项目检验和试验计划

郑州人力资源东市场项目 项目检验和实验计划

目 录

第一章 工 程 概 况 ··················································································· 2

第一节 总体简介 ···························································································· 2 第二节 工程建筑设计概况················································································· 2 第三节 工程结构设计概况················································································· 3 第四节 人防地下室工程概况 ·············································································· 5

第二章 施工检验计划 ················································································ 6

第一节 检验人员及检验设备 ··············································································· 6 第二节 施工过程检验、验收计划 ········································································· 9

2.2.1 分部分项工程划分 ····························································································· 9 2.2.2 检验批划分 ··········································································· 错误!未定义书签。 2.2.3检验、验收计划 ································································································ 14 第三节 混凝土结构实体检验计划 ········································································ 23 2.3.1 混凝土强度检验计划表 ····················································································· 23 2.3.2 混凝土钢筋保护层检验计划表 ············································································ 24 第四节 竣工项目安全与功能抽样检测计划表 ························································· 26

第三章 试验计划 ······················································································ 27

第一节 试验管理 ··························································································· 27 第二节 材料试验计划 ····················································································· 27 第三节 土建施工过程试验计划表 ········································································ 31

中国建筑第二工程局有限公司

第一章 工 程 概 况 第一节 总体简介

第二节 工程建筑设计概况

建筑设计概况一览表

第三节 工程结构设计概况

1.结构概况一览表

2.混凝土强度等级设计:

地下室外墙、地下室基础筏板、卫生间楼板、屋顶水箱间楼板混凝土抗渗设计等级:P6,地下室变配电房部分基础、地下室水池侧壁筏板混凝土抗渗设计等级: P8

3.室内装修设计概况: 室内装修做法表

4.建筑节能设计:

第四节 人防地下室工程概况

建筑功能:战时为二等人员掩蔽,平时为汽车库。 建筑面积:1364平方米,掩蔽人数为800人。

地下室耐火等级为一级,防水等级为二级,抗震烈度为7度; 本人防地下室为附建式人防地下室,设在车库地下一层,层高为4.25米;

结构类型为框架剪力墙结构,合理使用年限为50年;

本人防抗力级别为:防核武器抗力级别6级,防生化武器级别丙级; 本工程分为一个防护单元,三个防爆单元,设有两个人防2出入口,一个主要出入口,一个次出入口。

第二章 施工检验计划 第一节 检验人员及检验设备

2.1.1职责 2.1.1.1 质检部

a) 负责检验批划分,检验计划编制,并督促实施; b) 参加检验批验收、工序交接检验,并对其质量进行核定;

c) 参加预检、隐蔽工程验收、分项工程、子分部工程、分部工程、子单位工程、单位工程的验收,并对感观质量、验收资料质量进行核查。 2.1.1.2 工程部

负责组织作业队组自检及交接检、隐检、预检、检验批验收,参加分项、分部、单位工程验收。 2.1.1.3 项目执行经理

负责组织分项、分部、单位工程验收。 2.1.1.4 项目技术(专业)负责人

参加预检、隐检、分项、分布、单位工程验收。 2.1.1.5 分包方

组织或参加其所施工程的班组自检、交接检。 2.1.2 检验器具计划

2.1.2 检验器具计划(安装)

第二节 施工过程检验、验收计划 2.2.1 分部分项工程划分

2.2.1 分部分项工程划分(安装)

2.2.2检验批划分

说明:1.对于结构施工期间的检验批的划分要划分到水平构件和竖向构件。

2.检验批数量根据实际施工情况进行调整。

2.2.2检验批划分(安装)

说明:1.对于主体施工期间的检验批的划分要划分到水平构件和竖向构件。

2.检验批数量根据实际施工情况进行调整。

2.2.3检验、验收计划 2.2.3.1检验、验收计划表

说明:

1、具体检验内容按照各专业验收规范和检验批验收记录表中的要求执行;

2、预检记录、隐检记录在填写时必须将预检、隐检的内容填写齐全准确,可执行《北京市建筑工程资料管理规程》(DBJ01-51-2003); 3、自检、交接检的内容由专业工长指导班组对其实际操作完成且能够检验的项目进行检验,记录在填写时必须将自检交接检的内容、自检的结

