外墙脚手架搭.拆方案

目录

1 工程概况 . ............................................................................................................................. 1 2 编制依据 . ............................................................................................................................. 1 3 脚手架选型设计及要求 . ..................................................................................................... 1

3.1 脚手架基本要求 . ...................................................................................................... 1 3.2 落地双排扣件式钢管脚手架设计 . .......................................................................... 2 3.3 卸料平台 . .................................................................................................................. 7 3.4 脚手架出入口的构造 . .............................................................................................. 9 3.5 脚手架的拆除要求 . ................................................................................................ 10 4 施工部署 . ............................................................................................................................11

4.1 安全管理小组 . .........................................................................................................11 4.2 劳动力准备 . .............................................................................................................11 4.3 材料准备 . .................................................................................................................11 5 质量要求 . ........................................................................................................................... 12

5.1 构配件允许偏差 . .................................................................................................... 12 5.2 脚手架搭设的允许偏差和检验方法 . .................................................................... 12 5.3 扣件拧紧抽样检查数自及质量判定标淮 . ............................................................ 13 6 安全措施 . ........................................................................................................................... 13

6.1 脚手架搭设的安全技术措施 . ................................................................................ 13 6.2 脚手架上施工作业的安全技术措施 . .................................................................... 14 6.3 脚手架拆除的安全措施 . ........................................................................................ 14 7 文明、环保施工措施 . ....................................................................................................... 15

7.1 整体要求 . ................................................................................................................ 15 7.2 具体要求 . ................................................................................................................ 15

1 工程概况

工程地理位置:北京市海淀区北洼路33号。本工程为剪力墙结构,地下一层;地

上为六层。地上结构总高度为19m 。

外墙脚手架设计:双排落地式钢管脚手架,(全封闭处理)。

2 编制依据

本施工方案编制依据见表2-1。

3 脚手架选型设计及要求

按照现场状况及实际需要,脚手架选用落地式钢管脚手架进行搭设、施工。 3.1 脚手架基本要求

3.1.1 管理要求

1、供应商必须向购买、租用构配件的使用单位提供销售许可证、营业执照、备案登记凭证、产品合格证、检测报告等质量证明文件,并对其提供的构配件质量负责。

2、构配件进入施工现场时进行检查和验收,并应在施工现场随机抽样,委托具有资质的检测单位进行力学性能检测。

3、脚手架的搭设与拆除编制专项施工方案,并经具有审批权限的相关人员审批。 4、脚手架搭设、拆除施工前,依据专项施工技术方案进行安全技术交底并作出记

录。

5、脚手架搭设、拆除施工作业人员经专业培训,并持证上岗。 3.1.2 构配件

1、钢管符合下列规定:

①钢管选用符合现行国家标准GB/T13973《直缝电焊钢管》中Q235-A 级的普通用钢,其材质性能符合国家标准GB/T700《碳素结构钢》的有关规定。

②钢管规格φ48³3.5mm ,壁厚最小值不得小于3mm 。

2、扣件采用可锻铸铁制造,其材质符合现行国家标准GB15831《钢管脚手架扣件》的有关规定。

3、脚手板符合现行行业标准JGJ130《建筑施工扣件式钢管脚手架安全技术规范》的规定。

4、安全网符合现行国家标准GB5725《安全网》及GB16909《密目式安全网》的规定。

3.2 落地双排扣件式钢管脚手架设计

3.2.1 选用条件

按照DB11/T583-2008落地式钢管脚手架规定见表3-1。

表3-1 落地双排扣件式钢管脚手架

3.2.2落地双排扣件式脚手架设计

按照规范及现场施工条件,脚手架设计见表3-2。

表3-2 落地双排扣件式钢管脚手架架体构造及参数

3.2.3 搭设要求

1、脚手架底部应铺设通长脚手板,同时增设专用底托。 2、立杆搭设应符合下列规定:

①当立杆基础不在同一高度上时,必须将高处的纵向扫地杆向低处延长两跨与立杆固定,高低差不应大于1m 。靠边坡上方的立杆轴线到边坡的距离不应小于500mm 。见图

3-1

同基础高度架体搭设

图3-1不同基础高度架体搭设构造要求

2立杆接长除顶层顶步外,其余各层各步接头必须采用对接扣件连接。 ○

3立杆顶端高出檐口上皮1.5m ,女儿墙1m ;本工程统一高度为1.5m 。 ○

3、水平杆搭设应符合下列规定(水平按节点设置见图): ①纵向水平杆应设置在立杆内侧,其长度不宜小于3跨。 ②纵向水平杆接长宜采用对接扣件连接,也可采用搭接。

③横向水平杆应放置在纵向水平杆上部,靠墙一端至墙装饰面距离不宜大于100mm 。

④主节点处必须设置横向水平杆。

⑤杆件接头应交错布置,两根相邻杆件接头不应设置在同步或同跨内,接头位置错开距离不应小于500mm ,各接头中心至主节点的距离不宜大于纵距的1/3。

⑥搭接接头的搭接长度不应小于1m ,应采用不少于3个旋转扣件固定。

500

不同步距杆件接头

不同步距杆件接头

300

图3-2 水平杆件接头搭设

4、扫地杆设置应符合下列规定:

