝轴线设计成弧线。
1. 说明简述
2.1、坝体布置
土石坝位于主湖泊(L10)南部,坝顶长为893m ,为土工膜斜墙土石坝。坝轴线控制拐点坐标见设计图纸图号JLH.S-BG-01。
2.2、坝顶高程及坝顶结构
坝顶高程为341.50m ,最大坝高为13.2m ,坝顶主要宽度为10m ,坝顶设有观景平台,观景平台控制拐点坐标见设计图纸图号JLH.S-BG-01。
坝顶不设防浪墙,坝顶路面结构及护栏由景观统一设计。大坝两端与园区道路相接,结合部位处理见其他部分。
2.3、坝坡及护坡
上下游坝坡均为1:5,上游坝坡采用干砌块石护坡,护坡厚0.3m 。下游坝坡形式由景
观统一设计。
2.4、坝体结构
坝体自上游至下游依次为:300mm 厚块石护坡→500mm 厚砂砾料→50mm 厚细砂垫层→两布一膜→50mm 厚细砂垫层→Ⅰ区坝壳砂砾料→Ⅱ区利用料→贴坡排水体。
Ⅰ区与Ⅱ区填筑分界线设丙纶针刺无纺布一道,单位面积质量200g/m2,沿1:2折坡点向上铺设5m 。
2.5、基础防渗
大坝沿上游坝脚设单排帷幕,帷幕灌浆孔距2m ,帷幕灌浆深度达到q ≤5Lu 的埋深界线。灌浆孔顶部设2.0³0.8m (宽³厚)的砼盖板,坝体防渗土工膜通过5cm 宽扁钢、橡胶片用膨胀螺栓与砼盖板连接,使坝体与坝基防渗形成封闭整体。
砼盖板上回填1.5m 厚的粘土,粘土可采用库区开挖的泥岩。
2.6、基础处理
根据地质条件,坝断面范围内淤泥和腐植土等须全部清除干净,坝基清基至强风化下限基岩上,在坝基开挖时需预留30~50cm 厚的保护层,清基完成应尽快填筑砂砾料。以保证坝基不被快速风化。
坝壳建基面上有碍坝体填筑施工(有碍碾压机具行进到位或影响压实效果等)的陡坎、反坡、尖凸岩体及岩坎均应进行清理和削坡整治,使建基面大致平顺。
2. 主要工程量
本技术要求主要内容为坝体填筑工程、防渗土工膜工程、砌体工程、盖板砼浇筑工程、帷幕灌浆工程及土石方开挖工程。
主要工程量如下:
二、施工组织计划
1.项目管理网络
根据新疆****市金龙湖湖体工程 主湖泊(L10)大坝特点,我单位建立以项目经理为首的项目经理部,全权组织施工生产诸要素,对工程项目的工期、质量、安全、成本、合同等进行高效率、有计划的组织协调和管理。项目部下设质量办、技术办、材料设备供应办、经营办、HSE 和环境管理办公室、试验室、资料室、综合办等项目职能办公室。
1.1. 各职能办公室组成:
1. 生产技术办:设生产负责人、土建技术员、安装技术员、机械设备管理员、测量员
等。
2. 质量安全办:设质量员、调度员等。 3. 材料办:物资设备采购员、仓库管理员等。
4. 计划经营办:设计划统计员、预算员、合同管理员、会计、出纳等。 5. 综合办:食堂管理员、卫生员、保卫员等。 6. 资料室:资料员 7. 试验室:试验员
1.2. 项目管理组织机构
1.3. 项目质量管理网络
1.4. 项目安全管理网络
1.5. 项
1.6. 工程机械设备组织
1.6.1.
机械设备的管理与调配
本工程投入的机械设备均采用租赁为主,公司的机械设备为辅,由项目经理部统一指挥、调配使用,其中阶段性及加工性机械随工程进度情况逐步进出场;帷幕灌浆调用专业施工队进行施工。
1.6.2. 施工机械的合理配置
1.6.2.1. 土方施工机械的选择,本工程土方开挖及回填采用:反铲挖掘机、装载机、自
卸车、压路机、平地机、撒水车、打夯机械等。
1.6.2.2. 垂直运输机械选择,本工程砼均采用泵车输送。
1.7. 施工机械设备配置
施工主要机械设备表
1.8. 劳动力计划表
1.9. 施工总平面布置
工程位于****城区东南郊,东至东环路,南至石化大道,西、北至****河,地理坐标为北纬45°35′56″,东经84°54′54.9″,场地现状为戈壁滩, 施工队临时设施均设置在项目总部的后面,见施工总平面图。
1.10. 施工区域划分
本工程由于工期紧,工作面较大,为加快施工进度分为2个作业区,K0+00至K0+550为1个施工作业区,K0+550至K0+893为1个施工作业区. 每个作业区域从末尾两端同时施工作业.
