高压锅炉给水泵改造项目

田 静

(北京美信东方工程技术有限公司,北京 100125)

摘 要:国外某化工厂一台高压锅炉给水泵被搬迁回国内,计划用于某甲醇项目。由于该泵已经运行几十年并搁置过一段时间,为了使其在国内条件下能继续工作,必须对其进行改造。首先对泵体本身进行拆检试验,检查各零件的使用情况,更换损坏部件;其次根据国情和现场情况配置辅助设施;最后对改造后的泵机组进行试验。结果表明,经过改造后的泵能够满足工艺要求,效率达到改造预期目标。对于改造项目,详尽周密的计划是基础,认真细致的态度是保障,及时有效的沟通配合是关键。

关键词:高压锅炉给水泵;改造;拆检;试验中图分类号:TK223.52  文献标志码:B  文章编号:1003–6490(2016)06–0010–05

High Pressure Boiler Feed Water Pump Modification Project

Tian Jing

Abstract:One set of high pressure boiler feed water pump is relocated to China from an offshore chemical plant and is planned to be used in a methanol project.Since the pump had been worked for several decades then left unused for some time,it has to be modified to be able to rework in local conditions.Firstly,dismantle the pump,check each part and replace the worn one.Secondly,select auxiliary accessories suitable for Chinese standard and site condition.Finally,test the modified pump set.Test result shows that the modified pump can meet process request,efficiency reaches the predicted object.Generally speaking,for the modification project,the basis is detailed plan,the guarantee is careful attitude,the key is prompt and efficient communication and cooperation.

Key words:high pressure boiler feed water pump;modification;dismantle and check;test1 项目概况

青海桂鲁化工有限公司(以下简称用户),从加拿大某化工厂搬迁一台高压锅炉给水泵,经过大修整改后用于青海80万t/a甲醇项目。本人作为设计代表,有幸参与该项目的设计、

采购、出厂验收阶段,现将改造过程的一些心得体会总结如下,供同行借鉴。2 改造步骤

首先了解待改造泵的原有设计信息,见表1。

表1 高压锅炉给水泵原有信息表

制造厂生产年份系列号型号尺寸(inch)

苏尔寿宾汉姆泵有限公司(Sulzer Bingham Pumps,Inc.)

19814A843CP-D 8级6×8×10.5

流量(m3/h)扬程/m

3571 500

介质温度/℃水压试验压力/kPa

止推轴承径向轴承机械密封型号

94.731 710倾斜瓦块式JHJ-5

滑动轴承8B1

机械密封冲洗方案

联轴器驱动机功率/kW润滑方式冷却方案

方案-23系列-71,尺寸-562

1 865强制润滑方案-J(API610-5th)

转速/r·min-1)4 400效率%/介质比重

780.953

其次,了解待改造泵的现有状态。从青海现场拍摄的照片看,可见部件的总体状态一般,外部喷漆状态一般,各项标识明显可见,大部分温度表、压力表已损坏,部分管路已断开。原驱动机形式为蒸汽透平,现改用电机驱动,所以原驱动机未拆回。

3.1 电气部分整改

由于原驱动机为蒸汽透平,用户要求改用电机驱动,所以驱动机需要重新设计。设计方提出电机的技术要求:防爆等级:dIICT1;防护等级:IP55;电压等级:10kV;安装海拔高度:2 597m;配置定子绕组、轴承测温装置,轴承测振装置。改造方负责电机选型。

3.2 辅助系统整改

辅助系统包括润滑油系统、密封系统、冷却水系统。

3.2.1 润滑油系统整改

图1 高压锅炉给水泵外观图

接下来,选择国内泵厂负责改造该泵。该泵规格较大,系统复杂,需要有能力、有实力的厂家承接该项目。经过评标,选定大连苏尔寿泵及压缩机有限公司(以下简称改造方)。3 制定初步改造方案

掌握了待改造泵的现状,用户、设计方和改造方三方共同制定泵的初步改造方案。改造工作主要包括:电气部分整改;辅助系统整改;机械部分整改;组装试运转等。

收稿日期:2016–06–01作者简介:田静(1976—) ,女,河北涿州人,机械工程硕士,工程师,

主要从事机泵专业的设计管理工作。

原润滑系统是为泵和蒸汽透平提供润滑油的,而新配电机在润滑油的压力和油量方面与原蒸汽透平肯定不同;加之改造后新增变速箱,此设备的润滑油量原系统未考虑;并且原润滑系统中的电仪设备(包括油泵电机、控制仪表)的设计标准与中国不同,例如电压、频率等;从现场照片看,系统内大部分仪表已损坏,而且原润滑油站布置在泵底座上、泵非驱动端轴承箱下方,空间有限,维修存在一定困难;综合以上因素,润滑油系统必须新购。

设计方提出润滑油系统的技术要求:服务对象:电机、齿轮箱、泵;系统接油部件材质:不锈钢;主要仪表:液位/温度/压力/压差传感器;仪表的防爆/防护等级:dIICT4/IP65;仪表品牌:合资品牌;电机的防爆/防护等级:dIICT1/IP55;电机安装海拔高度:2 597m;系统安装形式:撬块安装。由改造方负责系统选型。

3.2.2 密封系统整改

原泵所配机械密封,需泵解体后才能检查,必要时可以委托密封厂家进行检查。是否能够继续使用,待检查后确定。

·10

·

Chemical Engineering Design Communications

化 工 设 计 通 讯

Coal Cemical Methanol

煤化工与甲醇第42卷第6期

2016年6月

机封冲洗系统中的换热器外观状态一般,也需要解体后判断是否能够继续使用。由改造方负责解体检查。

3.2.3 冷却水系统整改

原冷却水系统为机械密封的换热器及润滑油站的换热器提供冷却,仅包括一些管路、阀门。润滑油站需要新购,油站撬块范围内的冷却水管路由油站供应商负责;机械密封的换热器是否能继续使用还待定,所以冷却水系统暂定为拆卸检查,并修复。

3.3 机械部分整改

机械部分整改包括底座、变速箱、联轴器的整改及泵体拆卸检查。

3.3.1 底座

流衬套内径。

(6)通过加热,依次拆卸第1级叶轮,第1和2级叶轮间的隔套,第5级叶轮,第2级叶轮,第6、7、8级叶轮,第3、4级叶轮。测量各级叶轮口环尺寸。

(7)通过加热,拆卸中间轴套,测量轴套外径和中间衬套内径。

(8)检查轴的各部位尺寸,进行同轴度检查。(9)清洁所有零部件并对其外观和尺寸进行检查。

(10)编写拆检报告,详述零件拆卸后状况和需要修理或更换的细节资料。

3.4 组装、试运转

由于驱动机形式改为电机,而且要新增变速箱,原底座的长度肯定不够,所以底座需要重新设计。设计方提出底座的技术要求:设计标准:API 610;底座大小:应将所有设备投影包含在底座范围内;附件:接地耳,吊耳,调整螺栓,地脚螺栓。由改造方负责设计。