①纵向扫地杆必须连续设置,钢管中心距地面不得大于200mm 。 ②脚手架底部主节点应设置横向扫地杆,其位置应在纵向扫地杆下方。 5、剪刀撑设置应符合下列规定:

①本工程脚手架设置为连续剪刀撑,连续剪刀撑见图3-4。

②剪刀撑杆件接长可采用搭接或对接,斜杆与立杆交接点必须设扣件连接。 6、架体通过连墙件与建筑物主体结构连接牢固。连墙件的设置应符合下列规定: ①架体的连墙件与结构的连接为刚性连接,连墙件竖向间距2m ,横向间距连接点。连墙件做法见图3-5。

连墙件拉结柱子构造

连续剪刀撑设置

图3-4 连续剪刀撑设置构造

连墙件拉结窗口构造连墙件拉结剪力墙构

图3-5 连墙件拉结构造

②连墙件应靠近主节点设置,距离主节点不得大于300mm 。 ③开口型脚手架的两端及脚手架的开口处必须设置连墙件。

④在结构梁上需要埋置预埋件与外墙脚手架进行有效拉结,平均4米,小于计算中的3跨。见图3-6。

连墙件拉结梁构造

图3-6 连墙件拉结梁构造

7、扣件安装应符合下列规定:

①螺栓拧紧力矩应控制在40~65N ²m 之间。

②主节点处固定横向水平杆、纵向水平杆、横向斜撑等用的直角扣件、旋转扣件的中心点的相互距离不应大于150mm 。

③对接扣件开口应朝上或朝内。

④各杆件断头伸出扣件盖板边缘的长度不应小于100mm 。

8、连墙件、剪刀撑、横向斜撑应随立杆、纵横向水平杆同时搭设。 9、脚手板的设置应符合下列规定:

①作业层脚手板应铺满铺稳,离开施工墙面不宜大于100mm 。

②脚手板应设置在不少于三根的横向水平杆上,可采用对接平铺,也可采用搭接铺设。

③脚手板对接平铺时,接头处必须设两根横向水平杆,脚手板的外伸长度取130~150mm ;脚手板搭设时,接头必须支在横向水平杆上,搭接长度应大于200mm ,其伸出横向水平杆的长度不应小于100mm 。

④作业层端部脚手板探头长度应取150mm ,其板长两端均应与支撑杆可靠固定。 11、铺板层小横杆设置间距不得大于立杆纵距的1/2。 3.3 卸料平台

卸料平台设置在主体结构的北侧,按照塔吊的布置要求,在北侧设置1个。

从经济、实用的角度考虑,卸料平台设计为悬挑式型钢平台,大小为4.0m ³2.5m ³1.25m (长³宽³高),悬挑长度为4m 。平台上要设有限定荷载标牌,本工程卸料平台限重为1.5t 。

主梁、次梁分别采用[18工字钢、I 16槽钢,所有构件均为螺栓连接,即为铰接。防护栏采用φ48³3.5钢管,分别在高60cm 、120cm 处设立两道,并与四周工字钢焊接。四周工字钢外侧面及防护栏杆均统一颜色油漆标识,并满布密目安全网。平台每侧设两根6³37、φ22钢丝绳,每根绳设夹具三个。钢丝绳与卸料平台钢管架接触处垫橡胶胶皮,以缓冲钢丝绳的拉力。钢丝绳通过梁上预埋φ16拉环连接,但两根钢丝绳不得拉接于同一个对拉螺栓孔,并且梁上预留的拉环要保证能让上述钢丝绳穿过。平台底面设50mm 厚的脚手板,满铺、铺牢、两端用8号镀锌铁丝捆紧,并在四周设150mm 高踢脚板。卸料平台效果图见下图3-10、图3-11、图3-12。

图3-10 卸料平台剖面图

图3-11 平面效果图

图3-12 整体效果图

3.4 脚手架出入口的构造

1、出入口设在楼体北侧,跨越三步三跨,大小为4.0m*5.4m(宽*高)出入口处

再搭设6.0m*4.0m*6.0m(长*宽*高)的防护棚,两侧用密目安全网封闭,上铺50mm 厚双层脚手板。

2、在出人口两侧的内、外排单立杆处分别增设一根辅立杆, 并高于门洞口1~2

步, 立柱用短管斜撑相互联系。上方悬空立柱处增加两根斜杆, 斜杆与各主节点相交处用扣件固定。洞口上方增设两道横向支撑, 应伸出斜腹杆的端部, 以保证立柱悬空处的整体性。门洞两侧分别增加两根斜腹杆, 并用旋转扣件固定在与之相交的小横杆的伸出端上, 旋转扣件中心线至主节点的距离在15cm 内。当斜腹杆在1跨内跨越2个步距时, 应在相交的大横杆处增设一根小横杆, 将斜腹杆固定在其伸出端上; 斜腹杆宜采用通长杆件, 必须接长时用对接扣件连接。