果(包括实测实量的数据)填写齐全,对于自检内容比较多的工序,可在自交接检记录上只填写自交接检的内容,具体的检验结果可填写在检验批验收表上(只填写能够由班组完成的内容),并以此作为自检记录的支撑性记录;

4、对于钢筋加工检验批的验收,自检时的检验批的划分可以按照班组划分,可不与验收时检验批的划分一致。 2.2.3检验、验收计划(安装) 2.2.3.1检验、验收计划表(安装)

说明:

1、具体检验内容按照各专业验收规范和检验批验收记录表中的要求执行;

2、预检记录、隐检记录在填写时必须将预检、隐检的内容填写齐全准确。

3、自检、交接检的内容由专业工长指导班组对其实际操作完成且能够检验的项目进行检验,记录在填写时必须将自检交接检的内容、自检的结果(包括实测实量的数据)填写齐全,对于自检内容比较多的工序,可在自交接检记录上只填写自交接检的内容,具体的检验结果可填写在检验批验收表上(只填写能够由班组完成的内容),并以此作为自检记录的支撑性记录。

第三节 混凝土结构实体检验计划

2.3.1 混凝土强度检验计划表 砼强度检验计划

说明:

1.代表部位指每种等级的混凝土所用于的结构部位;

2.同条件养护试件的取样部位应由监理(建设)、施工单位共同选定,有相应的文字记录;

3.混凝土结构工程的各混凝土强度等级均应留置同条件试件; 4.同一强度等级的同条件养护试件,其留置数量应根据混凝土工程量和重要性确定,不宜少于10组,且不应少于3组;

5.同条件养护试件拆模后,应放置在靠近相应结构构件或结构部位的适当位置,并采取相同的养护方法;

6.同条件养护试件的强度试验执行GB50204中附录的规定。 7.具体取样组数根据现场实际施工情况进行调整。 2.3.2 混凝土钢筋保护层检验计划表

混凝土钢筋保护层检验计划

说明:检验的结构部位及选定的构件数量执行GB50204中附录E中的规定 2.3.2.2 检验时机

检验时机应与监理工程师协商,尽量安排在结构施工过程中。 2.3.2.3 检验标准

a) 对梁类构件,应对全部受力钢筋的保护层厚度进行检验; b) 对板类构件,应抽取不少于6根纵向受力钢筋的保护层进行检验; c) 对每根钢筋,应在有代表性的部位测量一点,应明确具体的代表性部位;

d) 梁类钢筋保护层的允许偏差为:+10mm,-5mm;板类钢筋保护层的允许偏差为:+5mm,-3mm。 2.3.2.4 合格判定条件

对梁类、板类构件纵向受力钢筋的保护层应分别进行验收: a) 当全部实体钢筋保护层厚度检验的合格点率为90%及以上时,检验结果应判为合格;

b) 当全部实体钢筋保护层厚度检验的合格点率小于90%但不小于80%,可再抽取相同数量的构件进行检验;当按两次抽样总和计算的合格点率为以上时,检验结果应判为合格;90%及以上时,检验结果仍应判为合格;

第四节 竣工项目安全与功能抽样检测计划表

安全与功能抽样检测计划表

说明:安全与功能检测时机应尽量安排在分部、子分部施工过程或验收时进行检测。

第三章 试验计划 第一节 试验管理

3.1.1 职责 3.1.1.1 技术部

a.及时编制原材料及施工过程试验计划并向实验员交底,当图纸有变化时及时进行修改;

b.定期认真审查、整理各类试验报告单,并将有关数据提供给有关部门; c.指导实验员填写试验委托单。 3.1.1.2 实验员

a.对负责送试验的原材料严格按照要求取样送试验,对试样的代表性、真实性负责;

b.对现场制作的试块作好管理养护工作; c.填写试验委托单。

d.对各送试、试验项目分别建立台帐,作好记录。 3.1.2试验管理程序

技术部对取样人交底→取样人取样→送样并填写委托试验单→试验→取样人取回报告交技术负责人审核(合格,使用;不合格,进行处理)→报告单存档。

第二节 材料试验计划

3.2.1、材料试验计划表

说明:

