塔吊拆除方案

目 录

1、编制依据 ........................................................................................................... 2 2、工程概况 ........................................................................................................... 2 3、塔吊选型及位置 ................................................................................................ 6 3.1塔吊安装安全距离及验收要求 .......................................................................... 6 3.2 塔吊安装位置:见附图:塔吊平面布置、位置图 ............................................. 6 3.3塔吊型号的选择 ................................................................................................ 6 3.4塔吊吊装范围 ................................................................................................... 7 3.5立塔高度计算 ................................................................................................... 7 3.6起吊的数量、重量、吊装能力核算 ................................................................... 8 3.7塔吊布置及吊运情况......................................................................................... 9 3.8附着加固位置 ................................................................................................... 9 3.9有效长度计算 ................................................................................................. 10 3.10地勘报告 ...................................................................................................... 10 3.11地基施工及安装防护..................................................................................... 10 3.12塔吊防雷设施 ............................................................................................... 13 3.13塔吊拆除(安、拆具体见出租单位方案) ......................................................... 13 4、施工准备 ......................................................................................................... 13 4.1.总包单位职责及准备 ...................................................................................... 13 4.2分包单位职责及准备....................................................................................... 13 5、施工顺序和方法 .............................................................................................. 14 5.1施工顺序 ........................................................................................................ 14 5.2施工方法 ........................................................................................................ 14 5.3塔吊的安装、使用与拆除(具体详见出租公司方案) ......................................... 14 6、使用安全管理.................................................................................................. 14 6.1管理措施 ........................................................................................................ 14 6.2环境保护和文明施工....................................................................................... 15 7.附图及附件: .................................................................................................... 15

1、编制依据

1.1施工图纸和施工组织设计

1.1.1《朝阳区将台乡613东地块11#、12#、14#、15#及3#地下车库施工图纸》 1.1.2《朝阳区将台乡613东地块11#、12#、14#、15#及3#地下车库施工织总设计》

1.3 所选型号的塔式起重机使用说明书 1.4工程现场勘察资料

2、工程概况

2.1工程位置

工程11#、12#、14#、15#楼及3#地下车库东段位于朝阳区将台乡,东临东坝路、西侧为相临10#、13#楼、北临将台北岗北路、南临东八间房路。

2.3建筑概况 2.3.1建筑设计概况 建筑设计概况如下表

2.5周围环境

2.5.1本工程属于与车库连体楼座,本标段内含车库、住宅、人防等,总建筑面积129600m2,其中主楼97637㎡,车库31963㎡,主楼有4栋楼,为11#、12#、14#、15#楼。场地较大,属于群体工程,塔吊安装没有覆盖周边高压线,只有部分覆盖施工场地临建设施,覆盖临建设施采用架子管搭设,采用脚手板搭设防护棚双层防护。 2.5.2 周围交叉道路多,本工程属于群塔作业。

3、塔吊选型及位置

3.1塔吊安装安全距离及验收要求

安全规定塔吊大臂垂直(大臂与大臂)距离不小于6米,水平距离(塔臂端头与塔身、建筑物等)不小于2米。

3.2 塔吊安装位置:见附图:塔吊平面布置、位置图

3.3塔吊型号的选择

3.3.1针对本工程特点及工期质量要求,选择能减轻劳动强度、提高生产率、加快工程进度、保证施工质量、适用性及多用性兼顾的施工机械,做到技术先进性与经济合理性的统一。尽可能充分发挥施工机械效率和利用程度。

3.3.2根据本工程特点、塔吊吊次、塔吊作用范围及塔吊拆除要求,选择FO23B型塔吊1台,ST60/15型塔吊2台,QTZ145(6018)型塔吊1台。有关参数如下: 3.3.2.1供电:380V-50HZ,防雷接地2组4欧姆,电源110KVA。

3.3.2.2塔身截面:FO23B2.0m×2.0m

,ST60/15为2.0m×2.0m,QTZ145(6018)2.0m×2.0m。

3.4塔吊吊装范围

3.4.1 11#楼塔负责11#座楼及车库的钢筋、模板、周转材料、部分砼及屋面材料的吊装

3.4.2 12#楼塔负责12#座楼及车库的钢筋、模板、周转材料、部分砼及屋面材料的吊装;

3.4.3 14#楼塔负责14#座楼及车库的钢筋、模板、周转材料、部分砼及屋面材料的吊装;

3.4.4 15#楼塔负责15#座楼及车库的钢筋、模板、周转材料、部分砼及屋面材料的吊装。

3.5立塔高度计算

3.5.1 按楼最高处+机房层+楼底板相对标高+吊装预留安全高度取6~12 m。 总立塔高度:从基础算起(根据塔节高调整最后高度)( FO23B塔:节/3.0m; ST60/15塔:节/3.0m,QTZ145(6018)节/3.0m;塔吊基础埋节固定,上部留1.5米)