防护棚脚手架搭设

图3-13 通道出入口设置

3.5 脚手架的拆除要求

拆架程序应遵守由上而下, 先搭后拆的原则, 即先拆拉杆、脚手板、剪刀撑、斜撑, 而后拆小横杆、大横杆、立杆等(一般的拆除顺序为:安全网→栏杆→脚手板→剪刀撑→小横杆→大横杆→立杆) 。

不准分立面拆架或在上下两步同时进行拆架。做到一步一清、一杆一清。拆立杆时, 要先抱住立杆再拆开最后两个扣。拆除大横杆、斜撑、剪刀撑时, 应先拆中间扣件, 然后托住中间, 再解端头扣。所有连墙杆等必须随脚手架拆除同步下降,严禁先将连墙件整层或数层拆除后再拆脚手架, 分段拆除高差不应大于2步, 如高差大于2步, 应增设连墙件加固。

拆除后架体的稳定性不被破坏, 如附墙杆被拆除前, 应加设临时支撑防止变形, 拆除各标准节时, 应防止失稳。

当脚手架拆至下部最后一根长钢管的高度(约6.5m) 时, 应先在适当位置搭临时抛撑加固, 后拆连墙件。

4 施工部署

4.1 安全管理小组

安全生产、文明施工是企业生存与发展的前提条件,是达到无伤亡事故的必然保障,也是项目创建“北京市文明安全工地”的根本要求。为此成立以项目经理为组长,项目副经理为副组长的安全防护小组,责任分工如下:

组长:项目经理(范建忠)—负责总体协调部署 副组长:项目生产经理(赵顺)—负责指挥协调工作 组 员:赵西亮、郭建军、陈伟杰、许尔华、沈继运、陈晨 赵西亮、郭建军、许尔华 —负责具体实施、检查、监督工作。 4.2 劳动力准备

4.3 材料准备

5 质量要求

5.1 构配件允许偏差

5.2 脚手架搭设的允许偏差和检验方法

5.3 扣件拧紧抽样检查数自及质量判定标淮 6 安全措施

6.1 脚手架搭设的安全技术措施

1、脚手架的基础必须经过硬化处理满足承载力要求, 做到不积水、不沉陷, 顶板基础的混凝土必须达到设计强度的75%以上才能施工。

2、搭设过程中划出工作标志区, 禁止行人进人、统一指挥、上下呼应、动作协调, 严禁在无人指挥下作业。当解开与另一人有关的扣件时必先告诉对方, 并得到允许, 以防坠落伤人。

3、开始搭设立杆时, 应每隔6跨设置一根抛撑, 直至连墙件安装稳定后, 方可根据情况拆除。

4、脚手架及时与结构拉结或采用临时支顶, 以保证搭设过程安全, 未完成脚手架在每日收工前, 一定要确保架子稳定。

5、脚手架必须配合施工进度搭设, 一次搭设高度不得超过相邻连墙件以上两步。

6、在搭设过程中应由安全员、架子班长等进行检查、验收和签证。每两步验收一次, 达到设计施工要求后挂合格牌一块。

7、外脚手架的卸荷严格采用φ15.5的钢丝绳通过梁上对拉螺栓孔与脚手架连接, 严禁私自拆改。

6.2 脚手架上施工作业的安全技术措施

1、结构外脚手架每支搭一层, 支搭完毕后, 经项目部安全员验收合格后方可使用。任何班组长和个人, 未经同意不得任意拆除脚手架部件。

2、严格控制施工荷载, 脚手板不得集中堆料施荷, 施工荷载不得大于3kN/m2,确保较大安全储备。

3、结构施工时不允许多层同时作业, 装修施工时同时作业层数不超过两层, 临时性用的悬挑架的同时作业层数不超过1层.

4、当作业层高出其下连墙件3.6m以上、且其上尚无连墙件时, 应采取适当的临时撑拉措施。

5、各作业层之间设置可靠的防护栅栏, 防止坠落物体伤人.

6、定期检查脚手架, 发现问题和隐患, 在施工作业前及时维修加固, 以达到坚固稳定, 确保施工安全。

6.3 脚手架拆除的安全措施

1、拆架前,全面检查待拆脚手架,根据检查结果, 拟订出作业计划, 报请批准, 进行技术交底后才准工作。

2、架体拆除前,必须查看施工现场环境,包括架空线路、外脚手架、地面的设施等各类障碍物、地锚、缆风绳、连墙杆及被拆架体各吊点、附件、电气装置情况, 凡能提前拆除的尽量拆除掉。

3、拆架时应划分作业区, 周围设绳绑围栏或竖立警戒标志, 地面应设专人指挥, 禁止非作业人员进入。

4、拆除时要统一指挥,上下呼应, 动作协调, 当解开与另一人有关的结扣时, 应先通知对方, 以防坠落。

5、在拆架时, 不得中途换人, 如必须换人时, 应将拆除情况交代清楚后方可离开。

6、每天拆架下班时, 不应留下隐患部位。

7、拆架时严禁碰撞脚手架附近电源线, 以防触电事故。

8、所有杆件和扣件在拆除时应分离, 不准在杆件上附着扣件或两杆连着送到地面。 9、所有的脚手板, 应自外向里竖立搬运, 以防脚手板和垃圾物从高处坠落伤人。 10、拆下的零配件要装入容器内, 用吊篮吊下; 拆下的钢管要绑扎牢固, 双点起吊, 严禁从高空抛掷。