1..计划用量或实用量指材料的总用量; 2 .原材料试验项目

原材料部分主要有水泥、砂、石、轻集料、粉煤灰、外加剂、掺和料、砌块、钢筋、防水材料、装修用外门窗、装修用人造木板、装修用花岗石、装修用安全玻璃、装修用外墙面砖等。要根据工程的具体情况予以阐述清

楚。

3.具体取样组数根据原材料实际进场情况进行调整。 3.2.1、材料试验计划表(安装)

第三节 土建施工过程试验计划表

3.3.1 混凝土抗压强度试验计划表(土建)

说明:具体取样组数根据现场实际施工情况进行调整。 3.3.2钢筋安装接头试验计划表

说明:具体取样组数根据现场实际施工情况进行调整。

钢管配管施工工艺流程图

郑州人力资源东市场项目 项目检验和实验计划

目 录

第一章 工 程 概 况 ··················································································· 2

第一节 总体简介 ···························································································· 2 第二节 工程建筑设计概况················································································· 2 第三节 工程结构设计概况················································································· 3 第四节 人防地下室工程概况 ·············································································· 5

第二章 施工检验计划 ················································································ 6

第一节 检验人员及检验设备 ··············································································· 6 第二节 施工过程检验、验收计划 ········································································· 9

2.2.1 分部分项工程划分 ····························································································· 9 2.2.2 检验批划分 ··········································································· 错误!未定义书签。 2.2.3检验、验收计划 ································································································ 14 第三节 混凝土结构实体检验计划 ········································································ 23 2.3.1 混凝土强度检验计划表 ····················································································· 23 2.3.2 混凝土钢筋保护层检验计划表 ············································································ 24 第四节 竣工项目安全与功能抽样检测计划表 ························································· 26

第三章 试验计划 ······················································································ 27

第一节 试验管理 ··························································································· 27 第二节 材料试验计划 ····················································································· 27 第三节 土建施工过程试验计划表 ········································································ 31

中国建筑第二工程局有限公司

第一章 工 程 概 况 第一节 总体简介

第二节 工程建筑设计概况

建筑设计概况一览表

第三节 工程结构设计概况

1.结构概况一览表

2.混凝土强度等级设计:

地下室外墙、地下室基础筏板、卫生间楼板、屋顶水箱间楼板混凝土抗渗设计等级:P6,地下室变配电房部分基础、地下室水池侧壁筏板混凝土抗渗设计等级: P8

3.室内装修设计概况: 室内装修做法表

4.建筑节能设计:

第四节 人防地下室工程概况

建筑功能:战时为二等人员掩蔽,平时为汽车库。 建筑面积:1364平方米,掩蔽人数为800人。

地下室耐火等级为一级,防水等级为二级,抗震烈度为7度; 本人防地下室为附建式人防地下室,设在车库地下一层,层高为4.25米;

结构类型为框架剪力墙结构,合理使用年限为50年;

本人防抗力级别为:防核武器抗力级别6级,防生化武器级别丙级; 本工程分为一个防护单元,三个防爆单元,设有两个人防2出入口,一个主要出入口,一个次出入口。

第二章 施工检验计划 第一节 检验人员及检验设备

2.1.1职责 2.1.1.1 质检部

a) 负责检验批划分,检验计划编制,并督促实施; b) 参加检验批验收、工序交接检验,并对其质量进行核定;

c) 参加预检、隐蔽工程验收、分项工程、子分部工程、分部工程、子单位工程、单位工程的验收,并对感观质量、验收资料质量进行核查。 2.1.1.2 工程部

负责组织作业队组自检及交接检、隐检、预检、检验批验收,参加分项、分部、单位工程验收。 2.1.1.3 项目执行经理

负责组织分项、分部、单位工程验收。 2.1.1.4 项目技术(专业)负责人

参加预检、隐检、分项、分布、单位工程验收。 2.1.1.5 分包方

组织或参加其所施工程的班组自检、交接检。 2.1.2 检验器具计划

2.1.2 检验器具计划(安装)

第二节 施工过程检验、验收计划 2.2.1 分部分项工程划分

2.2.1 分部分项工程划分(安装)

2.2.2检验批划分

说明:1.对于结构施工期间的检验批的划分要划分到水平构件和竖向构件。

2.检验批数量根据实际施工情况进行调整。

2.2.2检验批划分(安装)