3.5.2建委规定塔吊垂直安全距离(塔臂与塔臂)均为6米,水平安全距离(塔端头到塔身)均为2米以上,考虑群塔作业为保证相邻塔的塔臂高差在6米以上,确定正负零以上立塔高度及安全距离。

注:第二次顶升塔时,要由生产经理牵头协商后,依据第一次顶升高度为基数,在保证各塔安全距离的情况下在进行顶升。具体详见《群塔作业施工方案》。

3.6起吊的数量、重量、吊装能力核算

3.6.1吊装范围计算 (布料机每台1.6T。)

由上表可知,该4台塔吊重均满足要求。

3.7塔吊布置及吊运情况

3.7.1塔吊布置:根据整体楼座及车库考虑施工时要全覆盖,尽量不留盲区,为此11#楼60米塔吊布置在楼南侧,12#楼塔吊55米布置在楼南侧,14#楼55米塔吊布置在楼北侧,15#楼50米塔吊布置在楼北侧,各塔均能满足施工要求。 3.7.2吊装能力和吊次核算

3.7.2.1根据本工程的实际情况来看,地下结构施工周期相对较长,从±0.000以上起才能够组织正常的每栋楼分段4个流水施工,故按±0.000以上的吊次进行核算。 3.7.2.2 按11#楼塔吊计算,台班吊次计算(按最高计算):起吊高度×2÷速度(50m/min)=109.5×2÷50=4.38min/次,加上辅助操作时间按每小时8吊计算,每台班吊次为60吊。

3.7.2.3本工程每层大钢模墙体模板、木方、架子管等约需150吊次:150÷60=2.5台班。

3.7.2.4大钢模模板:每层约1500㎡,每吊按75㎡×1吊=75计算需20吊次,每台班按60吊次计算共需0.33个台班。

3.7.2.5顶板支撑每层约65t,每吊按1.5计算需65÷2=43吊次,每台班按60吊次共需0.72个台班。

3.7.2.6每层钢筋约40t,每吊按1.5t计算需26吊次,每台班按60吊次共需0.43个台班。

3.7.2.7每层挑架子架子管等15吊次,每台班按60吊次共需0.25个台班。 根据以上计算每层合计所需塔吊台班3.9个,小于每层施工作业时间7日历天(每天按2个台班)14个台班。

3.7.2.8经计算本塔吊的吊次满足施工需要,但根据施工现场实际情况,因人工装运速度、群塔作业时间相互影响等可以随时调整作业时间来弥补塔吊吊次,更好的满足施工要求。

3.8附着加固位置

3.8.1该工程主楼座各塔附着11#、12#楼3次,14#、15#楼2次。

3.9有效长度计算

3.10.1四个塔因全部在车库内安塔,根据地勘报告塔地基地耐力比较均匀,4个塔均立在车库天然地基上,天然地基承载力130KPa,已满足出租设备厂家要求地基不小于130Kpa的要求,为此塔吊基础可不做其它处理已满足要求。 3.10.2塔吊公司具体设计要求:1台塔吊基础(QTZ145(6018))为6.5×6.5m×高1.5m,1台塔吊基础(FO23B)为6.5×6.5m×高1.5m,2台(ST60/15)为6.5×6.5m×高1.5m,塔吊基础要求基础地耐力不小于130KPa,根据地勘报告本天然地基可满足塔吊地基承载力要求,塔吊基础不需要加强处理。 3.10.3塔基处理

3.10.3.1因塔吊基础范围为天然地基基础,塔基基础挖到底标高后,需要做钎探。

3.11地基施工及安装防护

3.11.1塔吊基础施工

3.11.1.1施工要求:要求在车库基槽验收合格后在进行塔基基础施工,因设计要求塔吊基础需埋入基础底板下。塔吊基础制作方法已于设计、塔吊出租公司沟通同意此做法,为此在车库正式底板施工前要做好塔吊基础,为正式基础底板施工创造条件,待基础正式施工之前,塔基砼强度达到要求立即安装。 3.11.1.2因设计要求塔吊基础需埋入基础底板下,塔吊基础钢筋混凝土等防水处理同车库基础。

3.11.1.3塔身防水做法

(1) 塔节防水处理:因该工程4台塔吊均安装在车库范围内,塔吊基础在车库底板下面制作,为避免塔吊基础部位防水出现缺陷,加强防水效果,在此处采用以下措施:

1).在塔吊基础下做3+4mmSBS聚酯胎改性沥青防水卷材(做法同同车库基础防水)。塔基基础防水与车库基础防水相连接形成一个整体防水。

2)在车库基础塔吊每个节中间焊接400mm宽3mm厚止水钢板加强了防水。

(2)塔身顶板开洞处理:因该工程四个塔均穿过各层楼板,当塔吊标准节穿过结构顶板时,顶板钢筋不截断,绕过或穿过标准节。顶板上标准节位置预留

2500mm*2500mm施工洞(地下部分在补浇砼工时要在楼板开洞四周粘钉30*30*25厚的橡胶止水条),待拆塔后使用比原顶板提高一个等级的(地下部分楼板浇筑C40P6抗渗砼)混凝土浇筑,若拆塔时需要截断部分钢筋,则截断的钢筋使用电弧帮条焊方法焊接,满足施工工艺及规范要求。本工程此类情况共涉及4处,共计8块顶板。