7 文明、环保施工措施

7.1 整体要求

本工程位于北京市海淀区北洼路33号,北临学校,东临北洼路,为保证本工程的绿色施工、标准化施工,所有外墙脚手架的颜色要求整齐统一、外贴悬挂标语要统一、安全网的规格尺寸要统一。此统一规划要求由本项目安全、环保部进行统一协调。 7.2 具体要求

1、进入施工现场的人员必须戴好安全帽, 高空作业系好安全带,穿好防滑鞋等, 现场严禁吸烟。

2、进入施工现场的人员要爱护场内的各种绿化设施和标示牌, 不得践踏草坪、损坏花草树木、随意拆除和移动标示牌。

3、严禁酗酒人员上架作业, 施工操作时要求精力集中、禁止开玩笑和打闹。 4、脚手架搭设人员必须是经考试合格的专业架子工, 上岗人员定期体检, 体检合格者方可发上岗证, 凡患有高血压、贫血病、心脏病及其他不适于高空作业者, 一律不得上脚手架操作。

5、上架子作业人员上下均应走人行梯道, 不准攀爬架子。

6、护身栏、脚手板、挡脚板、密目安全网等影响作业班组支模时, 如需拆改时, 应由架子工来完成, 任何人不得任意拆改。

7、脚手架验收合格后任何人不得擅自拆改, 如需做局部拆改时, 须经技术部同意后由架子工操作。

8、不准利用脚手架吊运重物; 作业人员不准攀登架子上下作业面; 不准推车在架子

上跑动,塔吊起吊物体时不能碰撞和拖动脚手架.

9、不得将模板支撑、缆风绳、泵送混凝土及砂浆的输送管等固定在脚手架上,严禁任意悬挂起重设备。

10、在架子上的作业人员不得随意拆动脚手架的所有拉接点和脚手板, 以及扣件绑扎扣等所有架子部件。

11、拆除架子而使用电焊气割时, 派专职人员做好防火工作, 配备料斗, 防止火星和切割物溅落。

12、脚手架使用时间较长, 因此在使用过程中需要进行检查, 发现基础下沉、杆件变形严重、防护不全、拉接松动等问题要及时解决。

13、要保证脚手架体的整体性, 不得与井架、升降机一并拉结, 不得截断架体。 14、施工人员严禁凌空投掷杆件、物料、扣件及其他物品, 材料、工具用滑轮和绳索运输, 不得乱扔。

15、使用的工具要放在工具袋内, 防止掉落伤人; 登高要穿防滑鞋, 袖口及裤口要扎紧。

16、脚手架堆放场做到整洁、摆放合理、专人保管, 并建立严格领退料手续。 17、施工人员做到活完料净脚下清, 确保脚手架施工材料不浪费。

18、运至地面的材料应按指定地点随拆随运, 分类堆放, 当天拆当天清, 拆下的扣件和铁丝要集中回收处理。应随时整理、检查, 按品种、分规格堆放整齐, 妥善保管。

19、五级以上大风、大雪、大雾、大雨天气停止脚手架作业. 在冬季、雨季要经常检查脚手板、斜道板、跳板上有无积雪、积水等物。若有则应随时清扫并要采取防滑措施。

目录

1 工程概况 . ............................................................................................................................. 1 2 编制依据 . ............................................................................................................................. 1 3 脚手架选型设计及要求 . ..................................................................................................... 1

3.1 脚手架基本要求 . ...................................................................................................... 1 3.2 落地双排扣件式钢管脚手架设计 . .......................................................................... 2 3.3 卸料平台 . .................................................................................................................. 7 3.4 脚手架出入口的构造 . .............................................................................................. 9 3.5 脚手架的拆除要求 . ................................................................................................ 10 4 施工部署 . ............................................................................................................................11

4.1 安全管理小组 . .........................................................................................................11 4.2 劳动力准备 . .............................................................................................................11 4.3 材料准备 . .................................................................................................................11 5 质量要求 . ........................................................................................................................... 12

5.1 构配件允许偏差 . .................................................................................................... 12 5.2 脚手架搭设的允许偏差和检验方法 . .................................................................... 12 5.3 扣件拧紧抽样检查数自及质量判定标淮 . ............................................................ 13 6 安全措施 . ........................................................................................................................... 13

6.1 脚手架搭设的安全技术措施 . ................................................................................ 13 6.2 脚手架上施工作业的安全技术措施 . .................................................................... 14 6.3 脚手架拆除的安全措施 . ........................................................................................ 14 7 文明、环保施工措施 . ....................................................................................................... 15

7.1 整体要求 . ................................................................................................................ 15 7.2 具体要求 . ................................................................................................................ 15