说明:1.对于主体施工期间的检验批的划分要划分到水平构件和竖向构件。

2.检验批数量根据实际施工情况进行调整。

2.2.3检验、验收计划 2.2.3.1检验、验收计划表

说明:

1、具体检验内容按照各专业验收规范和检验批验收记录表中的要求执行;

2、预检记录、隐检记录在填写时必须将预检、隐检的内容填写齐全准确,可执行《北京市建筑工程资料管理规程》(DBJ01-51-2003); 3、自检、交接检的内容由专业工长指导班组对其实际操作完成且能够检验的项目进行检验,记录在填写时必须将自检交接检的内容、自检的结

果(包括实测实量的数据)填写齐全,对于自检内容比较多的工序,可在自交接检记录上只填写自交接检的内容,具体的检验结果可填写在检验批验收表上(只填写能够由班组完成的内容),并以此作为自检记录的支撑性记录;

4、对于钢筋加工检验批的验收,自检时的检验批的划分可以按照班组划分,可不与验收时检验批的划分一致。 2.2.3检验、验收计划(安装) 2.2.3.1检验、验收计划表(安装)

说明:

1、具体检验内容按照各专业验收规范和检验批验收记录表中的要求执行;

2、预检记录、隐检记录在填写时必须将预检、隐检的内容填写齐全准确。

3、自检、交接检的内容由专业工长指导班组对其实际操作完成且能够检验的项目进行检验,记录在填写时必须将自检交接检的内容、自检的结果(包括实测实量的数据)填写齐全,对于自检内容比较多的工序,可在自交接检记录上只填写自交接检的内容,具体的检验结果可填写在检验批验收表上(只填写能够由班组完成的内容),并以此作为自检记录的支撑性记录。

第三节 混凝土结构实体检验计划

2.3.1 混凝土强度检验计划表 砼强度检验计划

说明:

1.代表部位指每种等级的混凝土所用于的结构部位;

2.同条件养护试件的取样部位应由监理(建设)、施工单位共同选定,有相应的文字记录;

3.混凝土结构工程的各混凝土强度等级均应留置同条件试件; 4.同一强度等级的同条件养护试件,其留置数量应根据混凝土工程量和重要性确定,不宜少于10组,且不应少于3组;

5.同条件养护试件拆模后,应放置在靠近相应结构构件或结构部位的适当位置,并采取相同的养护方法;

6.同条件养护试件的强度试验执行GB50204中附录的规定。 7.具体取样组数根据现场实际施工情况进行调整。 2.3.2 混凝土钢筋保护层检验计划表

混凝土钢筋保护层检验计划

说明:检验的结构部位及选定的构件数量执行GB50204中附录E中的规定 2.3.2.2 检验时机

检验时机应与监理工程师协商,尽量安排在结构施工过程中。 2.3.2.3 检验标准

a) 对梁类构件,应对全部受力钢筋的保护层厚度进行检验; b) 对板类构件,应抽取不少于6根纵向受力钢筋的保护层进行检验; c) 对每根钢筋,应在有代表性的部位测量一点,应明确具体的代表性部位;

d) 梁类钢筋保护层的允许偏差为:+10mm,-5mm;板类钢筋保护层的允许偏差为:+5mm,-3mm。 2.3.2.4 合格判定条件

对梁类、板类构件纵向受力钢筋的保护层应分别进行验收: a) 当全部实体钢筋保护层厚度检验的合格点率为90%及以上时,检验结果应判为合格;

b) 当全部实体钢筋保护层厚度检验的合格点率小于90%但不小于80%,可再抽取相同数量的构件进行检验;当按两次抽样总和计算的合格点率为以上时,检验结果应判为合格;90%及以上时,检验结果仍应判为合格;

