目录
综合编制说明·············································2 岩土工程概况······································2 设计与施工依据····································2 场地工程地质条件··································3 土方开挖前准备工作···································4 土方开挖方案······································6
(一)土方工程工期为18天·························6
(二)安全要求和措施······························6
(三)土方开挖顺序及质量保证措施··················7
(四)喷浆施工····································9
(五)、成品保护措施·······························10
(六)、施工应急抢险措施····························11
(七)、安全环保措施·······························12
(八)、质量控制要点·······························13
一、综合编制说明
①本方案针对污水处理工程基坑支护及地基处理施工的重点、难点,本着技术先进、安全可靠、工期合理、节约造价之设计原则,同时兼顾后续工程的施工,经组织公司专家多次研究论证和多方案比较,优化设计参数,提出本工程的总体设计和具体施工方案。
②本方案也是根据我公司目前自有施工机具、人员以及技术实力,并综合各方面具体情况进行编制的,我公司技术人员将在施工中进一步深化、细化和完善方案,达到‘安全、优质、快速、低耗’的施工总目标。
③本设计方案是经我公司组织内部专家多次研究论证,经与结构设计单位交流,并通过有关专家评审,汲取我公司多年施工经验,优化设计参数后提出本工程的总体设计方案。
二、岩土工程概况
①该工程所在地地下2m左右为石灰岩岩层,深基坑开挖十分困难。
②该项目为综合工程,施工高峰期时逢雨季,中午气温高,人员密度较大,各单位工程及各工艺车间安装交叉较多,对深基坑施工、厂区敷设管道、电缆施工过程增加难度;施工组织较为繁琐。这给劳力、机具的组织及调度增加了难度。
③电气设备、仪表及自控设备技术先进,安装要求高。 ④本工程自控系统为PLC控制,工程调试比较复杂。
三、设计与施工依据
1、本工程的《岩土工程勘察报告》
2、本工程总平面图
3、本工程地下结构平面图
4、《建筑地基基础设计规范》(GB50007-2002)
5、《混凝土结构工程施工质量验收规范》(GB50204-2002)
6、《混凝土结构设计规范》(JGJ50010-2002)
7、桂林市《地下室基坑围护设计》
8、《广西省建筑基坑工程技术规程》
四、场地工程地质条件
1、地形、地貌及环境条件:拟建工程位于广西全州县绍水镇,属于岩溶平地的丘谷地,地貌上属于侵蚀堆积及残积地貌区波状堆积平原亚区,地貌单元简单地形比较平坦,场地等级为三级。 污水处理规模一期为1000m³/d,二期为2000m³/d,三期为2000m³/d。场地原为农田,现已回填,组成成分复杂,工程性质不稳定。本区域属亚热带,气候温和,雨量充沛,交通不方便。
2、地层结构特征:
①杂填土:杂色,由块石、碎石、砖屑等夹砂粘性土等组成,组成成分复杂,工程性质不稳定,全场分布,厚度1.2-3.60米,为高压缩性。