3.3.2 变速箱

变速箱为新增设备,需要把泵转速增加到4 400r/min。速比和功率待电机选型后确定。由改造方负责选型。

3.3.3 联轴器

由于电机和变速箱都新购,原有联轴器无法与新设备匹配,所以泵与变速箱之间、变速箱与电机之间的联轴器都需要重新选型。设计方提出联轴器的技术要求:联轴器形式:弹性膜片式联轴器;联轴器应设计成能够承受最大驱动功率的125%负荷;联轴器护罩材质:无火花型。由改造方负责选型。

3.3.4 泵体拆检

泵体拆检按照API 610标准及改造方的技术要求进行。改造方各相关专业做好检修配合工作,准备好检修作业所需的相关机具、材料和作业文件。泵体拆检主要包括以下步骤:(1)主泵拆卸、吊装,将泵头移出底座,支撑泵头,做拆解标记。

(2)拆卸驱动端和非驱动端轴承箱体。检查推力轴承和径向轴承的磨损情况。

(3)拆卸驱动端和非驱动端机械密封。检查静环和动环的磨损情况。

(4)拆除非驱动端大端盖和驱动端压盖,将内筒体从壳体中抽出。拆除内筒体上盖,将转子总成吊离下盖,放置在专用的V型工作架上。对主要零件做标记。

(5)通过加热,拆卸节流轴套,测量节流轴套外径和节

泵体的各个零件经过必要的修理或更换后,重新组装。主要包括以下步骤:

(1)依次安装叶轮轮毂口环和叶轮口环,并用螺钉固定。(2)依次安装各级叶轮、级间中间轴套、隔套轴套和节流轴套。

(3)转子总成做动平衡试验,平衡精度G2.5级。(4)内筒体上下盖做流道检查。(5)将转子总成安装到下盖上,安装中间衬套,级间隔套,节流衬套。

(6)安装新的中开面密封垫。

(7)安装上盖,安装中开面紧固螺栓、螺母。(8)将内筒体吊进外筒体,安装端盖和压盖。(9)安装两端机械密封。

(10)组装两端轴承部件,检测轴心。如有需要重新打定位销。

(11)安装两端轴承箱体。

(12)泵体组装好后,进行整机试验,考查各项性能是否达到原厂设计值。要求泵效率不应低于原泵设计值的90%~ 95%。

4 确定补充改造方案

4.1 新购设备、系统选型

改造方根据初步改造方案,进行新购设备、系统的选型,将选型方案提交设计方和用户审查,见表2。

配套设备、系统的技术选型方案三方达成一致后,考虑到电机和润滑油站的商务报价较高,用户决定自行采购电机和润滑油站,由改造方负责整套机组的配套布置,并由改造方负责总成整套机组的图纸资料。润滑油站与泵底座之间的润滑油连接管路由用户提供。

4.2 泵体检查报告

表2 新购设备、系统选型

序号1

零件描述电机

单位台

数量1

备注

YAKK710-2W,2240kW,10kV,ExeIICT1,IP55,B3,转速:2 950 r/min,滑动轴承,强制润滑,安装海拔高度2 800m,

带温度、振动报警等,仪表接线汇总到接线箱。不锈钢材质。配温度报警、压力报警、差压报警等。齿轮箱油量要求为:90L/min;泵要求:40Lmin;电机要求基本与泵相同。

压力不低于0.2MPa,正常压力为0.6MPa,

最高压力不超过1MPa。所有仪表接线汇总到接线箱。功率2 240kW,输入转速2 950r/min,输出转速4 400 r/min。

带有温度报警、振动报警等。带有阀门、法兰、孔板、流动指示器、压力表、温度表等

电机与变速箱、泵与变速箱之间各一个

带有阀门、法兰、流动指示器等

供应商

南阳防爆集团股份有限公司

2润滑油站套1

上海利安润滑设备有限公司

34567

变速箱油管路

(泵底板范围内)

联轴器冷却水管路(泵底板范围内)

底座

台套套套件

11211

南京高速齿轮箱厂

国产大连挠叠联轴器厂

国产大连苏尔寿

备注1.根据相关电气标准,高压10kV,2 240kW电机无法同时做到隔爆型(d),C组别。经过与设计方及电机制造厂沟通,电机防爆等级调整为增安型(ExeIICT1)。

2.机械密封经拆检后发现密封环磨损严重,机封换热器经拆检后发现换热管堵塞,两者均需要换新。新购换热器对冷却水的压力、流量及连接位置的要求必定与原有系统不同,所以冷却水系统最终确定为重新设计。

·11·

第42卷第6期

2016年6月

Coal Cemical Methanol

煤化工与甲醇

Chemical Engineering Design Communications

化 工 设 计 通 讯

改造方提供了泵体的拆检报告。拆检报告格式如下:

表3 泵体拆卸检查报告

零件号[***********][1**********]2 113……

零件描述内部壳体螺杆螺母圆锥销衬套(内壳体与端盖之间)帽型螺母定位销垫片垫片(内部壳体调整)外壳体驱动端压盖

……

数量[1**********]11……

能否继续使用(是/否)

是是是是是是是否否是是……

状态一般一般一般一般一般

维修/更换建议清洁后使用清洁后使用清洁后使用清洁后使用清洁后使用

零件号[***********][***********]400

差一般一般……

需要更换清洁后使用清洁后使用

……

表4 必需更换的零件清单

零件描述垫片

垫片(内部壳体调整)

O型圈垫片垫片垫片节流轴套肩挡圈径向轴承O型圈呼吸器折流盘机械密封

数量[1**********]32

带2台换热器

备注

一般需要更换一个,其(一个损坏)他的清洁后使用

一般差

清洁后使用需要更换

备注1.没有出现在必需更换零件清单中的零件(主要是螺栓、螺母、垫片),改造方承诺如果这些零件确实需要更换,则由改造方免费负责更换,并保证更换零件的规格、材质与原制造厂一致。

报告显示,所有的垫片、O型圈都磨损严重,径向轴承生锈并磨损,驱动端和非驱动端机械密封的密封面磨损严重,等等。必需更换的零件清单见表4。其他零部件状态一般,清洁后可继续使用。

表4中更换零件的费用由用户提供。改造方保证更换零件的规格、材质、数量、零件号均与原制造厂一致。除机械密封外,其他零件均从国外进口。用户要求改造方将更换掉的零件随主机一起发货。

同时改造方提供了泵尺寸检查报告,见表5。改造方还提供了轴的同轴度检查报告,见表6。

在补充协议中,还确定泵机组和润滑油站的运输方式分

表5 泵尺寸检查报告 单位(mm)