轴线轴线

塔吊 标准

塔吊标准节

4+3厚SBS聚酯胎改性防水卷材

100厚C15垫层

3.11.1.4塔吊基础施工

(1)11#、12#、14#、15#塔基施工:在塔基位置下挖6.50×6.50×1.5m(12.40+1.50+0.15至-13.90m),然后做砼垫层。垫层达到强度后砌筑240厚砖胎模并内侧抹灰,后做4+3mmSBS改性沥青防水并做50mm厚C20细石混凝土防水保护层,开始绑钢筋、埋塔节、浇C35P8砼,塔基基础高度1.50m。见下图:

3.11.2塔吊安装及安全防护

3.11.2.1塔吊进场安装:塔吊安装前必须选好进场路线,进场安塔从南侧大门进出,由拖车运至塔边,由50T汽车吊进行安装,为塔基安全和便于施工,塔吊固定采用埋塔节方式。安装时塔基砼强度必须通过实验室试件确定,达到设计强度后再进行安装。

3.11.2.2安塔时安全防护:安装塔吊时要做好安全技术交底,用彩带拉临时警戒线,由塔吊公司派人看护,项目部派安全员现场监管,真正做好周边安全防护。

3.12塔吊防雷设施

3.12.1防雷材料:镀锌扁铁40*4mm,镀锌钢钎Ф20长2.5m,每个塔三根。

3.12.2埋设方法:从塔基下引入外墙外侧,结构施工时与外墙钢筋焊接,另一侧与埋塔节焊接,接地电阻不小于4Ώ。

3.12.3防雷接地埋设时,要由电工工长配合埋设施工。

3.13塔吊拆除(安、拆具体见出租单位方案)

3.13.1 FO23B塔,小臂长11.88m,大臂最长50m,15#楼塔拆除时大臂在东、小臂在西为一字形;

3.13.2 ST60/15塔,小臂长14.4m,大臂最长55m,12#楼、14#楼塔拆除时大臂在东、小臂在西为一字形;

3.13.3 QTZ145(6018)塔,小臂长14.4m,大臂最长60m,11#楼塔拆除时大臂在东、小臂在西为一字形;

4、施工准备

4.1.总包单位职责及准备

4.1.1技术准备:项目部技术管理人员认真熟悉塔吊说明书,编制安全使用及拆除方案,确定好塔吊安装位置等。

4.1.2总包职责:

(1)项目部安全组要与分包单位签订塔吊安装、拆除安全协议书,工程组做好安全技术交底,塔吊安装、拆除时安全员要亲临现场全过程监督检查。

(2)按合同要求总包单位提供道路、电源引至配电箱,按出租厂家提供图纸浇筑砼塔基、现场防护、日常安全教育、培训、安全监督等。

(3)总包负责塔基制作,各塔基留置3组试块、一组标养、二组同条件养护、一组抗渗,塔基砼按塔吊使用说明书中技术指标要求为C35P8。

(4)塔基在砼达到75%既总包以以书面形式移交分包安装,安装时塔基表面平整度要求小于1/1000。

4.2分包单位职责及准备

4.2.1塔吊出租单位应配备足够的塔吊安装工,起重工等,并持证上岗。

4.2.2分包单位负责设备、安装、拆除、日常使用过程中的维修、保养、按要求及时提供有效合格证书,检测报告,验收备案手续等事宜。

4.2.3分包单位按合同要求向总包单位提供塔吊合格证明和有效期内的检测报告和安装调试,拆除人员上岗证、作业证;编制完整审批手续齐全安装、拆除方案和安全

作业交底,安装前分包单位要提前进场与总包生产经理协商具体安装时间,并与安全组签订安全协议书。

5、施工顺序和方法

5.1施工顺序

定位放线→土方施工→钎探(地基处理)→垫层施工→放线复测→砌筑砖胎模→防水施工→防水保护层施工→施塔吊基础线→绑底铁钢筋→放塔节→钢筋绑扎→砼浇筑。

5.2施工方法

由测量员按控制网的轴线,确定塔基位置;采用反铲式挖掘机开挖至塔基及垫层底标高上200高停止,留20cm由人工清理,塔基做好钎探及记录,报监理验收认可,然后各塔基均采用10cm厚C15砼垫层;垫层达到一定强度后进行砌筑砖胎模并做防水及其保护层施工。再次放线复测合格后,先放底层钢筋和垫块,然后安放塔节固定,按设计图配双层双向钢筋。经监理验收合格后,浇筑C35P8砼,做到及时养护。