1.11. 项目部及临舍布置
经过对本工程施工区域和周边的勘查、分析结果;为了解决项目办公及施工人员用水、用电、生活等临时设施均设置项目总部的后面,见施工总平面图
(其布置相见 “项目部平面布置图”)。
1.12. 施工道路
施工道路及施工临施所需的通行路面由施工单位自行修筑临时道路,以满足生产和生的需要。
1.13. 施工用水用电概况
1.13.1施工用水
施工临时用水方案经业主及监理批准后,已到供水部门办理了相关接入手续,按照临时用水方案接入.
1.13.2施工用电
施工临时用电(高压、低压)方案经业主及监理批准后,已到供水部门办理了相关接入手续,按照临时用电方案接入.
2. 工程进度计划及工期保证措施
2.1. 工程施工计划
详:施进度计划表
按照工程实际情况及业主要求,本工程于2014年8月3日开工,2014年10月15日竣工;为了加快施工进度每天必须施工作业20小时以上,分班作业。我方根据工程特点制定了工程完工的一个框架目标:
土石方开挖:2014.6.3至2014.6.20
大坝土方回填碾压:2014.6.20至2014.9.10 砼盖板:2014.6.20至2014.9.5 帷幕灌浆 :2014.6.28至2014.9.15 上游块石护坡:2014.9.25至2014.8.10 贴坡排水及排水沟 :2014.9.25至2014.8.10
2.2. 工期保证措施
2.2.1、增加机械设备.
2.2.2、施工施工作业人员及施工管理人员. 2.2.3、增加作业时间.
2.2.4、租赁设备采用现金结算方式,采用月结或日结方式.
2.2.5、准备大量资金,以保障机械设备的油料及施工人员的生活及办公需求.
2.3. 组织管理措施
4.2.1.1 将该工程列为公司的重点工程,从机械、设备、技术人员、劳动力、材料、资金等方面给以优先保证。
4.2.1.2 严格按照项目法管理,配备强有力的项目经理部人员,建立完善的管理体系,将进度计划分解到各部门,层层签订承包合同,责任落实到人。制定明确的工期奖罚制度,
使效益、分配与质量、安全、进度挂钩,激发职工的生产积极性。
4.2.1.3 按施工组织设计投入足够的人力、物力、财力,满足进度要求。
4.2.1.4 建立奖罚制度:对将工期提前的班组,给予一定的经济奖励;对将工期拖延的施工班组进行处罚或更换施工班组,做到工期与经济效益挂钩。
4.2.1.5 配合业主做好前期准备工作,工期保证从工程开工初期抓起。
4.2.1.6 在取得业主、监理、设计单位的支持下,积极推广新技术、新工艺,加快施工进度。
4.2.1.7 加强质量检查工作,做到隐蔽工程验收一次通过,尽量不要返工和返修,不因质量方面的原因而影响工期。
4.2.1.8 对进度、劳力、材料、投资等方面的信息进行信息化动态管理,以科学为依据,运用统筹方法、网络技术合理配置资源,优化、深化施工组织。
2.4. 技术管理上的保证措施
4.2.2.1 根据设计图纸、地质勘测报告和现场情况,编制周密、科学的施工组织设计,合理安排各主要施工工序,在确保关键线路工程的同时有效地组织均衡生产,提高效率,确保整个工程的施工进度。
4.2.2.2 加强施工过程中的计划管理及进度控制,根据批准后的施工组织、总工期、关键工期的要求,编制周密细致的月、旬、周的施工生产计划,以日保周,以周保旬,以旬保月,强调当日计划当日完成。同时,还要对照实际进度、客观条件,对计划进行分析、调整,不断完善管理,从而确保工程进度。
4.2.2.3 施工机具按施工组织计划按时进场,并配备足够的易损件和消耗材料,制定机械操作规程,严格管理,配备机修小组对机械进行保养和维修。同时在现场配备发电机组,以应付停电和高峰期供电所需。在必要时,要及时加大设备的投入。
4.2.2.4 根据施工安排,制订合理的用款计划和材料供应计划,避免停工待料的现象发生。
4.2.2.5 定期对工人进行技术培训,做好新进场工人和新工序工前的技术交底,提高工人的素质和技术水平,加快施工进度。
3. 主要项目施工技术方案
3.1. 施工测量
对设计提供的施工区各级控制网、坐标点、水准点进行对比测量复核,确保准确无误后,根据这些控制网点建立施工测量控制系统。各控制点选点应选在视野宽、地势高、不