破洞门方案

XXX 土建工程

洞门破除专项方案

编制:

审核:

批准:

XXX 有限公司 XXXXXXXX 标项目部

XXXX 年XX 月XX 日

目 录

1、编制目的及编制依据 ········································································ 3

1. 1编制目的 ·················································································· 3 1. 2编制依据 ·················································································· 3 2、洞门破除施工进度安排 ···································································· 3 3、洞门破除施工工艺 ············································································ 3

3. 1 围岩判断 ················································································· 3 3. 2 洞门破除尺寸 ·········································································· 3 3. 3 施工步骤 ················································································· 4 4、质量保证措施 ··················································································· 5 5、安全保证措施 ··················································································· 5

洞门破除方案

1、编制目的及编制依据

1. 1编制目的

为确保盾构机始发时的洞口土体稳定,使盾构机安全、平稳、迅速地由盾构始发井进入隧道,防止洞门处土体坍塌及洞门漏水,特制定此施工方案。

1. 2编制依据

(1)盾构机图纸,盾构机使用维护技术文件; (2)盾构始发井主体结构设计图;

(3)《岩土工程勘察报告》,《岩土工程补充勘察报告》; (4)其它相关技术文件及图纸等。

2、洞门破除施工进度安排

洞门破除施工与盾构机组装、调试同时进行。为避免洞门暴露时间过长而失稳,应确保洞门破除完成的时间,和盾构机始发的时间相差48小时以内。右线洞门破除施工用时10天,开始时间为10月下旬,早于左线始发10~12天。左线线洞门破除比左线推迟一个月,用时亦为10天。

3、洞门破除施工工艺

3. 1 围岩判断

始发端头处隧道拱顶覆土约5.5m ,有、、地层,如图1所示。隧道全断面为富水砂层,洞门处地质围岩条件比较差。但是始发端头采用旋喷桩加固了12m 长,根据抽芯检查结果洞门处地质围岩条件已经改良、非常稳定,洞门的破除不会对周围土体和围岩产生大的影响。

3. 2 洞门破除尺寸

始发井围护结构采用地下连续墙,墙内布置有钢筋,考虑到刀盘外径和洞口止水装置的尺寸要求,故洞门破除外径定为6500mm ,洞门破除采用人工破除。施工前准确定位隧道洞门中心线,然后对洞门内进行开凿放样。洞门尺寸如图2所示。

图1

图2 洞门破除尺寸图

3. 3 施工步骤

洞门破除分两次完成,先凿除围护结构至墙体外侧钢筋,留下内侧钢筋及保护层以保证掌子面安全;当盾构机组装、调试完成后,准备始发时,割除围护结构内侧钢筋,盾构机迅速推进至土体。

洞门凿除施工时,在盾构机与掌子面之间搭钢管支架,利用人工进行凿除围护结构施工。第一步:凿除外层钢筋砼,直至留下最后一层钢筋,凿除范围和分

块方法按下图所示。凿除方法是先凿竖向和横向4道沟槽,再凿环向沟槽,分块沟槽宽度约为180mm ,如图3所示。凿除顺序按分块编号顺序,从上往下顺序凿除。计划安排6名工人,从盾构机主体组装之时开始凿除,在一周内完成凿除任务。第二步:剩余部分钢筋砼凿除时间定在盾构机掘进之前,凿除时加大人力投入,迅速破除洞门,确保盾构机安全进入。破除工作保证围护结构地下连续墙的钢筋全部切断,以避免盾构推进时刀盘被未切断的钢筋挂住。

图3 洞门凿除方法示意图

凿除施工完毕后拆除脚手架,快速拼装负环管片,使盾构机刀盘顶住掌子面,避免掌子面暴露太久发生失稳坍塌。

洞门破除施工工艺流程图见图4。

图4 洞门破除施工流程图

4、质量保证措施

⑴施工制作前,有关技术人员应熟悉图纸,施工前向施工班组进行技术交底。 ⑵在洞门边缘处用风镐开凿时,风镐应从圆形洞门轮廓线上向圆心方向斜向插入,小块凿除,防止洞边混凝土崩裂。

⑶控制洞门凿除尺寸不小于Φ6500mm.(盾构机刀盘最大直径为6280mm ,按允许隧道轴心线最大偏差为50mm 计,则刀盘能通过的理论最小直径为6380mm ,考虑刀盘与切割的钢筋头之间预留50mm 安全间隙故将洞门混凝土破除范围定为Φ6500mm) 。

