二、作业任务······························································1 三、作业准备及作业环境条件················································2 四、施工进度安排···························································4 五、作业方法及施工要求·····················································4 六、作业质量标准及检验要求················································8 七、职业安全卫生与环境管理················································8 八、强制性条文····························································11 九、应急预案······························································11
一、编制依据······························································1
离相封闭母线及设备安装作业指导书
一、编制依据
1、根据特变电工新疆硅业有限公司2×350MW 自备热电站工程,新疆电力设计院电气图册65-F102311S-D0401《发电机出线及封闭母线安装》;
2、《电气装置安装工程盘柜及二次回路接线施工及验收规范》 (GB50171—92) ; 3、《电气装置安装工程母线装置施工及验收规范》(GBJ 149-90);
4、《电气装置安装工程电力变压器、油浸电抗器、互感器施工及验收规范》(GBJ-148-90);
5、《电气装置安装工程质量检验及评定规程》(DL/T5161.1-17-2002); 6、设备厂家的出厂技术文件(阜新市新能电力设备厂); 7、《职业安全卫生与环境管理规程》;
8、《工程建设标准强制性条文》电力工程部分-2011版;
9、湖北省电力建设第二工程公司管理体系文件(2008版)及管理作业文件汇编(2008版);
10、电力建设安全工作规程(DL5009.1-2002)
二、作业任务
1、工程概况
发电机与主变压器之间的全连式离相封闭母线、中性点柜均布置在汽机房6.3米层,电压互感器及避雷器柜、励磁变由主回路封闭母线T 接布置在汽机房6.3米层。发电机封闭母线由主厂房6.3米平台引出汽机房A 列柱后与主变压器低压侧套管连接;厂用分支离相封闭母线在主厂房外由发电机封闭母线T 接引入高压厂用变压器高压侧套管,起/备变低压侧共箱母线引入汽机房,接入6KV 厂用配电装置进线柜;高厂变压器低压侧封闭母线沿汽机房A 排柱外布置引入主厂房,接入6KV 厂用配电装置进线柜。
2、特变电工新疆硅业有限公司2×350MW 自备热电站工程主要工程量
三、作业准备及作业环境条件
1、 作业人员的资格要求、劳动力组织
项目负责人 1人 作业组长 2人 技术员 1人 电气安装工 10人 辅助工 4人 试验人员 4人
2、施工机械及工器具准备
3、作业环境及应具备条件
1、施工技术准备
1、施工图纸应到齐,作业人员应认真学习图纸,理解设计要求。
2、技术人员应仔细审核电气图纸及土建相关图纸,及时联系设计人员进行交底并组织相关部门对图纸进行会审。
3、收集并认真学习设备制造厂资料,对制造厂的特殊要求尽早做好技术准备工作。 2、材料、设备准备
1、所有材料、设备和器材应符合国家现行技术规定,并有合格证、材质检验报告,设备有铭牌。
2、审核施工图纸,并按照现场条件及施工实际所需的材料准备到位。
3、核对到货设备的型号、数量及其附件,运至现场在施工区域开箱检查,并做好安装前的防护。
4、设备到现场后存放保管应有专人管理、统一规划。设备宜存放于室内或能避雨、雪、风、沙的干燥场所,有特殊要求的设备应按其要求进行保管。
5、根据工程量估算设备安装用的支撑铁件及垫铁、紧固件等辅助性材料的数量,及时采购、加工备用。
3、开始施工前对建筑工程的要求
1、基础、构架符合电气设备的设计要求,精确核对土建各埋件之间的尺寸。在土建施工时电气专业人员应与土建专业人员密切配合,保证埋件及构架表面平整,尺寸、开孔的数量、大小、位置应与设备承重点一致,保证设备的安装方向与土建埋件、构架的安装方向配合正确,保证埋件、构架的标高准确、中心线位置与设备安装要求相符。 在不能保证以上要求时,要求土建采取相应措施,以免导致设备无法安装。