②粉质粘土:黄灰色,湿,软塑—可塑,零星分布,厚度0.80—2.20米,为中高压缩性,qc=890Kpa,fs=66Kpa,工程性质一般。
③石灰岩:硬度极强,一般机械很难破除,施工难度大,工程性
质稳定,全场分布厚度未知。
④粘质粉土:灰黄色,稍密-中密,很湿,低韧性,干强度低,该层全场分布。厚度1.9~3.2M qc=470Kpa,fs=79Kpa为中等压缩性,工程性质差。
从地质勘探报告得知,场地地表为耕植土,很湿,可塑状态,工程性能差,在地表水渗流作用下很容易崩塌,受场地大小限制,该土层清理后没地方堆积,且耕表土下层为粘土,工程性能较差。经综合进度、质量、安全各方面考虑,决定在基坑开挖时采用喷浆护壁施工工艺。
五、土方开挖前准备工作
(一)技术准备
(1)、熟悉施工图纸和地质勘察报告,掌握基础部分标高和做法,土层和地下水位情况,编制挖土施工方案和交底。
(2)、测量放线工作,根据给定的规划永久性坐标水准点,按建筑物总平面图和建筑红线要求,引测到现场。在建筑物周围,设基测量控制基线,轴线和水平基准点,做好轴线控制的测量和校核。轴线控制网应避开建筑物、构筑物、机械操作运输线路,并设保护标志,作业前需要放出基槽(坑)上口和下口灰线。引测定位标高,对整个场地进行原始地坪测量,并且做好记录。定位龙门桩:在土方开挖不受影响的地方确定位置,并且用12毫米的钢筋头用经纬仪在地面做好复查点,以便随时复核。因为场地不够,土方需要全部外运,先联系好堆放场地,要配备3辆自卸汽车,办理好环境卫生许可证及相关手
续。协调邻里关系,保证工程正常施工,并且在相临建筑做好标记,以便随时测量由于基坑开挖后可能引起的沉降。
(3)、推倒西面调节池处围墙。由于场地面积较小,而政府在做封闭施工围墙时将整个厂区边线往里缩小2米,导致现场可用空地变小,调节池西面边线在围墙外轮廓处,即使合理向东平移后依旧距离围墙过近,使得施工难度增大,且围墙内有不明水源一直向外渗水,为了施工进度以及安全考虑,不得不推倒西面调节池处围墙。
(4)、对参加施工人员进行详细的技术和安全文明施工交底。
(二)材料准备
(1)、基槽(坑)需用明沟和集水井进行降排水时,应准备做集水井的材料,作简单支护时,需准备支护用的材料。
(2)、基槽(坑)需作局部处理或基底换垫时,需准备好换填用材料。
(3)、雨期施工应准备护坡用材料(如塑料布、钢丝网、水泥等)。
(4)、应准备好基础施工材料,以便验槽(坑)后立即进行基础工程的施工,防止过长时间的晾槽。
(三)主要工具
(1)机械:推土机、挖掘机、自卸汽车、水泵等。
(2)工具:铲锹、十字鞒、大锤、钢钎、手推车等。
(四)作业条件
(1)现场三通一平完成,地上地下障碍物已清除。
(2)、基槽(坑)开挖的测量放线工作已完成,并经验收符合设
计要求。
(3)、开挖现场的地表水已排除,采用轻型井点降低地下水位,要求地下水位降至基底500㎜以下。
(4)参加施工人员已进行了技术、安全和文明施工的交底。
(五)工艺流程
测量放线—分层开挖至基底20-30CM—降排水—机械和人工配合挖下翻梁及承台—人工修整—验槽(坑)。
六、土方开挖方案
(一)土方工程工期为18天
由于基坑开挖正处于黄梅雨季,所以开挖土方因天气影响很大,并且夜间不能连续施工,所以合理的安排施工是很重要的。主要是土方堆放问题,现场场地有限,土方不得不外运,应由甲方联系堆土场地。
(二)安全要求和措施
1、开工前全面调查地上、地下障碍物和管线情况,进行具体位置交底,对暂未处理的要树立明显标志。
2、根据本工程回转场地狭小,机械施工、配合工种多的特点,制定安全措施,建立安全责任制并定期开展安全活动。