Stg5Stg6Stg7Stg8Stg4Stg3Stg2Stg1

位置AB

描述

泵壳入口口环内径叶轮入口口环外径间隙=(A-B)

首级165.07/165.09164.62~63/164.650.44~0.45/0.44

NANANA81.6181.66-0.05101.60101.250.35

2级155.57155.11~170.40~0.46117.46116.95~980.48~0.5181.9682.03-0.07

3级155.56155.150.41117.49117.020.4782.08~0982.15-0.07~-0.06中间衬套内径中间轴套外径

间隙

4级155.57155.15~230.34~0.42

NA117.02NA82.2682.29-0.03114.30113.980.32

5级155.57155.120.45117.481170.4881.8781.9-0.03

6级155.56155.230.33117.491170.49

7级155.59155.20.39117.471170.47

8级155.57155.19~260.31~0.38

NA117.02NA82.2582.28-0.03

CD

泵壳轮毂口环内径叶轮轮毂口环外径间隙=(C-D)

EF

叶轮内径相对应轴径间隙=(E-F)

81.98~82.0082.11~14

82.03

82.15

-0.05~-0.03-0.04~-0.01隔套内径隔套轴套外径

间隙

101.57101.350.22

HI

节流衬套内径节流轴套外径间隙=(H-I)

结论:上述间隙均在磨损范围内,可以不用更换。

表6 同轴度检查报告 单位(mm)

轴上联轴器键槽处为零位,从驱动端看逆时针旋转

从驱动端看V型块定位

12345678

位置读数角度(度)结论

1+0.030

2+0.03270

3+0.030

4+0.03270

5+0.040

6+0.0250

7+0.02270

8+0.010

位置5圆跳动稍微偏大,还在允许范围内,可以继续使用。

·12·

别为整体撬块运输。5 出厂试验

补充改造方案确定后,改造方和用户分别采购新材料和设备。由用户采购的电机发货到改造方,由改造方装配完毕后,准备出厂试验。

5.1 试验前的准备工作

(2)1h后,启泵。平稳提高流量,随着流量增加,噪声增大,判断有汽蚀发生。在流量为182.9m3/h时,现场测转速为4 535r/min。到达正常流量272m3/h时,止推轴承温度为80℃。到达额定流量357m3/h时,止推轴承温度已达100℃,被迫停机。整个过程大约5min。

5.4 故障分析

(1)故障现象

止推轴承箱的油气分离器有白烟冒出,初步判断轴瓦烧了。拆除轴承箱回油管,发现没有油流出,油路没通,轴承没有得到充分的润滑和冷却,所以温升过快过高。(2)故障原因

启泵前,油路循环时没有仔细观察回油管视镜中润滑油的流动情况,造成止推轴承润滑油流动不畅。将进油管接到轴承箱另一侧的进油口,此时回油口有油流出,伴随大量白烟。检查左右两侧进油口,发现直径不等。试验时连接的进油口

5.2 试验前需注意的几点直径小,约Φ8mm,另一侧进油口较大,约Φ14mm。(1)由于额定转速4 400r/min,超过测试台程序默认最大(3)故障后果转速3 000r/min,所以决定在自动生成的性能测试报告上手改将泵移出试验台。拆开止推轴承检查,发现轴瓦烧损。转速,不影响其他参数。轴承箱的回油口有点阻塞。(2)泵的进口压力为0.25MPa(G),NPSHa为12m,NPSHr 机组额定点的振动、温升、噪音及转速没来得及测量。在额定流量时为9m。但是试验台上泵进口是抽吸状态,不能(4)解决办法保证泵的设计NPSHa,试验时有发生汽蚀的可能性。更换轴承。由于进口轴承供货周期长,为满足本项目泵(3)由于合同油站尺寸较大(3m×2.05m),试验车间的交货期要求,经协调,改造方将其他进口合同中的同型号轴地坑放不下,所以泵和电机使用试验台油站供油,齿轮箱借承借调来使用。用其他合同油站供油(试验台油站不能同时满足泵、齿轮箱、(5)重新试验电机用油)。齿轮箱借用油站的供油量比需油量少20L/min,更换止推轴承后,重新做试验。此次试验,泵的振动值齿轮箱轴承温度有可能过高。控制在7.1mm/s以内、轴承温度控制在85℃以内,噪声正常。(4)考虑上述因素,初步决定试验时间为30min。性能试验采集了10个点,从小流量点到额定点。泵性能试验5.3 出厂试验报告见表7,性能曲线见图2。试验报告显示,额定点的流量

扬程满足原泵设计要求,泵效率计算值(76.3%)是原泵效率(1)启动油站,润滑油循环,检查各回油管视镜是否有

油流动。

表7 泵性能试验记录单

大连苏尔寿第1页,共1页试验日期规定数据

额定流量额定扬程流量电磁

转速手持单位\序号r/minm3/hm3/hkPamMPammmmkWkWkW%试验纪要:运转试验时间:30 min

12-14-2011357m/h1 500 m

入口压力变送器14 400102.4102.4-21.38-2.1818.961 9340.091 9361 9361 2371 1631 16346.4

3

(1)泵、电机、齿轮箱主体设备在底座上就位。检查电机、

齿轮箱等新购设备的供货范围、铭牌参数,确保与批复图纸一致。

(2)调平、对中转子,固定泵、电机、齿轮箱后,安装联轴器。(3)检查冷却水管路,确保与批复图纸一致。(4)检查润滑油管路,确保与批复图纸一致。(5)检查主电缆连接。

(6)检查泵进出口管线连接。(7)试验台水池注水,油站注油。

制造号

泵性能试验记录单

泵型号合同号

试验标准额定转速额定效率出口压力变送器24 400182.9182.9-21.65-2.2118.61 8970.291 9001 9001 5491 4561 45664.9

4 400 r/min78%

试验电机2 240 kW

34 400221.5221.5-22.16-2.2618.211 8570.421 8601 8601 6931 5911 59170.5

功率电功率44 400250.5250.5-22.49-2.2917.81 8160.541 8181 8181 7781 6711 67174.2

额定功率试验水温12.6 ℃54 400272.3272.3-23.05-2.3517.351 7700.641 7731 7731 8521 7411 74175.5

1 781kW入口高差0 m64 400274274-22.94-2.3417.321 7670.651 7701 7701 8681 7561 75675.2

出口高差0 m74 400290.6290.6-23.54-2.416.941 7280.731 7311 7311 8951 7811 78176.9

API 610

工位号

叶轮直径试验回路入口管径出口管径

84 400351.5351.5-25.24-2.5715.51 5821.061 5861 5862 0561 9331 93378.5

4A843CP-D6×8×10.5

P-2481

280mm开式200 mm150 mm94 400358.3358.3-25.68-2.6215.151 5451.11 5491 5492 1071 9801 98076.3

104 400363.1363.1-25.71-2.6215.115411.141 5451 5452 1091 9821 98277

测试方法

试验项目试验转速泵流量额定转速下泵流量吸入水头表读数吸入水头米水柱吐出水头表读数吐出水头米水柱速度水头差泵总扬程额定转速下总扬程电机输入功率泵轴功率额定转速下泵轴功率

泵效率

用户代表验收代表试验代表改造方代表

(下转第17页)

·13·

参考文献

[1] 张清明.高温阀门的设计与计算[J].通用机械,2008,(2).[2] 戴宁生,陆文龙,周桂生.三维CAD技术的推广与应用[J].机械制造与自动化,2007,(6).