5.3塔吊的安装、使用与拆除(具体详见出租公司方案)

5.3.1主要施工顺序:塔吊进场检验---安装---验收交接---使用---验收交接---拆除---清点退场。

5.3.2施工方法:安装完成后在使用前,由安拆单位提供合格的验收计划,并办理交接手续,经有关方同意后方可使用。

5.3.3安全、拆除管理

安拆过程中分包必须认真严格执行自编方案和规程要求,按协议完成各项管理和义务。安拆全过程施工分包单位安全负责人必须在现场指挥,并监督其他作业人员;分包方应及时提供相关资料验收手续。

5.3.4总包管理:

在安拆塔吊前由总包对分包厂家进行安全交底,施工时总包单位派安全员跟班进行巡视和监督,并随时检查、人、证是否对应有效;检查方案中技术安全措施是否到位。

6、使用安全管理

6.1管理措施

6.1.1制定日常检查计划,制定培训计划、制定现场安全应急预案、建立建全安全组织、配备人员、采取定期和不定期对人员设备进行检查,有安全员做好安全培训和安全技术交底,安全员日常巡视时发出问题应及时处理;发现不安全隐患和违章作业现象及时纠正。

6.1.2严格执行群塔作业方案,坚持“动塔让静塔”前臂让后臂、低塔让高塔、空载让重载的“原则,加装限位,严禁私自拆除。

6.2环境保护和文明施工

6.2.1塔吊坑边加高1.5m高架子管防护,外挂密闭式安全网。

6.2.2所有扣件、油托、碗扣等小件吊运采用专用箱吊运,以防坠落伤人。

6.2.3吊运钢筋一律放置在梁墙上口,避免钢筋太重,压裂楼板现象发生。

6.2.4吊运大模板应按顺序起吊,避免非正常吊运产生噪声和撞击声。

6.2.5吊运外挂架时,应仔细清理架子上物品,防止垃圾坠落,扬起灰尘。

6.2.6如夜间施工,要按北京市要求办理夜施证,从22.00至早晨6.00停止施工,以免影响周围居民休息。

6.2.7现场设安全警戒线,悬挂安全标志。

7.附图及附件:

7.1塔吊整体平面布置图(详见附图:塔吊基础平面布置图)

7.2各塔基础位置图

7.3塔基设计及地基承载力验算

塔吊整体式混凝土基础的几何尺寸及配筋由塔吊租赁公司提供,验算如下: 塔吊基础计算:

ST60/15、QTZ125(6517B)、F0/23B属于125吨·米系列,水平臂架、载重小车变幅型、上回转自升式塔机;

砼基础设计尺寸:6.5×6.5×1.5

Fv=作用在基础上的垂直载荷=塔吊总重量+最大载荷重量=1068KN +100 KN=1168 KN

Fg=砼基础重力=6.5×6.5×1. 5×2.4=1521KN 3 砼密度=2.4t/m

7.4附件:

7.4.1.出租单位塔吊安、拆方案;

7.42.塔吊出租单位资质;

7.4.3.塔吊出租单位安全许可证;

7.4.4.塔吊出租单位安装人员上岗证;

7.4.5.塔吊出租单位安全协议;

7.4.6.塔吊使用说明书。

目 录

1、编制依据 ........................................................................................................... 2 2、工程概况 ........................................................................................................... 2 3、塔吊选型及位置 ................................................................................................ 6 3.1塔吊安装安全距离及验收要求 .......................................................................... 6 3.2 塔吊安装位置:见附图:塔吊平面布置、位置图 ............................................. 6 3.3塔吊型号的选择 ................................................................................................ 6 3.4塔吊吊装范围 ................................................................................................... 7 3.5立塔高度计算 ................................................................................................... 7 3.6起吊的数量、重量、吊装能力核算 ................................................................... 8 3.7塔吊布置及吊运情况......................................................................................... 9 3.8附着加固位置 ................................................................................................... 9 3.9有效长度计算 ................................................................................................. 10 3.10地勘报告 ...................................................................................................... 10 3.11地基施工及安装防护..................................................................................... 10 3.12塔吊防雷设施 ............................................................................................... 13 3.13塔吊拆除(安、拆具体见出租单位方案) ......................................................... 13 4、施工准备 ......................................................................................................... 13 4.1.总包单位职责及准备 ...................................................................................... 13 4.2分包单位职责及准备....................................................................................... 13 5、施工顺序和方法 .............................................................................................. 14 5.1施工顺序 ........................................................................................................ 14 5.2施工方法 ........................................................................................................ 14 5.3塔吊的安装、使用与拆除(具体详见出租公司方案) ......................................... 14 6、使用安全管理.................................................................................................. 14 6.1管理措施 ........................................................................................................ 14 6.2环境保护和文明施工....................................................................................... 15 7.附图及附件: .................................................................................................... 15