3、各分项工程,各工种要遵守各自的安全操作规程,注意相互间的安全距离,施工机械不得撞击测量桩等。
4、要执行现场施工用电规定,非专业人员禁止动用施工设备,要经常检查供电线路,闸箱、机电设备的完好和绝缘情况,供电线路
要架空或埋入地下,防止机械碰压。
5、基坑四周要搭设防护栏,设置专用上下通道。
6、机械挖土现场入口设安全岗、配备专人指挥挖土,机械操作者要遵守有关法律规定,按指定方式施工。
7、土方开挖按顺序、方法必须与设计要求相一致,并遵循开槽支撑,先撑后挖,分层开挖,严禁超挖的原则。
8、选择噪声低,振动小,公害小的施工机械和施工方法、减少对现场周围居民的干扰,同时做好周围居民的安抚工作,取得谅解,相互配合。
(三)土方开挖顺序及质量保证措施
1、地下土方开挖以1台SW-150型及一台225型挖机机械开挖为主,人工挖土为辅。挖土分二个施工段,根据施工现场的实际情况,以便于外运,考虑到土方开挖的施工进度和合理的施工顺序,从北向南进行大面积土方一次性分层开挖到设计基底标高,并保留150~300㎜的土不挖,待第一施工段上部土方施工完毕后,再用SW-120型小型挖机进行下翻梁、承台开挖,人工修整挖至设计标高后,立即进行基槽(坑)验收。达到设计规定标准后,即进行地下室工程的基础施工。
2、开挖按踏步式逐行进行,不准一次突发性开挖到底,避免土体短时期大量挖除后,造成围护结构侧向应力增大过快。
3、挖土过程中,保证地下水位离基底标高0.5M以下,为保证排水效果,应配备足够潜水泵和泥浆泵、和轻型井点进行明(暗)沟及
导管排水。
4、机械挖土绘制土方开挖图,规定开挖线路、顺序、范围、底部各层标高、边坡坡度、排水沟、集水井位置及流向,避免混乱,造成超挖、乱挖,应尽可能地使机械多挖,减少机械超挖和人工挖土。
5、为防止开挖过程中,围护体系发生意外,挖土深度应严格控制,每次挖土绝不超挖。并每24小时/次对基坑围护体系深层土体水平位移观测、定时对周围建筑物沉降观测和地下水位观测。
6、严格控制超挖量,土方挖土时排水沟不得靠边设置。
7、做好开挖样板制工作,即凡每一次开挖前,挖一段样板示范,操作者换班时,做好挖深、操作方法等交接班,确保开挖质量。
8、针对原基坑围护方案,因建设单位考虑施工成本多次协商要求取消水泥搅拌桩止水带,采用井点降水来保证基坑施工,详见降水施工方案。
9、同时结合现场情况,增加土钉墙加固边坡稳定,节点做法参照广西省《地下室基坑围护设计》基护-08节点,放坡比例采用1:1.75,下部设置排水沟距边坡大于0.3M,深度0.5M,宽0.3M,1:2水泥砂浆抹面,个边角设置500*500MM深1000MM的集水井。
10、IBR池西侧、西南侧由于堆积土方过多,下雨过大,处出现大面积塌方,所以对该部位边坡先进行修整,压实,然后用100厚C25细石混凝土找坡,上口做压顶挡水,防止地表水流入基坑,边坡下部即冠梁边侧设置砖砌排水沟400*400,并用1:2水泥砂浆抹面,具体做法如图3-1剖面。
米
3-1剖面 锚入钢筋深度视情况可调整
(四)喷浆施工
1、喷射砼的强度等级为C25,厚度为100MM,其配合比为水泥:砂:细石:水=1:2:2:0.45;水泥为普通硅酸盐425级,碎石最大粒径不超过15MM,砂为中粗黄砂
2、喷射顺序是由上而下,喷头与受喷面距离控制在1M左右,喷射方向垂直于受喷面。在钢筋部位,应先喷填钢筋和锚钉后方,然后再喷射其前方,以免其后出空隙。
3、喷射面宜二次喷射,第一次喷射厚度在50MM左右,在第一次砼层初凝前进行二次喷射。
4、在继续下层喷射作业时,清除施工缝接合面上浮浆层和松散碎石,并喷水使之湿润。
