五星级酒店装修工程造价的全过程控制 作者:张红琴
来源:《价值工程》2014年第11期
摘要: 笔者于2007年进入深圳万利加集团,负责集团工程造价的审计工作,集团旗下有酒店、烟草、地产、矿业四大产业。笔者做为昇逸酒店装修工程的结算审核人,现结合集团旗下的昇逸酒店和馨悦酒店精装修工程,从设计、招投标、施工、结算等方面分析影响酒店装修工程造价的因素,论述酒店精装修工程如何能够有效的全过程控制。
Abstract: The author joined the Shenzhen GloryHarvest Group in 2007, and have been responsible for the auditing of Group's construction cost. The Group has four major industries: the Hotels, the Tobacco, the Real Estate, and the Mining. As the reviewer of the settlement audit of Zense Hotel renovation project, combining the Group's decoration engineering of Zense Hotel and Zense Inn Hotel, The author would like to analyze the factors which influence the hotel renovation cost of the whole process in design, bidding, construction, and settlement, and also would like to discuss how to make the effectively control during the hotel renovation.
关键词: 酒店精装修;造价全过程控制;分析
Key words: hotel decoration;cost control of the whole process;analyze
中图分类号:TU723.3 文献标识码:A 文章编号:1006-4311(2014)11-0079-02 0 引言
昇逸酒店位于深圳市罗湖区文锦中路,酒店由水疗、餐饮、客房三部分组成,水疗位于酒店B、C座一、二、三、四层,面积是8800平方米,客房位于B座六至二十二层,面积是20000平方米,餐饮位于A座一至二层,面积是1600平方米。整个酒店按五星级酒店的装修标准设计并施工。
1 昇逸酒店装修工程造价管理中存在的问题
昇逸酒店精装修工程,在施工过程中,由于施工图存在问题,导致施工过程中,设计变更和现场签证比较多,造成了工期上的延误以及结算价大幅度超过预算价,其次,酒店装修工程涉及的专业多,和近三十个施工单位签订了工程施工合同或采购合同。由于总包和建设单位的管理均不到位,各专业的衔接出现了问题,造成工期的延误,签证单的增加,以及影响了工程质量。另外,该装修工程的造价管理是委托工程造价咨询公司全过程负责的,工程造价咨询公司人员流动性大,在工程施工中,人员频繁替换,导致后继人员对工程不熟悉,无法准确做出判断。竣工验收后的结算,只能由集团公司自行完成。
龙源期刊网 http://www.qikan.com.cn
五星级酒店装修工程造价的全过程控制 作者:张红琴
来源:《价值工程》2014年第11期
摘要: 笔者于2007年进入深圳万利加集团,负责集团工程造价的审计工作,集团旗下有酒店、烟草、地产、矿业四大产业。笔者做为昇逸酒店装修工程的结算审核人,现结合集团旗下的昇逸酒店和馨悦酒店精装修工程,从设计、招投标、施工、结算等方面分析影响酒店装修工程造价的因素,论述酒店精装修工程如何能够有效的全过程控制。
Abstract: The author joined the Shenzhen GloryHarvest Group in 2007, and have been responsible for the auditing of Group's construction cost. The Group has four major industries: the Hotels, the Tobacco, the Real Estate, and the Mining. As the reviewer of the settlement audit of Zense Hotel renovation project, combining the Group's decoration engineering of Zense Hotel and Zense Inn Hotel, The author would like to analyze the factors which influence the hotel renovation cost of the whole process in design, bidding, construction, and settlement, and also would like to discuss how to make the effectively control during the hotel renovation.
关键词: 酒店精装修;造价全过程控制;分析
Key words: hotel decoration;cost control of the whole process;analyze
中图分类号:TU723.3 文献标识码:A 文章编号:1006-4311(2014)11-0079-02 0 引言
昇逸酒店位于深圳市罗湖区文锦中路,酒店由水疗、餐饮、客房三部分组成,水疗位于酒店B、C座一、二、三、四层,面积是8800平方米,客房位于B座六至二十二层,面积是20000平方米,餐饮位于A座一至二层,面积是1600平方米。整个酒店按五星级酒店的装修标准设计并施工。
1 昇逸酒店装修工程造价管理中存在的问题
昇逸酒店精装修工程,在施工过程中,由于施工图存在问题,导致施工过程中,设计变更和现场签证比较多,造成了工期上的延误以及结算价大幅度超过预算价,其次,酒店装修工程涉及的专业多,和近三十个施工单位签订了工程施工合同或采购合同。由于总包和建设单位的管理均不到位,各专业的衔接出现了问题,造成工期的延误,签证单的增加,以及影响了工程质量。另外,该装修工程的造价管理是委托工程造价咨询公司全过程负责的,工程造价咨询公司人员流动性大,在工程施工中,人员频繁替换,导致后继人员对工程不熟悉,无法准确做出判断。竣工验收后的结算,只能由集团公司自行完成。