1、编制依据

1.1施工图纸和施工组织设计

1.1.1《朝阳区将台乡613东地块11#、12#、14#、15#及3#地下车库施工图纸》 1.1.2《朝阳区将台乡613东地块11#、12#、14#、15#及3#地下车库施工织总设计》

1.3 所选型号的塔式起重机使用说明书 1.4工程现场勘察资料

2、工程概况

2.1工程位置

工程11#、12#、14#、15#楼及3#地下车库东段位于朝阳区将台乡,东临东坝路、西侧为相临10#、13#楼、北临将台北岗北路、南临东八间房路。

2.3建筑概况 2.3.1建筑设计概况 建筑设计概况如下表

2.5周围环境

2.5.1本工程属于与车库连体楼座,本标段内含车库、住宅、人防等,总建筑面积129600m2,其中主楼97637㎡,车库31963㎡,主楼有4栋楼,为11#、12#、14#、15#楼。场地较大,属于群体工程,塔吊安装没有覆盖周边高压线,只有部分覆盖施工场地临建设施,覆盖临建设施采用架子管搭设,采用脚手板搭设防护棚双层防护。 2.5.2 周围交叉道路多,本工程属于群塔作业。

3、塔吊选型及位置

3.1塔吊安装安全距离及验收要求

安全规定塔吊大臂垂直(大臂与大臂)距离不小于6米,水平距离(塔臂端头与塔身、建筑物等)不小于2米。

3.2 塔吊安装位置:见附图:塔吊平面布置、位置图

3.3塔吊型号的选择

3.3.1针对本工程特点及工期质量要求,选择能减轻劳动强度、提高生产率、加快工程进度、保证施工质量、适用性及多用性兼顾的施工机械,做到技术先进性与经济合理性的统一。尽可能充分发挥施工机械效率和利用程度。

3.3.2根据本工程特点、塔吊吊次、塔吊作用范围及塔吊拆除要求,选择FO23B型塔吊1台,ST60/15型塔吊2台,QTZ145(6018)型塔吊1台。有关参数如下: 3.3.2.1供电:380V-50HZ,防雷接地2组4欧姆,电源110KVA。

3.3.2.2塔身截面:FO23B2.0m×2.0m

,ST60/15为2.0m×2.0m,QTZ145(6018)2.0m×2.0m。

3.4塔吊吊装范围

3.4.1 11#楼塔负责11#座楼及车库的钢筋、模板、周转材料、部分砼及屋面材料的吊装

3.4.2 12#楼塔负责12#座楼及车库的钢筋、模板、周转材料、部分砼及屋面材料的吊装;

3.4.3 14#楼塔负责14#座楼及车库的钢筋、模板、周转材料、部分砼及屋面材料的吊装;

3.4.4 15#楼塔负责15#座楼及车库的钢筋、模板、周转材料、部分砼及屋面材料的吊装。

3.5立塔高度计算

3.5.1 按楼最高处+机房层+楼底板相对标高+吊装预留安全高度取6~12 m。 总立塔高度:从基础算起(根据塔节高调整最后高度)( FO23B塔:节/3.0m; ST60/15塔:节/3.0m,QTZ145(6018)节/3.0m;塔吊基础埋节固定,上部留1.5米)

3.5.2建委规定塔吊垂直安全距离(塔臂与塔臂)均为6米,水平安全距离(塔端头到塔身)均为2米以上,考虑群塔作业为保证相邻塔的塔臂高差在6米以上,确定正负零以上立塔高度及安全距离。

注:第二次顶升塔时,要由生产经理牵头协商后,依据第一次顶升高度为基数,在保证各塔安全距离的情况下在进行顶升。具体详见《群塔作业施工方案》。

3.6起吊的数量、重量、吊装能力核算

3.6.1吊装范围计算 (布料机每台1.6T。)

由上表可知,该4台塔吊重均满足要求。

3.7塔吊布置及吊运情况

3.7.1塔吊布置:根据整体楼座及车库考虑施工时要全覆盖,尽量不留盲区,为此11#楼60米塔吊布置在楼南侧,12#楼塔吊55米布置在楼南侧,14#楼55米塔吊布置在楼北侧,15#楼50米塔吊布置在楼北侧,各塔均能满足施工要求。 3.7.2吊装能力和吊次核算

3.7.2.1根据本工程的实际情况来看,地下结构施工周期相对较长,从±0.000以上起才能够组织正常的每栋楼分段4个流水施工,故按±0.000以上的吊次进行核算。 3.7.2.2 按11#楼塔吊计算,台班吊次计算(按最高计算):起吊高度×2÷速度(50m/min)=109.5×2÷50=4.38min/次,加上辅助操作时间按每小时8吊计算,每台班吊次为60吊。