1 工程概况

工程地理位置:北京市海淀区北洼路33号。本工程为剪力墙结构,地下一层;地

上为六层。地上结构总高度为19m 。

外墙脚手架设计:双排落地式钢管脚手架,(全封闭处理)。

2 编制依据

本施工方案编制依据见表2-1。

3 脚手架选型设计及要求

按照现场状况及实际需要,脚手架选用落地式钢管脚手架进行搭设、施工。 3.1 脚手架基本要求

3.1.1 管理要求

1、供应商必须向购买、租用构配件的使用单位提供销售许可证、营业执照、备案登记凭证、产品合格证、检测报告等质量证明文件,并对其提供的构配件质量负责。

2、构配件进入施工现场时进行检查和验收,并应在施工现场随机抽样,委托具有资质的检测单位进行力学性能检测。

3、脚手架的搭设与拆除编制专项施工方案,并经具有审批权限的相关人员审批。 4、脚手架搭设、拆除施工前,依据专项施工技术方案进行安全技术交底并作出记

录。

5、脚手架搭设、拆除施工作业人员经专业培训,并持证上岗。 3.1.2 构配件

1、钢管符合下列规定:

①钢管选用符合现行国家标准GB/T13973《直缝电焊钢管》中Q235-A 级的普通用钢,其材质性能符合国家标准GB/T700《碳素结构钢》的有关规定。

②钢管规格φ48³3.5mm ,壁厚最小值不得小于3mm 。

2、扣件采用可锻铸铁制造,其材质符合现行国家标准GB15831《钢管脚手架扣件》的有关规定。

3、脚手板符合现行行业标准JGJ130《建筑施工扣件式钢管脚手架安全技术规范》的规定。

4、安全网符合现行国家标准GB5725《安全网》及GB16909《密目式安全网》的规定。

3.2 落地双排扣件式钢管脚手架设计

3.2.1 选用条件

按照DB11/T583-2008落地式钢管脚手架规定见表3-1。

表3-1 落地双排扣件式钢管脚手架

3.2.2落地双排扣件式脚手架设计

按照规范及现场施工条件,脚手架设计见表3-2。

表3-2 落地双排扣件式钢管脚手架架体构造及参数

3.2.3 搭设要求

1、脚手架底部应铺设通长脚手板,同时增设专用底托。 2、立杆搭设应符合下列规定:

①当立杆基础不在同一高度上时,必须将高处的纵向扫地杆向低处延长两跨与立杆固定,高低差不应大于1m 。靠边坡上方的立杆轴线到边坡的距离不应小于500mm 。见图

3-1

同基础高度架体搭设

图3-1不同基础高度架体搭设构造要求

2立杆接长除顶层顶步外,其余各层各步接头必须采用对接扣件连接。 ○

3立杆顶端高出檐口上皮1.5m ,女儿墙1m ;本工程统一高度为1.5m 。 ○

3、水平杆搭设应符合下列规定(水平按节点设置见图): ①纵向水平杆应设置在立杆内侧,其长度不宜小于3跨。 ②纵向水平杆接长宜采用对接扣件连接,也可采用搭接。

③横向水平杆应放置在纵向水平杆上部,靠墙一端至墙装饰面距离不宜大于100mm 。

④主节点处必须设置横向水平杆。

⑤杆件接头应交错布置,两根相邻杆件接头不应设置在同步或同跨内,接头位置错开距离不应小于500mm ,各接头中心至主节点的距离不宜大于纵距的1/3。

⑥搭接接头的搭接长度不应小于1m ,应采用不少于3个旋转扣件固定。

500

不同步距杆件接头

不同步距杆件接头

300

图3-2 水平杆件接头搭设

4、扫地杆设置应符合下列规定:

①纵向扫地杆必须连续设置,钢管中心距地面不得大于200mm 。 ②脚手架底部主节点应设置横向扫地杆,其位置应在纵向扫地杆下方。 5、剪刀撑设置应符合下列规定:

①本工程脚手架设置为连续剪刀撑,连续剪刀撑见图3-4。

②剪刀撑杆件接长可采用搭接或对接,斜杆与立杆交接点必须设扣件连接。 6、架体通过连墙件与建筑物主体结构连接牢固。连墙件的设置应符合下列规定: ①架体的连墙件与结构的连接为刚性连接,连墙件竖向间距2m ,横向间距连接点。连墙件做法见图3-5。

连墙件拉结柱子构造

连续剪刀撑设置

图3-4 连续剪刀撑设置构造

连墙件拉结窗口构造连墙件拉结剪力墙构

图3-5 连墙件拉结构造

②连墙件应靠近主节点设置,距离主节点不得大于300mm 。 ③开口型脚手架的两端及脚手架的开口处必须设置连墙件。

④在结构梁上需要埋置预埋件与外墙脚手架进行有效拉结,平均4米,小于计算中的3跨。见图3-6。

连墙件拉结梁构造

图3-6 连墙件拉结梁构造

7、扣件安装应符合下列规定:

①螺栓拧紧力矩应控制在40~65N ²m 之间。

②主节点处固定横向水平杆、纵向水平杆、横向斜撑等用的直角扣件、旋转扣件的中心点的相互距离不应大于150mm 。

③对接扣件开口应朝上或朝内。

④各杆件断头伸出扣件盖板边缘的长度不应小于100mm 。

8、连墙件、剪刀撑、横向斜撑应随立杆、纵横向水平杆同时搭设。 9、脚手板的设置应符合下列规定:

①作业层脚手板应铺满铺稳,离开施工墙面不宜大于100mm 。

②脚手板应设置在不少于三根的横向水平杆上,可采用对接平铺,也可采用搭接铺设。

③脚手板对接平铺时,接头处必须设两根横向水平杆,脚手板的外伸长度取130~150mm ;脚手板搭设时,接头必须支在横向水平杆上,搭接长度应大于200mm ,其伸出横向水平杆的长度不应小于100mm 。

④作业层端部脚手板探头长度应取150mm ,其板长两端均应与支撑杆可靠固定。 11、铺板层小横杆设置间距不得大于立杆纵距的1/2。 3.3 卸料平台

卸料平台设置在主体结构的北侧,按照塔吊的布置要求,在北侧设置1个。

从经济、实用的角度考虑,卸料平台设计为悬挑式型钢平台,大小为4.0m ³2.5m ³1.25m (长³宽³高),悬挑长度为4m 。平台上要设有限定荷载标牌,本工程卸料平台限重为1.5t 。

主梁、次梁分别采用[18工字钢、I 16槽钢,所有构件均为螺栓连接,即为铰接。防护栏采用φ48³3.5钢管,分别在高60cm 、120cm 处设立两道,并与四周工字钢焊接。四周工字钢外侧面及防护栏杆均统一颜色油漆标识,并满布密目安全网。平台每侧设两根6³37、φ22钢丝绳,每根绳设夹具三个。钢丝绳与卸料平台钢管架接触处垫橡胶胶皮,以缓冲钢丝绳的拉力。钢丝绳通过梁上预埋φ16拉环连接,但两根钢丝绳不得拉接于同一个对拉螺栓孔,并且梁上预留的拉环要保证能让上述钢丝绳穿过。平台底面设50mm 厚的脚手板,满铺、铺牢、两端用8号镀锌铁丝捆紧,并在四周设150mm 高踢脚板。卸料平台效果图见下图3-10、图3-11、图3-12。

图3-10 卸料平台剖面图

图3-11 平面效果图

图3-12 整体效果图

3.4 脚手架出入口的构造

1、出入口设在楼体北侧,跨越三步三跨,大小为4.0m*5.4m(宽*高)出入口处

再搭设6.0m*4.0m*6.0m(长*宽*高)的防护棚,两侧用密目安全网封闭,上铺50mm 厚双层脚手板。

2、在出人口两侧的内、外排单立杆处分别增设一根辅立杆, 并高于门洞口1~2

步, 立柱用短管斜撑相互联系。上方悬空立柱处增加两根斜杆, 斜杆与各主节点相交处用扣件固定。洞口上方增设两道横向支撑, 应伸出斜腹杆的端部, 以保证立柱悬空处的整体性。门洞两侧分别增加两根斜腹杆, 并用旋转扣件固定在与之相交的小横杆的伸出端上, 旋转扣件中心线至主节点的距离在15cm 内。当斜腹杆在1跨内跨越2个步距时, 应在相交的大横杆处增设一根小横杆, 将斜腹杆固定在其伸出端上; 斜腹杆宜采用通长杆件, 必须接长时用对接扣件连接。

防护棚脚手架搭设

图3-13 通道出入口设置

3.5 脚手架的拆除要求

拆架程序应遵守由上而下, 先搭后拆的原则, 即先拆拉杆、脚手板、剪刀撑、斜撑, 而后拆小横杆、大横杆、立杆等(一般的拆除顺序为:安全网→栏杆→脚手板→剪刀撑→小横杆→大横杆→立杆) 。

不准分立面拆架或在上下两步同时进行拆架。做到一步一清、一杆一清。拆立杆时, 要先抱住立杆再拆开最后两个扣。拆除大横杆、斜撑、剪刀撑时, 应先拆中间扣件, 然后托住中间, 再解端头扣。所有连墙杆等必须随脚手架拆除同步下降,严禁先将连墙件整层或数层拆除后再拆脚手架, 分段拆除高差不应大于2步, 如高差大于2步, 应增设连墙件加固。

拆除后架体的稳定性不被破坏, 如附墙杆被拆除前, 应加设临时支撑防止变形, 拆除各标准节时, 应防止失稳。

当脚手架拆至下部最后一根长钢管的高度(约6.5m) 时, 应先在适当位置搭临时抛撑加固, 后拆连墙件。

4 施工部署

4.1 安全管理小组

安全生产、文明施工是企业生存与发展的前提条件,是达到无伤亡事故的必然保障,也是项目创建“北京市文明安全工地”的根本要求。为此成立以项目经理为组长,项目副经理为副组长的安全防护小组,责任分工如下:

组长:项目经理(范建忠)—负责总体协调部署 副组长:项目生产经理(赵顺)—负责指挥协调工作 组 员:赵西亮、郭建军、陈伟杰、许尔华、沈继运、陈晨 赵西亮、郭建军、许尔华 —负责具体实施、检查、监督工作。 4.2 劳动力准备