[3] 鲍晓兵.船闸闸阀门液压启闭系统[J].液压气动与密封,2007,(6).

[4] 杨志峰,雷玉勇,熊佳,等.基于VB的工业阀门应用程序设计[J].机械设计与制造.2007,(12).

(上接第9页

图3 点火器

火焰检测系统:

火焰检测系统采用新一代智能火检,由光导管型火检探头、智能火检处理箱和冷却风管等组成,结构简单、操作方便,性能可靠,可长期连续检测各种燃气、燃油,是锅炉安全监控系统不可缺少的检测设备。

点火控制系统:更换就地点火控制柜并增加DCS远程控制点,如增加点火枪控制指令、甲醇阀控制指令、雾化阀控制指令、吹扫阀控制指令、点火器控制指令等。

3.3 安全注意事项

严重浪费资源。

改造后甲醇点火运行情况:

柏坡正元于2015年11月5日150t锅炉一次点火成功,下午16:30先西侧点火枪一次点燃成功,下午17:00东侧点火枪一次点燃成功。晚上9:00炉床温度升至550℃后,锅炉开

3

始投煤,甲醇点火系统关闭。本次甲醇点火共使用甲醇12m(按

。停用后用脱盐水置换甲甲醇密度0.8t/m3计算消耗甲醇9.6t)

醇管路,保证了停用后点火系统的安全。

通过甲醇点火和柴油点火的对比(见表1),发现本次甲醇点火用90%粗甲醇9.6t,成本约1 560元/t,费用约1.497 6万元,以往采用柴油点火用0#柴油4.5t,均价5 000元/t,费用约2.25万元,一次点火节约成本7 524元左右。同时点火时锅炉无黑烟冒出,降低了燃料燃烧排放的烟气对布袋的污染。

表1 成本比较(按照1台150t锅炉一次点火成本)

名称柴油甲醇

消耗(t)4.59.6

价格 5 0001 560

总消耗(元)22 50014 976

甲醇支管进甲醇喷枪前设置止逆阀,防止甲醇回火。

考虑点火完成后,甲醇储罐和甲醇外送管道的安全性,可用压缩空气吹尽管道内残留甲醇(至锅炉燃烧),再拆除甲醇管道两端法兰连接处加盲板隔断锅炉与甲醇储罐的连接。4 改造前后运行情况比较

改造前150t锅炉一次点火需消耗柴油4.5t,点火时长8h。点火时黑烟冒出,且当时油价较高,一次点火费用居高不下,

从表1可以看出,甲醇较柴油节省22 500-14 976=7 524元。5 结论

本项目共投资23.4万元,投资不高,此项目适合于化肥企业联产甲醇项目,可利用自身产的甲醇,成本更低,且此系统的安全和消防可依托原有安全和消防系统,不必增加额外投资。

依据此甲醇点火装置运行结果表明此装置安全可靠环保,使用经济,为改造锅炉点火系统的化工厂提供了技术保障。

(上接第13页)

泵性能曲线(Pump Performance Curves)

[1**********]0H(m)1800

[1**********]0

2100

Pa(kW)

[1**********]0

9080η(%)70

[1**********]00

Q(m3/h)

[***********][***********]420450

900

值(78%)的97.8%,说明泵维修改造是成功的。6 涂漆、包装、发货

出厂试验合格后,泵体喷漆,整套泵机组撬块包装、运输至现场。现场安装调试由用户主导,改造方提供指导。7 结束语

此台高压锅炉给水泵改造历时一年多,通过改造方,设计方,用户共同努力,不断完善改造方案,发现问题,及时讨论,解决问题,最终改造后的泵成功运行,为项目按时投产做好准备。就改造过程出现的问题总结以下几点,供大家借鉴。

1)进口高压锅炉给水泵在服役20多年后,通过更换易损件,性能仍能达标,说明进口泵的品质良好,值得国内泵企业学习。

2)泵利旧改造有风险,一旦改造不成功,既造成经济损失,又耽误工期,所以泵改造前应做充分的技术经济 分析。

3)细节决定成败。改造过程中的每一个细节都不能疏忽,否则可能造成严重后果。

4)改造项目历时长,牵扯面多,沟通协调、互相配合非常重要。

5)本次改造由于苏尔寿内部规定,更换零件只能进口。以后类似改造,在保证质量的前提下,可以考虑国产。

图2 泵性能试验曲线

·17·

第42卷第6期

2016年6月

Coal Cemical Methanol

煤化工与甲醇

Chemical Engineering Design Communications

化 工 设 计 通 讯

高压锅炉给水泵改造项目

田 静

(北京美信东方工程技术有限公司,北京 100125)

摘 要:国外某化工厂一台高压锅炉给水泵被搬迁回国内,计划用于某甲醇项目。由于该泵已经运行几十年并搁置过一段时间,为了使其在国内条件下能继续工作,必须对其进行改造。首先对泵体本身进行拆检试验,检查各零件的使用情况,更换损坏部件;其次根据国情和现场情况配置辅助设施;最后对改造后的泵机组进行试验。结果表明,经过改造后的泵能够满足工艺要求,效率达到改造预期目标。对于改造项目,详尽周密的计划是基础,认真细致的态度是保障,及时有效的沟通配合是关键。

关键词:高压锅炉给水泵;改造;拆检;试验中图分类号:TK223.52  文献标志码:B  文章编号:1003–6490(2016)06–0010–05

High Pressure Boiler Feed Water Pump Modification Project

Tian Jing

Abstract:One set of high pressure boiler feed water pump is relocated to China from an offshore chemical plant and is planned to be used in a methanol project.Since the pump had been worked for several decades then left unused for some time,it has to be modified to be able to rework in local conditions.Firstly,dismantle the pump,check each part and replace the worn one.Secondly,select auxiliary accessories suitable for Chinese standard and site condition.Finally,test the modified pump set.Test result shows that the modified pump can meet process request,efficiency reaches the predicted object.Generally speaking,for the modification project,the basis is detailed plan,the guarantee is careful attitude,the key is prompt and efficient communication and cooperation.