3.7.2.3本工程每层大钢模墙体模板、木方、架子管等约需150吊次:150÷60=2.5台班。

3.7.2.4大钢模模板:每层约1500㎡,每吊按75㎡×1吊=75计算需20吊次,每台班按60吊次计算共需0.33个台班。

3.7.2.5顶板支撑每层约65t,每吊按1.5计算需65÷2=43吊次,每台班按60吊次共需0.72个台班。

3.7.2.6每层钢筋约40t,每吊按1.5t计算需26吊次,每台班按60吊次共需0.43个台班。

3.7.2.7每层挑架子架子管等15吊次,每台班按60吊次共需0.25个台班。 根据以上计算每层合计所需塔吊台班3.9个,小于每层施工作业时间7日历天(每天按2个台班)14个台班。

3.7.2.8经计算本塔吊的吊次满足施工需要,但根据施工现场实际情况,因人工装运速度、群塔作业时间相互影响等可以随时调整作业时间来弥补塔吊吊次,更好的满足施工要求。

3.8附着加固位置

3.8.1该工程主楼座各塔附着11#、12#楼3次,14#、15#楼2次。

3.9有效长度计算

3.10.1四个塔因全部在车库内安塔,根据地勘报告塔地基地耐力比较均匀,4个塔均立在车库天然地基上,天然地基承载力130KPa,已满足出租设备厂家要求地基不小于130Kpa的要求,为此塔吊基础可不做其它处理已满足要求。 3.10.2塔吊公司具体设计要求:1台塔吊基础(QTZ145(6018))为6.5×6.5m×高1.5m,1台塔吊基础(FO23B)为6.5×6.5m×高1.5m,2台(ST60/15)为6.5×6.5m×高1.5m,塔吊基础要求基础地耐力不小于130KPa,根据地勘报告本天然地基可满足塔吊地基承载力要求,塔吊基础不需要加强处理。 3.10.3塔基处理

3.10.3.1因塔吊基础范围为天然地基基础,塔基基础挖到底标高后,需要做钎探。

3.11地基施工及安装防护

3.11.1塔吊基础施工

3.11.1.1施工要求:要求在车库基槽验收合格后在进行塔基基础施工,因设计要求塔吊基础需埋入基础底板下。塔吊基础制作方法已于设计、塔吊出租公司沟通同意此做法,为此在车库正式底板施工前要做好塔吊基础,为正式基础底板施工创造条件,待基础正式施工之前,塔基砼强度达到要求立即安装。 3.11.1.2因设计要求塔吊基础需埋入基础底板下,塔吊基础钢筋混凝土等防水处理同车库基础。

3.11.1.3塔身防水做法

(1) 塔节防水处理:因该工程4台塔吊均安装在车库范围内,塔吊基础在车库底板下面制作,为避免塔吊基础部位防水出现缺陷,加强防水效果,在此处采用以下措施:

1).在塔吊基础下做3+4mmSBS聚酯胎改性沥青防水卷材(做法同同车库基础防水)。塔基基础防水与车库基础防水相连接形成一个整体防水。

2)在车库基础塔吊每个节中间焊接400mm宽3mm厚止水钢板加强了防水。

(2)塔身顶板开洞处理:因该工程四个塔均穿过各层楼板,当塔吊标准节穿过结构顶板时,顶板钢筋不截断,绕过或穿过标准节。顶板上标准节位置预留

2500mm*2500mm施工洞(地下部分在补浇砼工时要在楼板开洞四周粘钉30*30*25厚的橡胶止水条),待拆塔后使用比原顶板提高一个等级的(地下部分楼板浇筑C40P6抗渗砼)混凝土浇筑,若拆塔时需要截断部分钢筋,则截断的钢筋使用电弧帮条焊方法焊接,满足施工工艺及规范要求。本工程此类情况共涉及4处,共计8块顶板。

轴线轴线

塔吊 标准

塔吊标准节

4+3厚SBS聚酯胎改性防水卷材

100厚C15垫层

3.11.1.4塔吊基础施工

(1)11#、12#、14#、15#塔基施工:在塔基位置下挖6.50×6.50×1.5m(12.40+1.50+0.15至-13.90m),然后做砼垫层。垫层达到强度后砌筑240厚砖胎模并内侧抹灰,后做4+3mmSBS改性沥青防水并做50mm厚C20细石混凝土防水保护层,开始绑钢筋、埋塔节、浇C35P8砼,塔基基础高度1.50m。见下图:

3.11.2塔吊安装及安全防护

3.11.2.1塔吊进场安装:塔吊安装前必须选好进场路线,进场安塔从南侧大门进出,由拖车运至塔边,由50T汽车吊进行安装,为塔基安全和便于施工,塔吊固定采用埋塔节方式。安装时塔基砼强度必须通过实验室试件确定,达到设计强度后再进行安装。