(五)、地下水控制
(1)排水沟和集水井设置在建筑基础边净距0.4m以外,排水沟边缘离开边坡坡脚0.3 m处,在基础四周每20~30m,设一个集水井。
(2)排水沟底面应比挖土面低0.4m,集水井底面应比沟底面低0.6 m以上。
(3)、抽水设备根据现场排水量大小及确定。
(4)、当基坑侧壁出现分层渗水时,可按不同高程设置导水管、导水沟等构成明排水系统,当基坑侧壁水量较大或不能分层明排时,宜采用导水降水方法。基坑明排尚应重视环境排水,当地表水对基坑侧壁产生冲刷时,宜在基坑外采取截水,封堵,导流等措施。
(五)、成品保护措施
(1)机械挖土作业时应注意保护测量控制定位桩、轴线桩、水准基桩,防止被挖土和运土机械设备碰撞,行驶破坏。
(2)基坑四周应设排水沟、集水井,场地应有一定坡度,以防止雨水浸泡基坑和场地。
(3)夜间施工应设足够的照明,防止地基、边坡超挖。
(4)基坑开挖时,在开挖全过程中应作好临时支撑保护,不得随意拆除和损害。
(5)在斜坡地段挖土时应遵循由上而下,分层开挖的顺序,以避免破坏坡脚,引起滑坡。
(6)基槽(坑)开挖完成后,应尽快进行下一道工序施工,如不能及时进行施工,应保留一层200~300㎜以上土层。在进行下一道工
序前挖去,以避免基底遭受扰动,降低地基承载力。
(六)施工应急抢险措施
由于基坑开挖深度较大,四周情况复杂,且施工周期长,影响基坑安全的因素很多。须随时做好应付可能出现的不利情况的准备,确定合适的应急措施。
1、 现场配备一定数量的沙包、钢管、钢板桩、水泥、注浆设
备等抢险物资。
2、 对基坑四周24小时进行水平位移监测,如位移较大,应立
即停止开挖土方,增加钢管支撑或斜支撑,必要时回填土方,并坑外卸土。
3、 如地面出现裂缝,应及时灌浆修补,防止地下水渗入。
4、 如围护结构变形过大,在坑底位置设置块石矮挡墙保护坑
脚防止踢脚破坏。
5、 密切关注天气预报,对暴雨等恶劣天气应停止挖土并密切
关注基坑安全。
6、 流砂现象的防治:(1)采用抢挖法,组织分段开挖,边挖
边做垫层及砖胎膜。做到当天挖土当天完成砖胎膜施工。
(2)采用井点降水,在基坑四周按设计方案设置井点降水,局部加深部位增设轻型井点降水,确保地下水降至基坑面以下50CM。
(七)、安全环保措施
(1)机械挖土应分层进行,合理放坡,防止塌方,溜坡等造成机械
倾翻,淹埋等事故。
(2)二台挖掘机在同一作业面机械开挖,挖掘机间距应大于10m,上下台阶挖掘机前后应相距30 m以上,挖掘机离下部边坡应有一定安全距离,以防造成翻车事故。
(3)在有支撑的基坑中挖土时,必须防止碰撞支撑,在坑沟边使用机械时应计算支撑强度、危险地段应加强支撑。
(4)机械施工区域禁止无关人员进入场地内,挖掘机工作回转半径范围内不得站人或进行其他作业。
(5)挖掘机操作和汽车装土行驶要听从指挥,所有车辆必须严格按规定的开行路线行驶,防止撞车。
(6)夜间作业,机械及工作地点必须有充足的照明设施,在危险地段设置明显的警示标志和护栏。
(7)采用降排水措施时,抽出的水应有组织地排放至指定位置,不得任其流而污染场地和环境。采用人工修土时,必须待挖掘机停稳后再挖土,不得在挖掘机回转半径内操作,以免挖掘机 碰撞伤人。
(8)运输土方的车采在场外行驶时,应用加盖车辆或采取覆盖措施,车轮冲洗等措施,以防污染道路和环境。
(八)、质量控制要点
(1)土方开挖前应检查定位放线,排水和降水地下水位系统,合理安排土方运输车的行走路线。
(2)施工过程中应检查平面位置,水平标高和边坡坡度,压实度,排水、降低地下水位系统,并随时观察周围的环境变化。