Key words:high pressure boiler feed water pump;modification;dismantle and check;test1 项目概况

青海桂鲁化工有限公司(以下简称用户),从加拿大某化工厂搬迁一台高压锅炉给水泵,经过大修整改后用于青海80万t/a甲醇项目。本人作为设计代表,有幸参与该项目的设计、

采购、出厂验收阶段,现将改造过程的一些心得体会总结如下,供同行借鉴。2 改造步骤

首先了解待改造泵的原有设计信息,见表1。

表1 高压锅炉给水泵原有信息表

制造厂生产年份系列号型号尺寸(inch)

苏尔寿宾汉姆泵有限公司(Sulzer Bingham Pumps,Inc.)

19814A843CP-D 8级6×8×10.5

流量(m3/h)扬程/m

3571 500

介质温度/℃水压试验压力/kPa

止推轴承径向轴承机械密封型号

94.731 710倾斜瓦块式JHJ-5

滑动轴承8B1

机械密封冲洗方案

联轴器驱动机功率/kW润滑方式冷却方案

方案-23系列-71,尺寸-562

1 865强制润滑方案-J(API610-5th)

转速/r·min-1)4 400效率%/介质比重

780.953

其次,了解待改造泵的现有状态。从青海现场拍摄的照片看,可见部件的总体状态一般,外部喷漆状态一般,各项标识明显可见,大部分温度表、压力表已损坏,部分管路已断开。原驱动机形式为蒸汽透平,现改用电机驱动,所以原驱动机未拆回。

3.1 电气部分整改

由于原驱动机为蒸汽透平,用户要求改用电机驱动,所以驱动机需要重新设计。设计方提出电机的技术要求:防爆等级:dIICT1;防护等级:IP55;电压等级:10kV;安装海拔高度:2 597m;配置定子绕组、轴承测温装置,轴承测振装置。改造方负责电机选型。

3.2 辅助系统整改

辅助系统包括润滑油系统、密封系统、冷却水系统。

3.2.1 润滑油系统整改

图1 高压锅炉给水泵外观图

接下来,选择国内泵厂负责改造该泵。该泵规格较大,系统复杂,需要有能力、有实力的厂家承接该项目。经过评标,选定大连苏尔寿泵及压缩机有限公司(以下简称改造方)。3 制定初步改造方案

掌握了待改造泵的现状,用户、设计方和改造方三方共同制定泵的初步改造方案。改造工作主要包括:电气部分整改;辅助系统整改;机械部分整改;组装试运转等。

收稿日期:2016–06–01作者简介:田静(1976—) ,女,河北涿州人,机械工程硕士,工程师,

主要从事机泵专业的设计管理工作。

原润滑系统是为泵和蒸汽透平提供润滑油的,而新配电机在润滑油的压力和油量方面与原蒸汽透平肯定不同;加之改造后新增变速箱,此设备的润滑油量原系统未考虑;并且原润滑系统中的电仪设备(包括油泵电机、控制仪表)的设计标准与中国不同,例如电压、频率等;从现场照片看,系统内大部分仪表已损坏,而且原润滑油站布置在泵底座上、泵非驱动端轴承箱下方,空间有限,维修存在一定困难;综合以上因素,润滑油系统必须新购。

设计方提出润滑油系统的技术要求:服务对象:电机、齿轮箱、泵;系统接油部件材质:不锈钢;主要仪表:液位/温度/压力/压差传感器;仪表的防爆/防护等级:dIICT4/IP65;仪表品牌:合资品牌;电机的防爆/防护等级:dIICT1/IP55;电机安装海拔高度:2 597m;系统安装形式:撬块安装。由改造方负责系统选型。

3.2.2 密封系统整改

原泵所配机械密封,需泵解体后才能检查,必要时可以委托密封厂家进行检查。是否能够继续使用,待检查后确定。

·10

·

Chemical Engineering Design Communications

化 工 设 计 通 讯

Coal Cemical Methanol

煤化工与甲醇第42卷第6期

2016年6月

机封冲洗系统中的换热器外观状态一般,也需要解体后判断是否能够继续使用。由改造方负责解体检查。

3.2.3 冷却水系统整改

原冷却水系统为机械密封的换热器及润滑油站的换热器提供冷却,仅包括一些管路、阀门。润滑油站需要新购,油站撬块范围内的冷却水管路由油站供应商负责;机械密封的换热器是否能继续使用还待定,所以冷却水系统暂定为拆卸检查,并修复。

3.3 机械部分整改

机械部分整改包括底座、变速箱、联轴器的整改及泵体拆卸检查。

3.3.1 底座

流衬套内径。

(6)通过加热,依次拆卸第1级叶轮,第1和2级叶轮间的隔套,第5级叶轮,第2级叶轮,第6、7、8级叶轮,第3、4级叶轮。测量各级叶轮口环尺寸。

(7)通过加热,拆卸中间轴套,测量轴套外径和中间衬套内径。

(8)检查轴的各部位尺寸,进行同轴度检查。(9)清洁所有零部件并对其外观和尺寸进行检查。

(10)编写拆检报告,详述零件拆卸后状况和需要修理或更换的细节资料。

3.4 组装、试运转

由于驱动机形式改为电机,而且要新增变速箱,原底座的长度肯定不够,所以底座需要重新设计。设计方提出底座的技术要求:设计标准:API 610;底座大小:应将所有设备投影包含在底座范围内;附件:接地耳,吊耳,调整螺栓,地脚螺栓。由改造方负责设计。

3.3.2 变速箱

变速箱为新增设备,需要把泵转速增加到4 400r/min。速比和功率待电机选型后确定。由改造方负责选型。

3.3.3 联轴器

由于电机和变速箱都新购,原有联轴器无法与新设备匹配,所以泵与变速箱之间、变速箱与电机之间的联轴器都需要重新选型。设计方提出联轴器的技术要求:联轴器形式:弹性膜片式联轴器;联轴器应设计成能够承受最大驱动功率的125%负荷;联轴器护罩材质:无火花型。由改造方负责选型。

3.3.4 泵体拆检

泵体拆检按照API 610标准及改造方的技术要求进行。改造方各相关专业做好检修配合工作,准备好检修作业所需的相关机具、材料和作业文件。泵体拆检主要包括以下步骤:(1)主泵拆卸、吊装,将泵头移出底座,支撑泵头,做拆解标记。

(2)拆卸驱动端和非驱动端轴承箱体。检查推力轴承和径向轴承的磨损情况。

(3)拆卸驱动端和非驱动端机械密封。检查静环和动环的磨损情况。

(4)拆除非驱动端大端盖和驱动端压盖,将内筒体从壳体中抽出。拆除内筒体上盖,将转子总成吊离下盖,放置在专用的V型工作架上。对主要零件做标记。

(5)通过加热,拆卸节流轴套,测量节流轴套外径和节

泵体的各个零件经过必要的修理或更换后,重新组装。主要包括以下步骤:

(1)依次安装叶轮轮毂口环和叶轮口环,并用螺钉固定。(2)依次安装各级叶轮、级间中间轴套、隔套轴套和节流轴套。

(3)转子总成做动平衡试验,平衡精度G2.5级。(4)内筒体上下盖做流道检查。(5)将转子总成安装到下盖上,安装中间衬套,级间隔套,节流衬套。

(6)安装新的中开面密封垫。

(7)安装上盖,安装中开面紧固螺栓、螺母。(8)将内筒体吊进外筒体,安装端盖和压盖。(9)安装两端机械密封。

(10)组装两端轴承部件,检测轴心。如有需要重新打定位销。

(11)安装两端轴承箱体。

(12)泵体组装好后,进行整机试验,考查各项性能是否达到原厂设计值。要求泵效率不应低于原泵设计值的90%~ 95%。

4 确定补充改造方案

4.1 新购设备、系统选型

改造方根据初步改造方案,进行新购设备、系统的选型,将选型方案提交设计方和用户审查,见表2。

配套设备、系统的技术选型方案三方达成一致后,考虑到电机和润滑油站的商务报价较高,用户决定自行采购电机和润滑油站,由改造方负责整套机组的配套布置,并由改造方负责总成整套机组的图纸资料。润滑油站与泵底座之间的润滑油连接管路由用户提供。

4.2 泵体检查报告

表2 新购设备、系统选型

序号1

零件描述电机

单位台

数量1

备注

YAKK710-2W,2240kW,10kV,ExeIICT1,IP55,B3,转速:2 950 r/min,滑动轴承,强制润滑,安装海拔高度2 800m,

带温度、振动报警等,仪表接线汇总到接线箱。不锈钢材质。配温度报警、压力报警、差压报警等。齿轮箱油量要求为:90L/min;泵要求:40Lmin;电机要求基本与泵相同。

压力不低于0.2MPa,正常压力为0.6MPa,

最高压力不超过1MPa。所有仪表接线汇总到接线箱。功率2 240kW,输入转速2 950r/min,输出转速4 400 r/min。

带有温度报警、振动报警等。带有阀门、法兰、孔板、流动指示器、压力表、温度表等

电机与变速箱、泵与变速箱之间各一个

带有阀门、法兰、流动指示器等

供应商

南阳防爆集团股份有限公司

2润滑油站套1

上海利安润滑设备有限公司

34567

变速箱油管路

(泵底板范围内)

联轴器冷却水管路(泵底板范围内)

底座

台套套套件

11211

南京高速齿轮箱厂

国产大连挠叠联轴器厂

国产大连苏尔寿

备注1.根据相关电气标准,高压10kV,2 240kW电机无法同时做到隔爆型(d),C组别。经过与设计方及电机制造厂沟通,电机防爆等级调整为增安型(ExeIICT1)。

2.机械密封经拆检后发现密封环磨损严重,机封换热器经拆检后发现换热管堵塞,两者均需要换新。新购换热器对冷却水的压力、流量及连接位置的要求必定与原有系统不同,所以冷却水系统最终确定为重新设计。

·11·

第42卷第6期

2016年6月

Coal Cemical Methanol

煤化工与甲醇

Chemical Engineering Design Communications

化 工 设 计 通 讯

改造方提供了泵体的拆检报告。拆检报告格式如下:

表3 泵体拆卸检查报告

零件号[***********][1**********]2 113……

零件描述内部壳体螺杆螺母圆锥销衬套(内壳体与端盖之间)帽型螺母定位销垫片垫片(内部壳体调整)外壳体驱动端压盖

……

数量[1**********]11……

能否继续使用(是/否)

是是是是是是是否否是是……

状态一般一般一般一般一般

维修/更换建议清洁后使用清洁后使用清洁后使用清洁后使用清洁后使用

零件号[***********][***********]400

差一般一般……

需要更换清洁后使用清洁后使用

……

表4 必需更换的零件清单

零件描述垫片

垫片(内部壳体调整)

O型圈垫片垫片垫片节流轴套肩挡圈径向轴承O型圈呼吸器折流盘机械密封

数量[1**********]32

带2台换热器

备注

一般需要更换一个,其(一个损坏)他的清洁后使用

一般差

清洁后使用需要更换

备注1.没有出现在必需更换零件清单中的零件(主要是螺栓、螺母、垫片),改造方承诺如果这些零件确实需要更换,则由改造方免费负责更换,并保证更换零件的规格、材质与原制造厂一致。

报告显示,所有的垫片、O型圈都磨损严重,径向轴承生锈并磨损,驱动端和非驱动端机械密封的密封面磨损严重,等等。必需更换的零件清单见表4。其他零部件状态一般,清洁后可继续使用。

表4中更换零件的费用由用户提供。改造方保证更换零件的规格、材质、数量、零件号均与原制造厂一致。除机械密封外,其他零件均从国外进口。用户要求改造方将更换掉的零件随主机一起发货。

同时改造方提供了泵尺寸检查报告,见表5。改造方还提供了轴的同轴度检查报告,见表6。

在补充协议中,还确定泵机组和润滑油站的运输方式分

表5 泵尺寸检查报告 单位(mm)

Stg5Stg6Stg7Stg8Stg4Stg3Stg2Stg1

位置AB

描述

泵壳入口口环内径叶轮入口口环外径间隙=(A-B)

首级165.07/165.09164.62~63/164.650.44~0.45/0.44

NANANA81.6181.66-0.05101.60101.250.35

2级155.57155.11~170.40~0.46117.46116.95~980.48~0.5181.9682.03-0.07

3级155.56155.150.41117.49117.020.4782.08~0982.15-0.07~-0.06中间衬套内径中间轴套外径

间隙

4级155.57155.15~230.34~0.42

NA117.02NA82.2682.29-0.03114.30113.980.32

5级155.57155.120.45117.481170.4881.8781.9-0.03

6级155.56155.230.33117.491170.49

7级155.59155.20.39117.471170.47

8级155.57155.19~260.31~0.38

NA117.02NA82.2582.28-0.03

CD

泵壳轮毂口环内径叶轮轮毂口环外径间隙=(C-D)

EF

叶轮内径相对应轴径间隙=(E-F)

81.98~82.0082.11~14

82.03

82.15

-0.05~-0.03-0.04~-0.01隔套内径隔套轴套外径

间隙

101.57101.350.22

HI

节流衬套内径节流轴套外径间隙=(H-I)

结论:上述间隙均在磨损范围内,可以不用更换。

表6 同轴度检查报告 单位(mm)