5、安全保证措施

⑴对各施工人员进行安全意识教育和操作规程教育。 ⑵进行施工作业之前应组织相关人员进行安全技术交底。

⑶井下施工人员均应正确佩带好安全防护设施, 及时避让混凝土块。 ⑷进行高空作业必须和地面人员协调好,禁止抛掷工具。

⑸脚手架搭设应牢固可靠, 并应加设足够支撑或拉杆以保证其稳定性。 ⑹委派专门的技术人员对现场施工进行技术和安全指导。

⑺密切注意掌子面的稳定和失水情况。若发现掌子面不稳定,应立即清理支架,撤离作业人员。推进盾构机顶住掌子面。

XXX 土建工程

洞门破除专项方案

编制:

审核:

批准:

XXX 有限公司 XXXXXXXX 标项目部

XXXX 年XX 月XX 日

目 录

1、编制目的及编制依据 ········································································ 3

1. 1编制目的 ·················································································· 3 1. 2编制依据 ·················································································· 3 2、洞门破除施工进度安排 ···································································· 3 3、洞门破除施工工艺 ············································································ 3

3. 1 围岩判断 ················································································· 3 3. 2 洞门破除尺寸 ·········································································· 3 3. 3 施工步骤 ················································································· 4 4、质量保证措施 ··················································································· 5 5、安全保证措施 ··················································································· 5

洞门破除方案

1、编制目的及编制依据

1. 1编制目的

为确保盾构机始发时的洞口土体稳定,使盾构机安全、平稳、迅速地由盾构始发井进入隧道,防止洞门处土体坍塌及洞门漏水,特制定此施工方案。

1. 2编制依据

(1)盾构机图纸,盾构机使用维护技术文件; (2)盾构始发井主体结构设计图;

(3)《岩土工程勘察报告》,《岩土工程补充勘察报告》; (4)其它相关技术文件及图纸等。

2、洞门破除施工进度安排

洞门破除施工与盾构机组装、调试同时进行。为避免洞门暴露时间过长而失稳,应确保洞门破除完成的时间,和盾构机始发的时间相差48小时以内。右线洞门破除施工用时10天,开始时间为10月下旬,早于左线始发10~12天。左线线洞门破除比左线推迟一个月,用时亦为10天。

3、洞门破除施工工艺

3. 1 围岩判断

始发端头处隧道拱顶覆土约5.5m ,有、、地层,如图1所示。隧道全断面为富水砂层,洞门处地质围岩条件比较差。但是始发端头采用旋喷桩加固了12m 长,根据抽芯检查结果洞门处地质围岩条件已经改良、非常稳定,洞门的破除不会对周围土体和围岩产生大的影响。

3. 2 洞门破除尺寸

始发井围护结构采用地下连续墙,墙内布置有钢筋,考虑到刀盘外径和洞口止水装置的尺寸要求,故洞门破除外径定为6500mm ,洞门破除采用人工破除。施工前准确定位隧道洞门中心线,然后对洞门内进行开凿放样。洞门尺寸如图2所示。

图1

图2 洞门破除尺寸图

3. 3 施工步骤

洞门破除分两次完成,先凿除围护结构至墙体外侧钢筋,留下内侧钢筋及保护层以保证掌子面安全;当盾构机组装、调试完成后,准备始发时,割除围护结构内侧钢筋,盾构机迅速推进至土体。

洞门凿除施工时,在盾构机与掌子面之间搭钢管支架,利用人工进行凿除围护结构施工。第一步:凿除外层钢筋砼,直至留下最后一层钢筋,凿除范围和分

块方法按下图所示。凿除方法是先凿竖向和横向4道沟槽,再凿环向沟槽,分块沟槽宽度约为180mm ,如图3所示。凿除顺序按分块编号顺序,从上往下顺序凿除。计划安排6名工人,从盾构机主体组装之时开始凿除,在一周内完成凿除任务。第二步:剩余部分钢筋砼凿除时间定在盾构机掘进之前,凿除时加大人力投入,迅速破除洞门,确保盾构机安全进入。破除工作保证围护结构地下连续墙的钢筋全部切断,以避免盾构推进时刀盘被未切断的钢筋挂住。