4.3 材料准备

5 质量要求

5.1 构配件允许偏差

5.2 脚手架搭设的允许偏差和检验方法

5.3 扣件拧紧抽样检查数自及质量判定标淮 6 安全措施

6.1 脚手架搭设的安全技术措施

1、脚手架的基础必须经过硬化处理满足承载力要求, 做到不积水、不沉陷, 顶板基础的混凝土必须达到设计强度的75%以上才能施工。

2、搭设过程中划出工作标志区, 禁止行人进人、统一指挥、上下呼应、动作协调, 严禁在无人指挥下作业。当解开与另一人有关的扣件时必先告诉对方, 并得到允许, 以防坠落伤人。

3、开始搭设立杆时, 应每隔6跨设置一根抛撑, 直至连墙件安装稳定后, 方可根据情况拆除。

4、脚手架及时与结构拉结或采用临时支顶, 以保证搭设过程安全, 未完成脚手架在每日收工前, 一定要确保架子稳定。

5、脚手架必须配合施工进度搭设, 一次搭设高度不得超过相邻连墙件以上两步。

6、在搭设过程中应由安全员、架子班长等进行检查、验收和签证。每两步验收一次, 达到设计施工要求后挂合格牌一块。

7、外脚手架的卸荷严格采用φ15.5的钢丝绳通过梁上对拉螺栓孔与脚手架连接, 严禁私自拆改。

6.2 脚手架上施工作业的安全技术措施

1、结构外脚手架每支搭一层, 支搭完毕后, 经项目部安全员验收合格后方可使用。任何班组长和个人, 未经同意不得任意拆除脚手架部件。

2、严格控制施工荷载, 脚手板不得集中堆料施荷, 施工荷载不得大于3kN/m2,确保较大安全储备。

3、结构施工时不允许多层同时作业, 装修施工时同时作业层数不超过两层, 临时性用的悬挑架的同时作业层数不超过1层.

4、当作业层高出其下连墙件3.6m以上、且其上尚无连墙件时, 应采取适当的临时撑拉措施。

5、各作业层之间设置可靠的防护栅栏, 防止坠落物体伤人.

6、定期检查脚手架, 发现问题和隐患, 在施工作业前及时维修加固, 以达到坚固稳定, 确保施工安全。

6.3 脚手架拆除的安全措施

1、拆架前,全面检查待拆脚手架,根据检查结果, 拟订出作业计划, 报请批准, 进行技术交底后才准工作。

2、架体拆除前,必须查看施工现场环境,包括架空线路、外脚手架、地面的设施等各类障碍物、地锚、缆风绳、连墙杆及被拆架体各吊点、附件、电气装置情况, 凡能提前拆除的尽量拆除掉。

3、拆架时应划分作业区, 周围设绳绑围栏或竖立警戒标志, 地面应设专人指挥, 禁止非作业人员进入。

4、拆除时要统一指挥,上下呼应, 动作协调, 当解开与另一人有关的结扣时, 应先通知对方, 以防坠落。

5、在拆架时, 不得中途换人, 如必须换人时, 应将拆除情况交代清楚后方可离开。

6、每天拆架下班时, 不应留下隐患部位。

7、拆架时严禁碰撞脚手架附近电源线, 以防触电事故。

8、所有杆件和扣件在拆除时应分离, 不准在杆件上附着扣件或两杆连着送到地面。 9、所有的脚手板, 应自外向里竖立搬运, 以防脚手板和垃圾物从高处坠落伤人。 10、拆下的零配件要装入容器内, 用吊篮吊下; 拆下的钢管要绑扎牢固, 双点起吊, 严禁从高空抛掷。

7 文明、环保施工措施

7.1 整体要求

本工程位于北京市海淀区北洼路33号,北临学校,东临北洼路,为保证本工程的绿色施工、标准化施工,所有外墙脚手架的颜色要求整齐统一、外贴悬挂标语要统一、安全网的规格尺寸要统一。此统一规划要求由本项目安全、环保部进行统一协调。 7.2 具体要求

1、进入施工现场的人员必须戴好安全帽, 高空作业系好安全带,穿好防滑鞋等, 现场严禁吸烟。

2、进入施工现场的人员要爱护场内的各种绿化设施和标示牌, 不得践踏草坪、损坏花草树木、随意拆除和移动标示牌。

3、严禁酗酒人员上架作业, 施工操作时要求精力集中、禁止开玩笑和打闹。 4、脚手架搭设人员必须是经考试合格的专业架子工, 上岗人员定期体检, 体检合格者方可发上岗证, 凡患有高血压、贫血病、心脏病及其他不适于高空作业者, 一律不得上脚手架操作。

5、上架子作业人员上下均应走人行梯道, 不准攀爬架子。

6、护身栏、脚手板、挡脚板、密目安全网等影响作业班组支模时, 如需拆改时, 应由架子工来完成, 任何人不得任意拆改。

7、脚手架验收合格后任何人不得擅自拆改, 如需做局部拆改时, 须经技术部同意后由架子工操作。

8、不准利用脚手架吊运重物; 作业人员不准攀登架子上下作业面; 不准推车在架子

上跑动,塔吊起吊物体时不能碰撞和拖动脚手架.

