土方挖填计算

注:场地平整土方量计算步骤:

(1)场地设计标高确定后,求出平整的场地各角点的施工高度Hi ;

(2)确定“零线”的位置,有助于了解整个场地的挖填区域分布状况;

(3)然后按每个方格角点的施工高度算出挖、填土方量,并计算边坡的土方量,这样即得到整个场地的挖、填土方总量。

两挖两填:Vw=a^2/4[(h1^2/(h1+h4)+h2^2/(h2+h3)]

Vt=a^2/4[(h4^2/(h1+h4)+h3^2/(h2+h3)]

三挖一填(三填一挖):V 填=a^2/6*h4^3/[(h1+h4)(h2+h3)]

V 挖=a^2/6*(2h1+h2+2h3-h4)+V填

全挖全填:V=a^2/4(h1+h2+h2+h4)

一挖一填:V=1/6*a^2*h

列:某建筑场地地形图和方格网(边长a=20.0m)布置图如图所示,土壤为二类土,场地地面泄水坡度ix=0.3%,iy=0.2%。试确定场地设计标高(不考虑土的可松性影响,余土加宽边坡)计算方格网土方挖填工程量。

解:(1)初步确定设计标高

H0=1/4n (Σh1+2Σh2+3Σh3+4Σh4)

=1/(4*8)[(43.24+44.80+42.58+44.17)+2*(43.67+43.94+43.34+42.94+44.67+43.23+43.67)+4*(43.35+43.76+44.17)]=43.71

(2)泄水坡度确定各点设计标高(物理中心Vw=Vt)

H3y=H0±Lxix±Lyiy=43.71-40*0.3%+20*0.2%=43.63

(3)计算施工高度Hi

Hi'=H0-Hi

H8=43.71-43.71=-0.05

(4)确定零线

X1=h1/(h1+h2)*a

X2-3=0.02/(0.02+0.19)*20=1.9

(5)计算挖填方量

Vt-1=a^2/4(h1+h2+h2+h4)=20^2/4(0.39+0.02+0.3+0.65)=136m^3

Vt-5=a^2/4(h1+h2+h2+h4)=20^2/4(0.65+0.3+0.71+0.97)=263m^3

Vw-3=a^2/4(h1+h2+h2+h4)=20^2/4(0.19+0.53+0.4+0.05)=117m^3

Vw-4=a^2/4(h1+h2+h2+h4)=20^2/4(0.53+0.93+0.84+0.1)=270m^3

Vt-2=a^2/4[(h1^2/(h1+h4)+h2^2/(h2+h3)]=20^2/4(0.02^2/(0.02+0.19)+0.3^2/

(0.3+0.05)]=25.89m^3

Vw-2=a^2/4[(h3^2/(h2+h3)+h4^2/(h1+h4)]=20^2/4(0.05^2/(0.3+0.05)+0.19^2/(0.02+0.19)]=17.9m^3

Vt-7=a^2/4[(h1^2/(h1+h4)+h2^2/(h2+h3)]=20^2/4(0.44^2/(0.44+0.05)+0.06^2/(0.06+0.4)]=40.28m^3

Vw-7=a^2/4[(h3^2/(h2+h3)+h4^2/(h1+h4)]=20^2/4(0.4^2/(0.06+0.4)+0.05^2/(0.3+0.05)]=35.30m^3

Vw-6=a^2/6*h4^3/[(h1+h4)(h2+h3)]=20^3/6*0.05^3/[(0.44+0.05)(0.71+0.3)]=0.0168m^3 Vt-6=a^2/6*(2h1+h2+2h3-h4)+Vw=20^2/6*(2*0.44+0.71+2*0.3-0.05)+0.0168=142.71m^3 Vt-8=a^2/6*h4^3/[(h1+h4)(h2+h3)]=20^3/6*(0.06^3/[(0.4+0.06)(0.84+0.38)]=0.026m^3 Vw-8=a^2/6*(2h1+h2+2h3-h4)+Vt=20^2/6*(2*0.4+0.84+2*0.38-0.06)+0.026=156.026m^3 Vw 总=Vw-3+Vw-4+Vw-7+Vw-6+Vw-8+Vw-2=117+270+35.30+0.0168+0.026+17.9=408.2428m^3 Vt 总=Vt-1+Vt-5+Vt-2+Vt-7+Vt-8+Vt-6=136+263+25.89+40.28+142.71+0.026=607.906m^3