第四节 竣工项目安全与功能抽样检测计划表

安全与功能抽样检测计划表

说明:安全与功能检测时机应尽量安排在分部、子分部施工过程或验收时进行检测。

第三章 试验计划 第一节 试验管理

3.1.1 职责 3.1.1.1 技术部

a.及时编制原材料及施工过程试验计划并向实验员交底,当图纸有变化时及时进行修改;

b.定期认真审查、整理各类试验报告单,并将有关数据提供给有关部门; c.指导实验员填写试验委托单。 3.1.1.2 实验员

a.对负责送试验的原材料严格按照要求取样送试验,对试样的代表性、真实性负责;

b.对现场制作的试块作好管理养护工作; c.填写试验委托单。

d.对各送试、试验项目分别建立台帐,作好记录。 3.1.2试验管理程序

技术部对取样人交底→取样人取样→送样并填写委托试验单→试验→取样人取回报告交技术负责人审核(合格,使用;不合格,进行处理)→报告单存档。

第二节 材料试验计划

3.2.1、材料试验计划表

说明:

1..计划用量或实用量指材料的总用量; 2 .原材料试验项目

原材料部分主要有水泥、砂、石、轻集料、粉煤灰、外加剂、掺和料、砌块、钢筋、防水材料、装修用外门窗、装修用人造木板、装修用花岗石、装修用安全玻璃、装修用外墙面砖等。要根据工程的具体情况予以阐述清

楚。

3.具体取样组数根据原材料实际进场情况进行调整。 3.2.1、材料试验计划表(安装)

第三节 土建施工过程试验计划表

3.3.1 混凝土抗压强度试验计划表(土建)

说明:具体取样组数根据现场实际施工情况进行调整。 3.3.2钢筋安装接头试验计划表

说明:具体取样组数根据现场实际施工情况进行调整。

钢管配管施工工艺流程图


相关文章

  • 质量计划范本
  • 中国建筑第五工程局有限公司 项 目 质 量 计 划 (范本) 目 录 1. 工程概况 ............................................................. 3 2. 总则 ....... ...查看


  • 质量计划模板
  • 冀建集生字[2002]第 7 号河北建设集团有限公司关于颁发<项目质量计划管理规定><项目质 . 量计划样板>的通知各分公司.机关相关部室: 根据公司 A 版质量体系文件和 GB/T19001-2000 标准, 对本 ...查看


  • XIN-新汉城施工质量计划范本
  • 质 量 计 划 目 录 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. 18. 19. 20. 工程概况 ................................ ...查看


  • 8质量计划模板C
  • 石油三厂火炬项目 质 量 计 划 山西亚乐士环保技术股份有限公司 火炬项目经理部 2014年 3月 10日 质 量 计 划 项目名称:石油三厂火炬系统改造安装项目 编制单位:(盖章) 编制人: 年 月审核人: 年 月批准人: 年 月 日 日 ...查看


  • 工程质量保证体系样板
  • 工程质量保证体系 一.项目质量保证体系的组成及其分工 为确保该工程达到预定的质量目标,在施工现场设立专职质量员.在业务上服从公司技术质量部的指导,具体在本工程施工过程中按照ISO9001的标准和要求,负责施工质量和管理.检查.监督.在质量问 ...查看


  • 工地试验室检验试验计划
  • 四川公路桥梁建设集团有限责任公司诸永高速公路十四合同段项目经理部 质量体系作业文件 (单行本) 名称:诸永高速公路温州段第十四合同 项目检验.试验计划 文件编号 SRBG-C-GB-C15 版 号 受控状态 发放编号 拟 制 人 审 核 人 ...查看


  • 施工质量计划书
  • 江苏润东医药包装车间项目质量计划书 1. 项目质量计划的编制依据 (1)工程承包合同.设计文件: (2)施工企业的<质量手册>及相应的程序文件: (3)施工操作规程及作业指导书: (4)各专业工程施工质量验收规范: (5)< ...查看


  • 见证取样细则
  • 集美物流园杏美路.前朝路.前场七路道路工程 见证取样监理细则 1.目的 为了规范工程质量的监理工作,满足监理规划和合同目标的要求,实现工程的质量目标,制定本监理实施细则. 2.监理依据 查看具体的分项工程的监理细则. 3.验收准则 合同上有 ...查看


  • 质量管理办法
  • 第三项目部工程质量管理办法 一. 总则 1.为进一步深入贯彻贵广公司"六位一体"管理要求,切实提高本项目部质量管理水平,实现工程质量制度化.科学化.程序化.规范化,根据贵广公司<工程质量管理办法>.<贵 ...查看


热门内容