轴上联轴器键槽处为零位,从驱动端看逆时针旋转

从驱动端看V型块定位

12345678

位置读数角度(度)结论

1+0.030

2+0.03270

3+0.030

4+0.03270

5+0.040

6+0.0250

7+0.02270

8+0.010

位置5圆跳动稍微偏大,还在允许范围内,可以继续使用。

·12·

别为整体撬块运输。5 出厂试验

补充改造方案确定后,改造方和用户分别采购新材料和设备。由用户采购的电机发货到改造方,由改造方装配完毕后,准备出厂试验。

5.1 试验前的准备工作

(2)1h后,启泵。平稳提高流量,随着流量增加,噪声增大,判断有汽蚀发生。在流量为182.9m3/h时,现场测转速为4 535r/min。到达正常流量272m3/h时,止推轴承温度为80℃。到达额定流量357m3/h时,止推轴承温度已达100℃,被迫停机。整个过程大约5min。

5.4 故障分析

(1)故障现象

止推轴承箱的油气分离器有白烟冒出,初步判断轴瓦烧了。拆除轴承箱回油管,发现没有油流出,油路没通,轴承没有得到充分的润滑和冷却,所以温升过快过高。(2)故障原因

启泵前,油路循环时没有仔细观察回油管视镜中润滑油的流动情况,造成止推轴承润滑油流动不畅。将进油管接到轴承箱另一侧的进油口,此时回油口有油流出,伴随大量白烟。检查左右两侧进油口,发现直径不等。试验时连接的进油口

5.2 试验前需注意的几点直径小,约Φ8mm,另一侧进油口较大,约Φ14mm。(1)由于额定转速4 400r/min,超过测试台程序默认最大(3)故障后果转速3 000r/min,所以决定在自动生成的性能测试报告上手改将泵移出试验台。拆开止推轴承检查,发现轴瓦烧损。转速,不影响其他参数。轴承箱的回油口有点阻塞。(2)泵的进口压力为0.25MPa(G),NPSHa为12m,NPSHr 机组额定点的振动、温升、噪音及转速没来得及测量。在额定流量时为9m。但是试验台上泵进口是抽吸状态,不能(4)解决办法保证泵的设计NPSHa,试验时有发生汽蚀的可能性。更换轴承。由于进口轴承供货周期长,为满足本项目泵(3)由于合同油站尺寸较大(3m×2.05m),试验车间的交货期要求,经协调,改造方将其他进口合同中的同型号轴地坑放不下,所以泵和电机使用试验台油站供油,齿轮箱借承借调来使用。用其他合同油站供油(试验台油站不能同时满足泵、齿轮箱、(5)重新试验电机用油)。齿轮箱借用油站的供油量比需油量少20L/min,更换止推轴承后,重新做试验。此次试验,泵的振动值齿轮箱轴承温度有可能过高。控制在7.1mm/s以内、轴承温度控制在85℃以内,噪声正常。(4)考虑上述因素,初步决定试验时间为30min。性能试验采集了10个点,从小流量点到额定点。泵性能试验5.3 出厂试验报告见表7,性能曲线见图2。试验报告显示,额定点的流量

扬程满足原泵设计要求,泵效率计算值(76.3%)是原泵效率(1)启动油站,润滑油循环,检查各回油管视镜是否有

油流动。

表7 泵性能试验记录单

大连苏尔寿第1页,共1页试验日期规定数据

额定流量额定扬程流量电磁

转速手持单位\序号r/minm3/hm3/hkPamMPammmmkWkWkW%试验纪要:运转试验时间:30 min

12-14-2011357m/h1 500 m

入口压力变送器14 400102.4102.4-21.38-2.1818.961 9340.091 9361 9361 2371 1631 16346.4

3

(1)泵、电机、齿轮箱主体设备在底座上就位。检查电机、

齿轮箱等新购设备的供货范围、铭牌参数,确保与批复图纸一致。

(2)调平、对中转子,固定泵、电机、齿轮箱后,安装联轴器。(3)检查冷却水管路,确保与批复图纸一致。(4)检查润滑油管路,确保与批复图纸一致。(5)检查主电缆连接。

(6)检查泵进出口管线连接。(7)试验台水池注水,油站注油。

制造号

泵性能试验记录单

泵型号合同号

试验标准额定转速额定效率出口压力变送器24 400182.9182.9-21.65-2.2118.61 8970.291 9001 9001 5491 4561 45664.9

4 400 r/min78%

试验电机2 240 kW

34 400221.5221.5-22.16-2.2618.211 8570.421 8601 8601 6931 5911 59170.5

功率电功率44 400250.5250.5-22.49-2.2917.81 8160.541 8181 8181 7781 6711 67174.2

额定功率试验水温12.6 ℃54 400272.3272.3-23.05-2.3517.351 7700.641 7731 7731 8521 7411 74175.5

1 781kW入口高差0 m64 400274274-22.94-2.3417.321 7670.651 7701 7701 8681 7561 75675.2

出口高差0 m74 400290.6290.6-23.54-2.416.941 7280.731 7311 7311 8951 7811 78176.9

API 610

工位号

叶轮直径试验回路入口管径出口管径

84 400351.5351.5-25.24-2.5715.51 5821.061 5861 5862 0561 9331 93378.5

4A843CP-D6×8×10.5

P-2481

280mm开式200 mm150 mm94 400358.3358.3-25.68-2.6215.151 5451.11 5491 5492 1071 9801 98076.3

104 400363.1363.1-25.71-2.6215.115411.141 5451 5452 1091 9821 98277

测试方法

试验项目试验转速泵流量额定转速下泵流量吸入水头表读数吸入水头米水柱吐出水头表读数吐出水头米水柱速度水头差泵总扬程额定转速下总扬程电机输入功率泵轴功率额定转速下泵轴功率

泵效率

用户代表验收代表试验代表改造方代表

(下转第17页)

·13·

参考文献

[1] 张清明.高温阀门的设计与计算[J].通用机械,2008,(2).[2] 戴宁生,陆文龙,周桂生.三维CAD技术的推广与应用[J].机械制造与自动化,2007,(6).

[3] 鲍晓兵.船闸闸阀门液压启闭系统[J].液压气动与密封,2007,(6).

[4] 杨志峰,雷玉勇,熊佳,等.基于VB的工业阀门应用程序设计[J].机械设计与制造.2007,(12).