2、屋顶、楼板施工完毕,不得渗漏;地面基层施工完毕,并标出标高;有可能损坏已经安装的母线装置或安装后不能再进行的装饰工作全部结束。
3、设备的土建基础及构架达到允许的安装强度,由土建专业精确放样,标出各基础的中心线及标高。
4、完成的建筑工程的质量,应符合国家现行的建筑工程施工及验收规范中的有关规定,经验收合格并办理建筑、安装中间交接验收签证书。
5、施工场所杂物应清理干净,施工用的通道畅通。 6、施工区域照明应充足。
7、施工场所临时用电应满足施工要求。用电设施应符合安全要求。
四、施工进度安排
根据总装配图. 逐段校对母线部件、相序、相序编号,然后逐段进行组装定位。安装顺序以从发电机出线箱开始为宜。每一段母线的头尾不能颠倒。
离相封闭母线的安装工序应为:
离相封闭母线吊装→离相封闭母线对口→离相封闭母线焊接
五、作业方法及施工要求
1、作业措施及方案
1.1、土建基础检查
a 、所有基础及预埋按设计要求进行施工. b 、测量发电机纵、横向中心线. c 、测量主变、厂变纵横向中心线. d 、测量PT 柜基础位置及标高. e 、核对墙上予留孔位置的尺寸. f 、画出封闭母线的中心线. 1.2、现场验收保管及搬运开箱检查
a 、封闭母线运到现场后, 应存放在干燥、通风、远离潮湿及含有腐蚀性气体的场所. 开箱验收前应提前通知制造厂人员到达现场共同验收。
b 、产品开箱后, 首先应检查箱内的产品有无因运输及其他原因发生的碰撞损坏现象,如有损坏现象,应做好记录. 双方验收人员在记录上签字。
c 、对于各箱零部件、应根据装箱清单仔细核对箱内零部件的名称、型号、数量。 d 、对于散部件、标准件,特别是镀银件验收后,应立即运往专用保管库,分类登记,按图样要求及施工进度发放零部件. 防止因存放在露天仓库造成受潮、腐蚀、损坏及丢失。
e 、PT 柜、中性点柜、微正压装置、空压机等设备验收后,应妥善保管。 f 、厂家图纸资料齐全. 资料包括:设备装箱清单、产品合格证、出厂试验报告、产品安装图和使用说明书。
g 、用吊车、汽车把封闭母线转运到安装现场附近,严禁碰撞和拖拉。 1.3、钢结构架安装
母线支持钢结构应预先在母线安装前焊接到母线土建的钢结构预埋件上,同时找好水平标高,以便母线安放。
a 、封闭母线支、吊架及固定螺栓均应采用热镀锌件。 b 、焊接处应及时涂刷油漆, 防止锈蚀。 1.4、穿墙板安装
穿墙板由封闭母线厂成套供货. 施工中应按厂家的图纸进行安装。 1.5、封闭母线安装
a 、母线按厂家分段表、相序、编号和标志正确安装放置. 每相外壳的纵向间隙应分配均匀。
b 、根据总装配图,校对母线部件、相序、顺序编号,然后逐段进行组装定位. 安装顺序以从发电机出线箱开始为宜。
c 、母线与外壳同心,两相邻母线及外壳应对准,连接后不应使母线及外壳受机械压力。
d 、每段母线组装后,检查母线对外壳绝缘,并做好记录。
e 、封闭母线安装组合时,要求现场清洁,严防杂物尘土进入封闭母线内部。 1.6 、PT 避雷器柜,中性点柜安装
a 、PT 柜、中性点柜应在母线安装前大致就位. 将盘临时就位在基础上,调正柜的位置,使其能和封闭母线连接合适. 并在PT 柜接地处与接地网可靠焊接。
b 、安装好柜内设备后,按图纸将柜与封闭母线连接。 1.7、母线连接
a 、调整母线支持绝缘子,使母线和外壳的同心度达到最佳的状态,同时校对段与段间的相互位置、距离及轴向同心位置尺寸。对于因运输、吊装可能产生的外壳的圆度变形应做圆度调整,对于现场焊接铝波纹管的接口处,外壳圆度更应做圆度调整。
b 、在封闭母线全部就位,并调整尺寸误差合格,以及绝缘子、盘式绝缘子和电流互感器经过试验合格后,用石棉布做好防护措施,同时应做好发电机出口母线、各段连接母线的防漏油、防淋雨、防土建施工泼水进入母线的防护措施。
c 、母线焊接前,对母线的焊接试验进行检查,检查合格后才能继续进行下阶段
的焊接工作,外壳包箍应紧固定位。
d 、首先进行导体抱瓦的焊接,焊接外壳前清扫母线导体、外壳内表面的积尘、
污物和清洁母线支持瓷瓶等。
e 、在导体金具与设备连接前,将外壳密封用橡胶密封圈及橡胶密封环、紧箍等套到外壳上,以便密封时使用。
f 、母线金具端子镀银搭接面,在吊装时严禁碰撞、划伤,不得任意挫磨。连接时拆下母线金具端子的护板包装,清洗端子镀银表面,清洗铜编织带接头的镀银表面,然后在全部镀银端子上涂以电力复合脂。
g 、贯穿螺栓应由下往上穿,螺栓长度宜露出螺母2~3扣。
h 、螺栓受力应均匀,不应使电器设备的接线端子受到额外的应力。 i 、使用力矩扳手拧紧螺栓,力矩值应符合下表规定.