3.11.2.2安塔时安全防护:安装塔吊时要做好安全技术交底,用彩带拉临时警戒线,由塔吊公司派人看护,项目部派安全员现场监管,真正做好周边安全防护。

3.12塔吊防雷设施

3.12.1防雷材料:镀锌扁铁40*4mm,镀锌钢钎Ф20长2.5m,每个塔三根。

3.12.2埋设方法:从塔基下引入外墙外侧,结构施工时与外墙钢筋焊接,另一侧与埋塔节焊接,接地电阻不小于4Ώ。

3.12.3防雷接地埋设时,要由电工工长配合埋设施工。

3.13塔吊拆除(安、拆具体见出租单位方案)

3.13.1 FO23B塔,小臂长11.88m,大臂最长50m,15#楼塔拆除时大臂在东、小臂在西为一字形;

3.13.2 ST60/15塔,小臂长14.4m,大臂最长55m,12#楼、14#楼塔拆除时大臂在东、小臂在西为一字形;

3.13.3 QTZ145(6018)塔,小臂长14.4m,大臂最长60m,11#楼塔拆除时大臂在东、小臂在西为一字形;

4、施工准备

4.1.总包单位职责及准备

4.1.1技术准备:项目部技术管理人员认真熟悉塔吊说明书,编制安全使用及拆除方案,确定好塔吊安装位置等。

4.1.2总包职责:

(1)项目部安全组要与分包单位签订塔吊安装、拆除安全协议书,工程组做好安全技术交底,塔吊安装、拆除时安全员要亲临现场全过程监督检查。

(2)按合同要求总包单位提供道路、电源引至配电箱,按出租厂家提供图纸浇筑砼塔基、现场防护、日常安全教育、培训、安全监督等。

(3)总包负责塔基制作,各塔基留置3组试块、一组标养、二组同条件养护、一组抗渗,塔基砼按塔吊使用说明书中技术指标要求为C35P8。

(4)塔基在砼达到75%既总包以以书面形式移交分包安装,安装时塔基表面平整度要求小于1/1000。

4.2分包单位职责及准备

4.2.1塔吊出租单位应配备足够的塔吊安装工,起重工等,并持证上岗。

4.2.2分包单位负责设备、安装、拆除、日常使用过程中的维修、保养、按要求及时提供有效合格证书,检测报告,验收备案手续等事宜。

4.2.3分包单位按合同要求向总包单位提供塔吊合格证明和有效期内的检测报告和安装调试,拆除人员上岗证、作业证;编制完整审批手续齐全安装、拆除方案和安全

作业交底,安装前分包单位要提前进场与总包生产经理协商具体安装时间,并与安全组签订安全协议书。

5、施工顺序和方法

5.1施工顺序

定位放线→土方施工→钎探(地基处理)→垫层施工→放线复测→砌筑砖胎模→防水施工→防水保护层施工→施塔吊基础线→绑底铁钢筋→放塔节→钢筋绑扎→砼浇筑。

5.2施工方法

由测量员按控制网的轴线,确定塔基位置;采用反铲式挖掘机开挖至塔基及垫层底标高上200高停止,留20cm由人工清理,塔基做好钎探及记录,报监理验收认可,然后各塔基均采用10cm厚C15砼垫层;垫层达到一定强度后进行砌筑砖胎模并做防水及其保护层施工。再次放线复测合格后,先放底层钢筋和垫块,然后安放塔节固定,按设计图配双层双向钢筋。经监理验收合格后,浇筑C35P8砼,做到及时养护。

5.3塔吊的安装、使用与拆除(具体详见出租公司方案)

5.3.1主要施工顺序:塔吊进场检验---安装---验收交接---使用---验收交接---拆除---清点退场。

5.3.2施工方法:安装完成后在使用前,由安拆单位提供合格的验收计划,并办理交接手续,经有关方同意后方可使用。

5.3.3安全、拆除管理

安拆过程中分包必须认真严格执行自编方案和规程要求,按协议完成各项管理和义务。安拆全过程施工分包单位安全负责人必须在现场指挥,并监督其他作业人员;分包方应及时提供相关资料验收手续。

5.3.4总包管理:

在安拆塔吊前由总包对分包厂家进行安全交底,施工时总包单位派安全员跟班进行巡视和监督,并随时检查、人、证是否对应有效;检查方案中技术安全措施是否到位。

6、使用安全管理

6.1管理措施

6.1.1制定日常检查计划,制定培训计划、制定现场安全应急预案、建立建全安全组织、配备人员、采取定期和不定期对人员设备进行检查,有安全员做好安全培训和安全技术交底,安全员日常巡视时发出问题应及时处理;发现不安全隐患和违章作业现象及时纠正。