目录
综合编制说明·············································2 岩土工程概况······································2 设计与施工依据····································2 场地工程地质条件··································3 土方开挖前准备工作···································4 土方开挖方案······································6
(一)土方工程工期为18天·························6
(二)安全要求和措施······························6
(三)土方开挖顺序及质量保证措施··················7
(四)喷浆施工····································9
(五)、成品保护措施·······························10
(六)、施工应急抢险措施····························11
(七)、安全环保措施·······························12
(八)、质量控制要点·······························13
一、综合编制说明
①本方案针对污水处理工程基坑支护及地基处理施工的重点、难点,本着技术先进、安全可靠、工期合理、节约造价之设计原则,同时兼顾后续工程的施工,经组织公司专家多次研究论证和多方案比较,优化设计参数,提出本工程的总体设计和具体施工方案。
②本方案也是根据我公司目前自有施工机具、人员以及技术实力,并综合各方面具体情况进行编制的,我公司技术人员将在施工中进一步深化、细化和完善方案,达到‘安全、优质、快速、低耗’的施工总目标。
③本设计方案是经我公司组织内部专家多次研究论证,经与结构设计单位交流,并通过有关专家评审,汲取我公司多年施工经验,优化设计参数后提出本工程的总体设计方案。
二、岩土工程概况
①该工程所在地地下2m左右为石灰岩岩层,深基坑开挖十分困难。
②该项目为综合工程,施工高峰期时逢雨季,中午气温高,人员密度较大,各单位工程及各工艺车间安装交叉较多,对深基坑施工、厂区敷设管道、电缆施工过程增加难度;施工组织较为繁琐。这给劳力、机具的组织及调度增加了难度。
③电气设备、仪表及自控设备技术先进,安装要求高。 ④本工程自控系统为PLC控制,工程调试比较复杂。
三、设计与施工依据
1、本工程的《岩土工程勘察报告》
2、本工程总平面图
3、本工程地下结构平面图
4、《建筑地基基础设计规范》(GB50007-2002)
5、《混凝土结构工程施工质量验收规范》(GB50204-2002)
6、《混凝土结构设计规范》(JGJ50010-2002)
7、桂林市《地下室基坑围护设计》
8、《广西省建筑基坑工程技术规程》
四、场地工程地质条件
1、地形、地貌及环境条件:拟建工程位于广西全州县绍水镇,属于岩溶平地的丘谷地,地貌上属于侵蚀堆积及残积地貌区波状堆积平原亚区,地貌单元简单地形比较平坦,场地等级为三级。 污水处理规模一期为1000m³/d,二期为2000m³/d,三期为2000m³/d。场地原为农田,现已回填,组成成分复杂,工程性质不稳定。本区域属亚热带,气候温和,雨量充沛,交通不方便。
2、地层结构特征:
①杂填土:杂色,由块石、碎石、砖屑等夹砂粘性土等组成,组成成分复杂,工程性质不稳定,全场分布,厚度1.2-3.60米,为高压缩性。