(6)计算挖填方量

三棱椎:V=1/3*AL=1/3*58.1*1/2*1*0.93^2=8.38m^2

三棱柱:V=(A1+A2)/2*L=(1/2*0.93^2*1/2*0.38^2)/2*40

(7)验算

|Vw-vt|≦0.2%(|Vw|+|Vt|

注:场地平整土方量计算步骤:

(1)场地设计标高确定后,求出平整的场地各角点的施工高度Hi ;

(2)确定“零线”的位置,有助于了解整个场地的挖填区域分布状况;

(3)然后按每个方格角点的施工高度算出挖、填土方量,并计算边坡的土方量,这样即得到整个场地的挖、填土方总量。

两挖两填:Vw=a^2/4[(h1^2/(h1+h4)+h2^2/(h2+h3)]

Vt=a^2/4[(h4^2/(h1+h4)+h3^2/(h2+h3)]

三挖一填(三填一挖):V 填=a^2/6*h4^3/[(h1+h4)(h2+h3)]

V 挖=a^2/6*(2h1+h2+2h3-h4)+V填

全挖全填:V=a^2/4(h1+h2+h2+h4)

一挖一填:V=1/6*a^2*h

列:某建筑场地地形图和方格网(边长a=20.0m)布置图如图所示,土壤为二类土,场地地面泄水坡度ix=0.3%,iy=0.2%。试确定场地设计标高(不考虑土的可松性影响,余土加宽边坡)计算方格网土方挖填工程量。

解:(1)初步确定设计标高

H0=1/4n (Σh1+2Σh2+3Σh3+4Σh4)

=1/(4*8)[(43.24+44.80+42.58+44.17)+2*(43.67+43.94+43.34+42.94+44.67+43.23+43.67)+4*(43.35+43.76+44.17)]=43.71

(2)泄水坡度确定各点设计标高(物理中心Vw=Vt)

H3y=H0±Lxix±Lyiy=43.71-40*0.3%+20*0.2%=43.63

(3)计算施工高度Hi

Hi'=H0-Hi

H8=43.71-43.71=-0.05

(4)确定零线

X1=h1/(h1+h2)*a

X2-3=0.02/(0.02+0.19)*20=1.9

(5)计算挖填方量

Vt-1=a^2/4(h1+h2+h2+h4)=20^2/4(0.39+0.02+0.3+0.65)=136m^3

Vt-5=a^2/4(h1+h2+h2+h4)=20^2/4(0.65+0.3+0.71+0.97)=263m^3

Vw-3=a^2/4(h1+h2+h2+h4)=20^2/4(0.19+0.53+0.4+0.05)=117m^3

Vw-4=a^2/4(h1+h2+h2+h4)=20^2/4(0.53+0.93+0.84+0.1)=270m^3

Vt-2=a^2/4[(h1^2/(h1+h4)+h2^2/(h2+h3)]=20^2/4(0.02^2/(0.02+0.19)+0.3^2/

(0.3+0.05)]=25.89m^3

Vw-2=a^2/4[(h3^2/(h2+h3)+h4^2/(h1+h4)]=20^2/4(0.05^2/(0.3+0.05)+0.19^2/(0.02+0.19)]=17.9m^3

Vt-7=a^2/4[(h1^2/(h1+h4)+h2^2/(h2+h3)]=20^2/4(0.44^2/(0.44+0.05)+0.06^2/(0.06+0.4)]=40.28m^3

Vw-7=a^2/4[(h3^2/(h2+h3)+h4^2/(h1+h4)]=20^2/4(0.4^2/(0.06+0.4)+0.05^2/(0.3+0.05)]=35.30m^3

Vw-6=a^2/6*h4^3/[(h1+h4)(h2+h3)]=20^3/6*0.05^3/[(0.44+0.05)(0.71+0.3)]=0.0168m^3 Vt-6=a^2/6*(2h1+h2+2h3-h4)+Vw=20^2/6*(2*0.44+0.71+2*0.3-0.05)+0.0168=142.71m^3 Vt-8=a^2/6*h4^3/[(h1+h4)(h2+h3)]=20^3/6*(0.06^3/[(0.4+0.06)(0.84+0.38)]=0.026m^3 Vw-8=a^2/6*(2h1+h2+2h3-h4)+Vt=20^2/6*(2*0.4+0.84+2*0.38-0.06)+0.026=156.026m^3 Vw 总=Vw-3+Vw-4+Vw-7+Vw-6+Vw-8+Vw-2=117+270+35.30+0.0168+0.026+17.9=408.2428m^3 Vt 总=Vt-1+Vt-5+Vt-2+Vt-7+Vt-8+Vt-6=136+263+25.89+40.28+142.71+0.026=607.906m^3