6.1.2严格执行群塔作业方案,坚持“动塔让静塔”前臂让后臂、低塔让高塔、空载让重载的“原则,加装限位,严禁私自拆除。

6.2环境保护和文明施工

6.2.1塔吊坑边加高1.5m高架子管防护,外挂密闭式安全网。

6.2.2所有扣件、油托、碗扣等小件吊运采用专用箱吊运,以防坠落伤人。

6.2.3吊运钢筋一律放置在梁墙上口,避免钢筋太重,压裂楼板现象发生。

6.2.4吊运大模板应按顺序起吊,避免非正常吊运产生噪声和撞击声。

6.2.5吊运外挂架时,应仔细清理架子上物品,防止垃圾坠落,扬起灰尘。

6.2.6如夜间施工,要按北京市要求办理夜施证,从22.00至早晨6.00停止施工,以免影响周围居民休息。

6.2.7现场设安全警戒线,悬挂安全标志。

7.附图及附件:

7.1塔吊整体平面布置图(详见附图:塔吊基础平面布置图)

7.2各塔基础位置图

7.3塔基设计及地基承载力验算

塔吊整体式混凝土基础的几何尺寸及配筋由塔吊租赁公司提供,验算如下: 塔吊基础计算:

ST60/15、QTZ125(6517B)、F0/23B属于125吨·米系列,水平臂架、载重小车变幅型、上回转自升式塔机;

砼基础设计尺寸:6.5×6.5×1.5

Fv=作用在基础上的垂直载荷=塔吊总重量+最大载荷重量=1068KN +100 KN=1168 KN

Fg=砼基础重力=6.5×6.5×1. 5×2.4=1521KN 3 砼密度=2.4t/m

7.4附件:

7.4.1.出租单位塔吊安、拆方案;

7.42.塔吊出租单位资质;

7.4.3.塔吊出租单位安全许可证;

7.4.4.塔吊出租单位安装人员上岗证;

7.4.5.塔吊出租单位安全协议;

7.4.6.塔吊使用说明书。


相关文章

  • 4#楼.6#楼塔吊附墙件拆卸方案
  • 4#楼.6#楼塔吊附墙件拆卸方案 一.编制依据 1.塔吊平面布置图 2.4#楼.6#楼建施和结施图 3.<建筑施工扣件式钢管脚手架安全技术规范>JGJ130-2011 4.<建筑施工高处作业安全技术规范>(JGJ80 ...查看


  • 塔吊拆除方案 1
  • 塔吊拆除方案 一.工程概况 淮北闹供水调度中心A1区.A2区6#楼工程,搭设了江苏省南京云龙建筑机械制造有限公司生产的QTZ63自升塔式起重机(以下简称塔吊)壹台,塔吊额定起重力矩为63T.M,安装高度为112M,臂长56M.塔吊安装在东方 ...查看


  • 高空塔吊拆除方案
  • 高空塔吊拆卸专项施工工艺 工程名称:康桥长郡项目部 工程地点:长沙星沙 施工单位: 编制依据:JGJ196-2010«建筑施工塔式起重机安装.使用.拆卸安全技术规程» 编制单位: 编制人: 编制日期: 2013 年 8 月 5 日 审批负责 ...查看


  • 塔吊安拆专项防雷接地方案[科比特防雷厂家]
  • 塔吊安拆专项防雷接地方案 一.工程概况 二.现场布置 本工程共设置 型塔吊 台,分别在 ,具体设置详见总平面布罩图. 三.塔吊的基本性能 型号 起升高度 吊臂幅度 额定起重力矩 QTZ40 独立 29.7m 最大起重量 4t 最大 48m ...查看


  • 各专项方案编制要求
  • 各专项方案编制要求 1.基坑支护.降水工程施工方案 1.1 编制说明及依据 简述安全专项施工方案的编制目的以及方案编制所依据的相关法律.法规.规范性文件.标准.规范及图纸(国标图集).施工组织设计等,及编制依据的版本.编号等.采用电算软件的 ...查看


  • 高层大厦内爬式塔吊施工方案
  • ***大厦二期工程 ZSC800内爬式塔吊 施工方案 **京唐天润建设***大厦工程项目部 目 录 1. 工程概况 .............................................................. ...查看


  • 塔吊安拆方案
  • 达丰技字TD 2013 塔吊安拆施工方案 编 制: 审 核: 审 批: 项目确认: 编制日期:2013/1/20 江苏中建达丰机械租赁有限公司 JIANGSU ZHONGJIAN TATHONG EQUIPMENT RENTAL CO.,L ...查看


  • 塔吊监理细则
  • A.0.4 苏地2015-WG-1号地块(中南雅苑) 工程 监理实施细则 (塔吊安装与拆除工程) 内容提要: 专业工程特点 监理工作流程 监理工作内容 项目监理机构(章): 专业监理工程师: 总监理工程师(签字): (执业印章) 日 期: ...查看


  • 安007塔吊安拆专项施工方案(1)
  • 塔吊安装拆卸专项施工方案 报验申请表 工程名称:贵州申发久长科技有限公司一期工程(办公楼.宿舍.食堂) 编号:安007 贵州申发久长科技有限公司一期工程 (办公楼.宿舍.食堂) 塔吊安装拆卸专项施工方案 编制人: 审核人: 审批人: 贵州汇 ...查看


热门内容