②粉质粘土:黄灰色,湿,软塑—可塑,零星分布,厚度0.80—2.20米,为中高压缩性,qc=890Kpa,fs=66Kpa,工程性质一般。
③石灰岩:硬度极强,一般机械很难破除,施工难度大,工程性
质稳定,全场分布厚度未知。
④粘质粉土:灰黄色,稍密-中密,很湿,低韧性,干强度低,该层全场分布。厚度1.9~3.2M qc=470Kpa,fs=79Kpa为中等压缩性,工程性质差。
从地质勘探报告得知,场地地表为耕植土,很湿,可塑状态,工程性能差,在地表水渗流作用下很容易崩塌,受场地大小限制,该土层清理后没地方堆积,且耕表土下层为粘土,工程性能较差。经综合进度、质量、安全各方面考虑,决定在基坑开挖时采用喷浆护壁施工工艺。
五、土方开挖前准备工作
(一)技术准备
(1)、熟悉施工图纸和地质勘察报告,掌握基础部分标高和做法,土层和地下水位情况,编制挖土施工方案和交底。
(2)、测量放线工作,根据给定的规划永久性坐标水准点,按建筑物总平面图和建筑红线要求,引测到现场。在建筑物周围,设基测量控制基线,轴线和水平基准点,做好轴线控制的测量和校核。轴线控制网应避开建筑物、构筑物、机械操作运输线路,并设保护标志,作业前需要放出基槽(坑)上口和下口灰线。引测定位标高,对整个场地进行原始地坪测量,并且做好记录。定位龙门桩:在土方开挖不受影响的地方确定位置,并且用12毫米的钢筋头用经纬仪在地面做好复查点,以便随时复核。因为场地不够,土方需要全部外运,先联系好堆放场地,要配备3辆自卸汽车,办理好环境卫生许可证及相关手
续。协调邻里关系,保证工程正常施工,并且在相临建筑做好标记,以便随时测量由于基坑开挖后可能引起的沉降。
(3)、推倒西面调节池处围墙。由于场地面积较小,而政府在做封闭施工围墙时将整个厂区边线往里缩小2米,导致现场可用空地变小,调节池西面边线在围墙外轮廓处,即使合理向东平移后依旧距离围墙过近,使得施工难度增大,且围墙内有不明水源一直向外渗水,为了施工进度以及安全考虑,不得不推倒西面调节池处围墙。
(4)、对参加施工人员进行详细的技术和安全文明施工交底。
(二)材料准备
(1)、基槽(坑)需用明沟和集水井进行降排水时,应准备做集水井的材料,作简单支护时,需准备支护用的材料。
(2)、基槽(坑)需作局部处理或基底换垫时,需准备好换填用材料。
(3)、雨期施工应准备护坡用材料(如塑料布、钢丝网、水泥等)。
(4)、应准备好基础施工材料,以便验槽(坑)后立即进行基础工程的施工,防止过长时间的晾槽。
(三)主要工具
(1)机械:推土机、挖掘机、自卸汽车、水泵等。
(2)工具:铲锹、十字鞒、大锤、钢钎、手推车等。
(四)作业条件
(1)现场三通一平完成,地上地下障碍物已清除。
(2)、基槽(坑)开挖的测量放线工作已完成,并经验收符合设
计要求。
(3)、开挖现场的地表水已排除,采用轻型井点降低地下水位,要求地下水位降至基底500㎜以下。
(4)参加施工人员已进行了技术、安全和文明施工的交底。
(五)工艺流程
测量放线—分层开挖至基底20-30CM—降排水—机械和人工配合挖下翻梁及承台—人工修整—验槽(坑)。
六、土方开挖方案
(一)土方工程工期为18天
由于基坑开挖正处于黄梅雨季,所以开挖土方因天气影响很大,并且夜间不能连续施工,所以合理的安排施工是很重要的。主要是土方堆放问题,现场场地有限,土方不得不外运,应由甲方联系堆土场地。
(二)安全要求和措施
1、开工前全面调查地上、地下障碍物和管线情况,进行具体位置交底,对暂未处理的要树立明显标志。
2、根据本工程回转场地狭小,机械施工、配合工种多的特点,制定安全措施,建立安全责任制并定期开展安全活动。