图3 洞门凿除方法示意图

凿除施工完毕后拆除脚手架,快速拼装负环管片,使盾构机刀盘顶住掌子面,避免掌子面暴露太久发生失稳坍塌。

洞门破除施工工艺流程图见图4。

图4 洞门破除施工流程图

4、质量保证措施

⑴施工制作前,有关技术人员应熟悉图纸,施工前向施工班组进行技术交底。 ⑵在洞门边缘处用风镐开凿时,风镐应从圆形洞门轮廓线上向圆心方向斜向插入,小块凿除,防止洞边混凝土崩裂。

⑶控制洞门凿除尺寸不小于Φ6500mm.(盾构机刀盘最大直径为6280mm ,按允许隧道轴心线最大偏差为50mm 计,则刀盘能通过的理论最小直径为6380mm ,考虑刀盘与切割的钢筋头之间预留50mm 安全间隙故将洞门混凝土破除范围定为Φ6500mm) 。

5、安全保证措施

⑴对各施工人员进行安全意识教育和操作规程教育。 ⑵进行施工作业之前应组织相关人员进行安全技术交底。

⑶井下施工人员均应正确佩带好安全防护设施, 及时避让混凝土块。 ⑷进行高空作业必须和地面人员协调好,禁止抛掷工具。

⑸脚手架搭设应牢固可靠, 并应加设足够支撑或拉杆以保证其稳定性。 ⑹委派专门的技术人员对现场施工进行技术和安全指导。

⑺密切注意掌子面的稳定和失水情况。若发现掌子面不稳定,应立即清理支架,撤离作业人员。推进盾构机顶住掌子面。


相关文章

  • 盾构始发洞门破除方案
  • 目录 一.编制依据 ...................................................................................................... 1 二.工程概 ...查看


  • 洞门破除方案_secret
  • 洞门破除方案 1 目 录 一. 二. 工程概况 . .......................................................... 3 施工方法 . .......................... ...查看


  • 洞门破除方案
  • 天津地铁六号线土建工程17标 鞍山西道站-天拖站-一中心医院站-红旗南路站盾构区间洞门凿除施工方案 编 制: 校 对: 审 定: 中煤隧道工程有限公司 红旗南路盾构项目部 二零一四年七月 目 录 1. 编制目的及编制依据 ......... ...查看


  • 盾构始发洞门破除施工方案
  • 珠江路站~长江路站区间盾构始发洞门破除方案 一. 编织依据 1.<中华人民共和国安全生产法> 2.<中华人民共和国消防法> 3.<建筑机械使用安全技术规程> 4.<建筑施工安全检查标准> 5. ...查看


  • 隧道口洞门端墙整修施工方案
  • 隧道口洞门端墙整修施工方案 ● 工程概况 本工程位于XX高速,主线里程K33+500~K33+800段,属双连拱断面隧道.洞门口为端墙式洞门墙,本次施工主要内容包括原条石端墙压顶拆除更换为现浇钢筋混凝土压顶.洞门端墙条石重新勾缝以及洞口轮廓 ...查看


  • 斗篷山隧道出口端墙式隧道洞门施工方案
  • 斗篷山隧道出口端墙式洞门施工方案 1.洞门设计概况 1.1洞门形式 斗篷山隧道出口洞门形式为端墙式洞门,端墙为直墙,墙厚1.5m.洞口段翼墙为U形挡墙,挡墙纵向长10m,垂直坡比为1:0.2,高端为10.0m×1.0m(高×宽),低端为6. ...查看


  • 隧道洞口段的施工方法及注意事项
  • 隧道洞口段的施工方法及注意事项 摘 要:目前国内对隧道洞口段的设计大多考虑了预加固措施,这里详细阐述了洞口段围岩预加固的措施以及隧道洞口段施工开挖的方法,指出坚持施工原则,采取有效的施工方法,对确保隧道施工和运营安全至关重要. 关键词:隧道 ...查看


  • 轨道交通工程测量工作监理指南
  • 轨道交通工程测量监理工作指南 上海申通地铁集团有限公司建设事业部 上海申诚隧道轨道交通工程建设监理有限公司 二00九年七月 目 录 一.施工阶段区间隧道工程监理测量节点复核工作内容 1.区间隧道监理现场测量复核工作内容 2.测量监理程序性工 ...查看


  • 盾构始发准备工作顺序
  • 1.盾构始发准备工作: 盾构掘进施工的竖井 始发工作井: 满足盾构掘进机安装和出洞施工的要求接收工作井: 盾构隧道掘进完成后进入接收井,满足盾构拆卸或转场吊装移位的工作空间要求 竖井施工方法: 沉井法.地下连续墙围护.钢板桩围护 ⑴凿除洞门 ...查看


热门内容