9、不得将模板支撑、缆风绳、泵送混凝土及砂浆的输送管等固定在脚手架上,严禁任意悬挂起重设备。

10、在架子上的作业人员不得随意拆动脚手架的所有拉接点和脚手板, 以及扣件绑扎扣等所有架子部件。

11、拆除架子而使用电焊气割时, 派专职人员做好防火工作, 配备料斗, 防止火星和切割物溅落。

12、脚手架使用时间较长, 因此在使用过程中需要进行检查, 发现基础下沉、杆件变形严重、防护不全、拉接松动等问题要及时解决。

13、要保证脚手架体的整体性, 不得与井架、升降机一并拉结, 不得截断架体。 14、施工人员严禁凌空投掷杆件、物料、扣件及其他物品, 材料、工具用滑轮和绳索运输, 不得乱扔。

15、使用的工具要放在工具袋内, 防止掉落伤人; 登高要穿防滑鞋, 袖口及裤口要扎紧。

16、脚手架堆放场做到整洁、摆放合理、专人保管, 并建立严格领退料手续。 17、施工人员做到活完料净脚下清, 确保脚手架施工材料不浪费。

18、运至地面的材料应按指定地点随拆随运, 分类堆放, 当天拆当天清, 拆下的扣件和铁丝要集中回收处理。应随时整理、检查, 按品种、分规格堆放整齐, 妥善保管。

19、五级以上大风、大雪、大雾、大雨天气停止脚手架作业. 在冬季、雨季要经常检查脚手板、斜道板、跳板上有无积雪、积水等物。若有则应随时清扫并要采取防滑措施。


相关文章

  • 外墙装饰脚手架施工方案
  • 会东县会东镇全球通路立面改造工程A标段 脚 手 架 施 工 方 案 编制: 复核: 审批: 四川华隆建设集团有限公司会东项目部 2013年02月20日 施工组织设计/方案申报表 施工单位: 监理单位: 四川华隆建设工程有限公司 合同号: 四 ...查看


  • 外墙面砖粘贴施工方案
  • 外墙面砖粘贴施工方案 第一章 工程概况及特点 本工程坐落于敦煌市七里镇昆仑路青海油田分公司局机关办公区内,交通便利.施工现场由于绿化地较多,主要施工场地为以往的室外道路.施工场地较狭窄,不利于施工现场临时设施的布置和施工的需要.办公楼2#大 ...查看


  • 某大楼拆除施工方案
  • 某大楼拆除施工方案 大楼 拆除施工方案 目 录 第一部分:前期准备 1.本方案编制依据---------------------------------------------------P 2.拆除方案的主导构思------------- ...查看


  • 某大楼拆除施工方案3
  • 某大楼拆除施工方案 大楼 拆除施工方案 目 录 第一部分:前期准备 1.本方案编制依---------------------------------------------------P 2.拆除方案的主导构--------------- ...查看


  • 外墙软瓷面砖施工方案TJI
  • 盐城 地块 商住项目工程 编制单位: 编制人: 审核人: 编制日期:外 墙 软 磁 面 砖 施 工 方 案 2011年4月7日 软 瓷 面 砖 施 工 方 案 一. 工程概况: 盐城 地块商住项目 工程由盐城置业有限公司建设,南京市建筑设计 ...查看


  • 外墙装饰装修施工方案 1
  • 外墙装饰装修施工方案 外墙装饰装修专项施工方案 一.编制依据 <德阳市人民医院内科综合住院大楼工程设计施工图纸及修改设计通知单> <绝热用挤塑聚苯依稀泡沫塑料(XFS)>GB/T10801.2-2002 <民用 ...查看


  • 高层外墙保温施工方案
  • 大华锦绣华城E块18栋.20栋.24栋工程 胶粉聚苯颗粒外墙外保温 专 项 施 工 方 案 编制人: 审核人: 批准人: 上海名华工程建筑有限公司 方 案 目 录 一.编制依据 二.工程概况 三.施工组织结构图 四.施工部署 五.机械设备及 ...查看


  • 外墙脚手架搭设.拆除方案
  • 外架搭设.拆除方案 根据本工程建筑造型以及拟定回填土的施工时间,结合考虑施工便利和经济因素,主楼第一层采用落地式双排钢管扣件脚手架,二层以上采用悬挑式钢管脚手架. (一)落地式双排钢管扣件脚手架搭设及拆除方案 1.落地式双排钢管扣件脚手架搭 ...查看


  • 外墙外保温_膨胀玻化微珠_施工方案
  • 膨胀玻化微珠外墙外保温系统 施 工 方 案 编 制: 校 核: 审 批: 编制单位:安徽中嘉建设有限公司 二0一二年十月二十日 目 录 1 工程概况 2 编制依据 3 外墙外保温工程相关工序的要求 4 施工方案 5 外墙外保温系统的验收 6 ...查看


  • 外墙装饰抹灰工程安全施工方案
  • 外墙装饰抹灰工程安全施工方案: 1.进入施工现场必须遵守安全生产六大纪律和十项安全技术措施. 2.高空作业时,应检查脚手架是否稳固,特别是大风或雨后作业. 3.对脚手板不牢固之处和跷头板等及时处理,要铺有足够的宽度,以保证手推车运灰浆时的安 ...查看


热门内容