3、各分项工程,各工种要遵守各自的安全操作规程,注意相互间的安全距离,施工机械不得撞击测量桩等。
4、要执行现场施工用电规定,非专业人员禁止动用施工设备,要经常检查供电线路,闸箱、机电设备的完好和绝缘情况,供电线路
要架空或埋入地下,防止机械碰压。
5、基坑四周要搭设防护栏,设置专用上下通道。
6、机械挖土现场入口设安全岗、配备专人指挥挖土,机械操作者要遵守有关法律规定,按指定方式施工。
7、土方开挖按顺序、方法必须与设计要求相一致,并遵循开槽支撑,先撑后挖,分层开挖,严禁超挖的原则。
8、选择噪声低,振动小,公害小的施工机械和施工方法、减少对现场周围居民的干扰,同时做好周围居民的安抚工作,取得谅解,相互配合。
(三)土方开挖顺序及质量保证措施
1、地下土方开挖以1台SW-150型及一台225型挖机机械开挖为主,人工挖土为辅。挖土分二个施工段,根据施工现场的实际情况,以便于外运,考虑到土方开挖的施工进度和合理的施工顺序,从北向南进行大面积土方一次性分层开挖到设计基底标高,并保留150~300㎜的土不挖,待第一施工段上部土方施工完毕后,再用SW-120型小型挖机进行下翻梁、承台开挖,人工修整挖至设计标高后,立即进行基槽(坑)验收。达到设计规定标准后,即进行地下室工程的基础施工。
2、开挖按踏步式逐行进行,不准一次突发性开挖到底,避免土体短时期大量挖除后,造成围护结构侧向应力增大过快。
3、挖土过程中,保证地下水位离基底标高0.5M以下,为保证排水效果,应配备足够潜水泵和泥浆泵、和轻型井点进行明(暗)沟及
导管排水。
4、机械挖土绘制土方开挖图,规定开挖线路、顺序、范围、底部各层标高、边坡坡度、排水沟、集水井位置及流向,避免混乱,造成超挖、乱挖,应尽可能地使机械多挖,减少机械超挖和人工挖土。
5、为防止开挖过程中,围护体系发生意外,挖土深度应严格控制,每次挖土绝不超挖。并每24小时/次对基坑围护体系深层土体水平位移观测、定时对周围建筑物沉降观测和地下水位观测。
6、严格控制超挖量,土方挖土时排水沟不得靠边设置。
7、做好开挖样板制工作,即凡每一次开挖前,挖一段样板示范,操作者换班时,做好挖深、操作方法等交接班,确保开挖质量。
8、针对原基坑围护方案,因建设单位考虑施工成本多次协商要求取消水泥搅拌桩止水带,采用井点降水来保证基坑施工,详见降水施工方案。
9、同时结合现场情况,增加土钉墙加固边坡稳定,节点做法参照广西省《地下室基坑围护设计》基护-08节点,放坡比例采用1:1.75,下部设置排水沟距边坡大于0.3M,深度0.5M,宽0.3M,1:2水泥砂浆抹面,个边角设置500*500MM深1000MM的集水井。
10、IBR池西侧、西南侧由于堆积土方过多,下雨过大,处出现大面积塌方,所以对该部位边坡先进行修整,压实,然后用100厚C25细石混凝土找坡,上口做压顶挡水,防止地表水流入基坑,边坡下部即冠梁边侧设置砖砌排水沟400*400,并用1:2水泥砂浆抹面,具体做法如图3-1剖面。
米
3-1剖面 锚入钢筋深度视情况可调整
(四)喷浆施工
1、喷射砼的强度等级为C25,厚度为100MM,其配合比为水泥:砂:细石:水=1:2:2:0.45;水泥为普通硅酸盐425级,碎石最大粒径不超过15MM,砂为中粗黄砂
2、喷射顺序是由上而下,喷头与受喷面距离控制在1M左右,喷射方向垂直于受喷面。在钢筋部位,应先喷填钢筋和锚钉后方,然后再喷射其前方,以免其后出空隙。
3、喷射面宜二次喷射,第一次喷射厚度在50MM左右,在第一次砼层初凝前进行二次喷射。
4、在继续下层喷射作业时,清除施工缝接合面上浮浆层和松散碎石,并喷水使之湿润。