(6)计算挖填方量

三棱椎:V=1/3*AL=1/3*58.1*1/2*1*0.93^2=8.38m^2

三棱柱:V=(A1+A2)/2*L=(1/2*0.93^2*1/2*0.38^2)/2*40

(7)验算

|Vw-vt|≦0.2%(|Vw|+|Vt|


相关文章

  • 鸿业土方计算设计软件
  • 鸿业土方计算设计软件HYECS8.0版|鸿业土方计算 8.0版 宝贝含:安装盘和加密狗 详细介绍 一.什么是HYECS For C3D? 鸿业土方计算设计软件是鸿业公司研制的CAD系列软件之一,旨在为土木工程设计部门提供一套完整.智能化.自 ...查看


  • 南方cass三角网计算土方量流程总结
  • 南方CASS 方格网计算土方量流程总结 一. 方格网计算由三个要素组成:计算范围+原地面标高数据文件+完成面标高三角网 二. 计算范围 计算范围一定要用复合线(PL )画,且最后闭合(CAD 按c 闭合): 三. 生成原地面标高数据文件 要 ...查看


  • HTCAD土方计算软件土方计算过程
  • 方格网法 1. 规划场区 (就是圈面积) (采集离散点) 2. 布置方格网(注意场区也就是田块的距离) 3. 计算自然标高 4. 土方优化设计 5. 输入设计标高 6. 优化土方设计(三角点法 也就是说一中 俩边) 填完进行计算 7. 计算 ...查看


  • 土地平整项目中土方量计算方法比较
  • 龙源期刊网 http://www.qikan.com.cn 土地平整项目中土方量计算方法比较 作者:刘双 汪明 来源:<科技创新与应用>2014年第26期 摘 要:在工程施工中,如何对土方进行准确测量,以及合理利用土方量计算方法 ...查看


  • 土方量计算 1
  • 土建工程工程量计算规则公式汇总 分享 作者:一只草履虫 已被分享15次 评论(0) 复制链接 分享 转载 举报 平整场地: 建筑物场地厚度在±30cm以内的挖.填.运.找平. 1.平整场地计算规则 (1)清单规则:按设计图示尺寸以建筑物首层 ...查看


  • 土方计算方法
  • 三.土方工程的有关说明: 1. 本章子目未包括地下水位以下施工的排水费用,发生时另行计算.挖土方时如有地表水需要排除时,亦应另行计算. 2. 平整场地是指建筑场地挖.填土方厚度在±30cm 以内的挖.填.运.找平.挖.填土方厚度超过±30c ...查看


  • 工程量清单计算公式
  • [转] 工程量计算规则公式汇总 工程量计算规则公式汇总 土建工程工程量计算规则公式汇总 平整场地: 建筑物场地厚度在±30cm以内的挖.填.运.找平. 1.平整场地计算规则 (1)清单规则:按设计图示尺寸以建筑物首层面积计算. (2)定额规 ...查看


  • 基坑.基槽土方量计算
  • 复习指导--基坑.基槽土方量简易计算 基坑.基槽土方开挖,如何较简便.准确.快捷计算土方量,作为安排施工进度计划.编制预算和进行工程验收.结算的依据,是施工中需要解决的一个技术问题,以下简介简易计算方法. 1.基坑土方量计算 挖基坑多用于需 ...查看


  • 建筑工程工程量计算规则公式汇总
  • 建筑工程量计算规则公式汇总 一.平整场地 建筑物场地厚度在±30cm以内的挖.填.运.找平. 1.平整场地计算规则 (1)清单规则:按设计图示尺寸以建筑物首层面积计算. (2)定额规则:按设计图示尺寸以建筑物首层面积计算. 2.平整场地计算 ...查看


  • 清单规则与定额规则
  • 清单规则与定额规则02 1.平整场地计算规则 (1)清单规则:按设计图示尺寸以建筑物首层面积计算. (2)定额规则:按设计图示尺寸以建筑物首层面积计算. 2.平整场地计算方法 (1)清单规则的平整场地面积:清单规则的平整场地面积=首层建筑面 ...查看


热门内容