(上接第9页

图3 点火器

火焰检测系统:

火焰检测系统采用新一代智能火检,由光导管型火检探头、智能火检处理箱和冷却风管等组成,结构简单、操作方便,性能可靠,可长期连续检测各种燃气、燃油,是锅炉安全监控系统不可缺少的检测设备。

点火控制系统:更换就地点火控制柜并增加DCS远程控制点,如增加点火枪控制指令、甲醇阀控制指令、雾化阀控制指令、吹扫阀控制指令、点火器控制指令等。

3.3 安全注意事项

严重浪费资源。

改造后甲醇点火运行情况:

柏坡正元于2015年11月5日150t锅炉一次点火成功,下午16:30先西侧点火枪一次点燃成功,下午17:00东侧点火枪一次点燃成功。晚上9:00炉床温度升至550℃后,锅炉开

3

始投煤,甲醇点火系统关闭。本次甲醇点火共使用甲醇12m(按

。停用后用脱盐水置换甲甲醇密度0.8t/m3计算消耗甲醇9.6t)

醇管路,保证了停用后点火系统的安全。

通过甲醇点火和柴油点火的对比(见表1),发现本次甲醇点火用90%粗甲醇9.6t,成本约1 560元/t,费用约1.497 6万元,以往采用柴油点火用0#柴油4.5t,均价5 000元/t,费用约2.25万元,一次点火节约成本7 524元左右。同时点火时锅炉无黑烟冒出,降低了燃料燃烧排放的烟气对布袋的污染。

表1 成本比较(按照1台150t锅炉一次点火成本)

名称柴油甲醇

消耗(t)4.59.6

价格 5 0001 560

总消耗(元)22 50014 976

甲醇支管进甲醇喷枪前设置止逆阀,防止甲醇回火。

考虑点火完成后,甲醇储罐和甲醇外送管道的安全性,可用压缩空气吹尽管道内残留甲醇(至锅炉燃烧),再拆除甲醇管道两端法兰连接处加盲板隔断锅炉与甲醇储罐的连接。4 改造前后运行情况比较

改造前150t锅炉一次点火需消耗柴油4.5t,点火时长8h。点火时黑烟冒出,且当时油价较高,一次点火费用居高不下,

从表1可以看出,甲醇较柴油节省22 500-14 976=7 524元。5 结论

本项目共投资23.4万元,投资不高,此项目适合于化肥企业联产甲醇项目,可利用自身产的甲醇,成本更低,且此系统的安全和消防可依托原有安全和消防系统,不必增加额外投资。

依据此甲醇点火装置运行结果表明此装置安全可靠环保,使用经济,为改造锅炉点火系统的化工厂提供了技术保障。

(上接第13页)

泵性能曲线(Pump Performance Curves)

[1**********]0H(m)1800

[1**********]0

2100

Pa(kW)

[1**********]0

9080η(%)70

[1**********]00

Q(m3/h)

[***********][***********]420450

900

值(78%)的97.8%,说明泵维修改造是成功的。6 涂漆、包装、发货

出厂试验合格后,泵体喷漆,整套泵机组撬块包装、运输至现场。现场安装调试由用户主导,改造方提供指导。7 结束语

此台高压锅炉给水泵改造历时一年多,通过改造方,设计方,用户共同努力,不断完善改造方案,发现问题,及时讨论,解决问题,最终改造后的泵成功运行,为项目按时投产做好准备。就改造过程出现的问题总结以下几点,供大家借鉴。

1)进口高压锅炉给水泵在服役20多年后,通过更换易损件,性能仍能达标,说明进口泵的品质良好,值得国内泵企业学习。

2)泵利旧改造有风险,一旦改造不成功,既造成经济损失,又耽误工期,所以泵改造前应做充分的技术经济 分析。

3)细节决定成败。改造过程中的每一个细节都不能疏忽,否则可能造成严重后果。

4)改造项目历时长,牵扯面多,沟通协调、互相配合非常重要。

5)本次改造由于苏尔寿内部规定,更换零件只能进口。以后类似改造,在保证质量的前提下,可以考虑国产。

图2 泵性能试验曲线

·17·


相关文章

  • 锅炉给水预热器的改造_姚晓明
  • O ct. 2004 56 热能工程 化肥设计 Chemical Fertilizer Design 第42卷 第5期 2004年10月 锅炉给水预热器的改造 姚晓明 (中国核工业建峰化工总厂, 重庆 408601) 摘 要:介绍了原锅炉给 ...查看


  • 企业基本情况
  • 临沂恒昌热电有限责任公司 企业基本情况 一.企业简介 临沂恒昌热电有限责任公司成立于2011年8月,企业为临沂恒昌煤业有限责任公司收购原郯城新原热电有限公司整体资产成立的热电企业,公司位于郯城经济开发区新凯路7号,现有主体工程为15MW热电 ...查看


  • 火力发电基础应用及火力发电原理
  • 火力发电基础应用及火力发电原理 热电厂为火力发电厂,采用煤炭作为一次能源,利用皮带传送技术,向锅炉输送经处理过的煤粉,煤粉燃烧加热锅炉使锅炉中的水变为水蒸汽,经一次加热之后,水蒸汽进入高压缸.为了提高热效率,应对水蒸汽进行二次加热,水蒸汽进 ...查看


  • 余热锅炉给水系统改造
  • 靖边燃气发电厂余热锅炉给水系统改造 靖边燃气发电厂 靖边燃气发电厂余热锅炉给水系统改造 摘 要:本文根据靖边燃气发电厂给水系统存在的给水系统压力低和给水泵电机电流高的实际问题,从安全与节能两个角度分析了对余热锅炉造成的危害,通过对造成给水系 ...查看


  • 锅炉节能技术探讨
  • 锅炉节能技术探讨 摘要 锅炉的节能要靠合理的设备选用和科学的运用技术实现. 关键词 锅炉 节能 技术 一 背景分析 在世界能源短缺,各国都在重视节能减排.环境保护的背景下,我国也加强了对高耗能各种设备的节能监管,并颁发多部法规标准,为节能监 ...查看


  • 锅炉存在的风险及改造建议
  • 注汽六队锅炉存在的风险及改造建议 2012年3月2日 1 现状分析 外部输入乔庄变电站的输电线路主要有2条,江乔线和古乔线(魏乔线还没有使用),乔庄变电站给我队提供有6条高压输电线路,4条10KV 到高压设备(其中给水泵为一用一备),另外2 ...查看


  • 学校设计说明
  • 设计说明 一.设计概要 1. 设计背景 建设用地位于日喀则市江当乡.位于市区东,雅鲁藏布江南岸,距市区约45公里.面积304平方公里,人口0.5万.农作物以青稞.油菜为主.古迹有恩归寺,境内有和平机场. 2. 设计概要 用地内预计将建设学校 ...查看


  • 2014年公司工作目标任务及措施
  • 茌平齐鲁供热有限公司 2014年工作任务.目标及措施 为贯彻落实集团"节能降耗,降低生产成本"生产方针,继续全面开展节能增效和节能降耗活动,树立"管理是超级生产力"的思想,向管理要效益,2014年公司 ...查看


  • 华能巢湖发电厂调研报告090621
  • 华能巢湖发电厂调研报告 大开二热项目调研组 2009年6月20日 调研提纲 调研时间:2009年6月15日--6月17日 调研地点:安徽华能巢湖电厂 调研人员: 国电电力:李 斌 大开二热:周国强 任功德 靳德全 毛羽丰 韩 彬 张文臣 陈 ...查看


热门内容