(五)、地下水控制
(1)排水沟和集水井设置在建筑基础边净距0.4m以外,排水沟边缘离开边坡坡脚0.3 m处,在基础四周每20~30m,设一个集水井。
(2)排水沟底面应比挖土面低0.4m,集水井底面应比沟底面低0.6 m以上。
(3)、抽水设备根据现场排水量大小及确定。
(4)、当基坑侧壁出现分层渗水时,可按不同高程设置导水管、导水沟等构成明排水系统,当基坑侧壁水量较大或不能分层明排时,宜采用导水降水方法。基坑明排尚应重视环境排水,当地表水对基坑侧壁产生冲刷时,宜在基坑外采取截水,封堵,导流等措施。
(五)、成品保护措施
(1)机械挖土作业时应注意保护测量控制定位桩、轴线桩、水准基桩,防止被挖土和运土机械设备碰撞,行驶破坏。
(2)基坑四周应设排水沟、集水井,场地应有一定坡度,以防止雨水浸泡基坑和场地。
(3)夜间施工应设足够的照明,防止地基、边坡超挖。
(4)基坑开挖时,在开挖全过程中应作好临时支撑保护,不得随意拆除和损害。
(5)在斜坡地段挖土时应遵循由上而下,分层开挖的顺序,以避免破坏坡脚,引起滑坡。
(6)基槽(坑)开挖完成后,应尽快进行下一道工序施工,如不能及时进行施工,应保留一层200~300㎜以上土层。在进行下一道工
序前挖去,以避免基底遭受扰动,降低地基承载力。
(六)施工应急抢险措施
由于基坑开挖深度较大,四周情况复杂,且施工周期长,影响基坑安全的因素很多。须随时做好应付可能出现的不利情况的准备,确定合适的应急措施。
1、 现场配备一定数量的沙包、钢管、钢板桩、水泥、注浆设
备等抢险物资。
2、 对基坑四周24小时进行水平位移监测,如位移较大,应立
即停止开挖土方,增加钢管支撑或斜支撑,必要时回填土方,并坑外卸土。
3、 如地面出现裂缝,应及时灌浆修补,防止地下水渗入。
4、 如围护结构变形过大,在坑底位置设置块石矮挡墙保护坑
脚防止踢脚破坏。
5、 密切关注天气预报,对暴雨等恶劣天气应停止挖土并密切
关注基坑安全。
6、 流砂现象的防治:(1)采用抢挖法,组织分段开挖,边挖
边做垫层及砖胎膜。做到当天挖土当天完成砖胎膜施工。
(2)采用井点降水,在基坑四周按设计方案设置井点降水,局部加深部位增设轻型井点降水,确保地下水降至基坑面以下50CM。
(七)、安全环保措施
(1)机械挖土应分层进行,合理放坡,防止塌方,溜坡等造成机械
倾翻,淹埋等事故。
(2)二台挖掘机在同一作业面机械开挖,挖掘机间距应大于10m,上下台阶挖掘机前后应相距30 m以上,挖掘机离下部边坡应有一定安全距离,以防造成翻车事故。
(3)在有支撑的基坑中挖土时,必须防止碰撞支撑,在坑沟边使用机械时应计算支撑强度、危险地段应加强支撑。
(4)机械施工区域禁止无关人员进入场地内,挖掘机工作回转半径范围内不得站人或进行其他作业。
(5)挖掘机操作和汽车装土行驶要听从指挥,所有车辆必须严格按规定的开行路线行驶,防止撞车。
(6)夜间作业,机械及工作地点必须有充足的照明设施,在危险地段设置明显的警示标志和护栏。
(7)采用降排水措施时,抽出的水应有组织地排放至指定位置,不得任其流而污染场地和环境。采用人工修土时,必须待挖掘机停稳后再挖土,不得在挖掘机回转半径内操作,以免挖掘机 碰撞伤人。
(8)运输土方的车采在场外行驶时,应用加盖车辆或采取覆盖措施,车轮冲洗等措施,以防污染道路和环境。
(八)、质量控制要点
(1)土方开挖前应检查定位放线,排水和降水地下水位系统,合理安排土方运输车的行走路线。
(2)施工过程中应检查平面位置,水平标高和边坡坡度,压实度,排水、降低地下水位系统,并随时观察周围的环境变化。