j 、套上外壳用密封活动套筒及密封橡胶件,并用紧箍箍紧,以实现外壳的密封。 k 、检查并安装外壳接地装置等附件,并根据总装配图样检查母线及外壳固定和活动支点。
1.8、铝母线焊接,详见离相封闭母线焊接作业指导书。 1.9、焊后工作
全部工作完毕后, 清理母线、外壳及安装现场, 对由于运输、吊装时碰、划伤的表面漆膜进行补漆处理,在两端和中间适当部分涂相序色标环。
1.10、地线连接
所有封闭母线的支架、发电机出线箱、外壳的短路板、PT 柜、中性点柜均用扁钢与接地网焊接牢固,封闭母线接地点不得少于两点,焊接处涂防腐材料。
1.11、内部清扫、封闭
a 、封闭母线外壳、内壁、绝缘子表面,内部导体,均清洁无尘,严禁遗留杂物在封闭母线内部。
b 、由人进入封闭母线内部清扫时,应穿无扣工作服,穿绝缘鞋,进出内部的工具要清点并有记录,严防损坏内部绝缘子。
c 、封闭母线进行最后清扫检查,请甲方代表,监理工程师,厂家,公司质检,安全,保卫等有关部门参加检查认可签字。
d 、封闭母线最后进行全封闭工作。 1.12、附件安装
a 、按设计安装微正压装置,并连接管路。 b 、微正压装置的检查调试,按照厂家说明书进行。 1.13、封闭母线的密封检查及充气
a 、利用微正压装置为封闭母线内充气,用刷肥皂水等方法检查封闭母线密封情况。
b 、在密封良好的情况,封闭母线内即可充以制造厂规定的微正压,可投入运行。
2、工艺流程图
3、质量及工艺保证措施
1、由经过培训的有经验的施工人员持证上岗作业。
2、施工过程中使用的工、器具及量具必须经过检验并有标识;所用的材料、设备有合格证及检验报告。
3、每段母线安装后,必须经过有关的人员验收后方可进行下一道工序施工。 4、施工人员严格按设计图纸施工,未经有关单位批准不得随意改动;加强一级验收和过程控制,经多级验收合格签证后,方可投入运行。
5、封母支吊架及盘柜基础施工时,下料尺寸应准确、中间端头切割应平齐、端头上平面应平正,不应有毛刺、飞边;焊接部位应美观,不应有渣孔,整体油漆应均匀。
6、接地线布置应横平竖直,连接点应密实、服贴、焊接牢固。
7、封闭母线不得用裸钢丝绳起吊和绑扎,母线不得任意堆放和在地面上拖拉。 8、盘柜在搬运时应采取防止柜架变形和漆面受损等措施;严禁盘柜外侧焊接,内部焊接点应补刷防锈漆和面漆。
9、施工人员在封母及盘柜上作业时,应用木凳或木梯上下,不准用铁架等有损面漆的构架直接靠到封母及盘柜上,不准穿有泥沙或潮湿的鞋踩在电气设备上。
10、氩弧焊工艺要求详见铝母线焊接作业指导书。
六、作业质量标准及检验要求
在离相封闭母线、盘柜安装结束后,技术员应及时检查验收,根据《电气装置安装工程质量检验及评定规程》(DL/T5161.1-17-2002)规定,填写验收评定表,并由相关的质检员现场仔细验收,合格后参加人员应及时签证认可。
1、强制性条文
为保证工程质量、杜绝安全事故的频繁发生,建设部特颁布了《工程建设标准强制性条文电力部分2006年版》, 各条文内容直接涉及人民财产安全、人身健康、环境保护和其他公众利益,因此班组在施工过程中应当严格按照下列条文执行,以保证工程建设的质量。
与本工程相关的强制性条文如下所示:
《电气装置安装工程 母线装置施工及验收规范》 GBJ 149-1990 第2.4.9条 母线施焊前,焊工必须经过考试合格。
七、职业安全卫生与环境管理
1、发电机出线离相封闭母线安装主要危险辨识
2、发电机出线离相封闭母线安装主要环境因素辨识
3、安全文明施工措施及环境管理目标
1、电气作业人员应掌握《电力建设安全工作规程》的有关规定,并且考试合格;且必须经过安全技术交底。
2、进入施工现场的作业人员必须戴好安全帽;严禁酒后、带病作业。
3、施工中所需电源必须经漏电保护器,明确电压等级,回路正确接引。 4、使用电焊机、电动工具应先检查设备绝缘及接地是否良好,焊机所用的导线必须是良好的绝缘软导线,使用时应穿绝缘鞋戴绝缘手套。
5、搬运及吊装盘柜、变压器、封闭母线时,由起重人员指挥,注意相互间的配合,防止碰伤、挤伤手脚。
6、安装封闭母线时,使用的手动葫芦应找准吊点,防止母线倾斜、移动时砸伤、挤伤。
7、施工所用临时脚手架、板应架设牢固,绑扎结实,经过专业部门验收并挂牌。 8、登高作业,应扎好安全带,系在上方牢固处;高处行走,应注意通道的安全性。 9、在人字梯上施工时,人字梯应架设牢固,地面有专人监护,防止滑倒。
10、使用电火焊时,应配备相应的防护用具,并正确使用。 11、施工废料应及时清理干净,做到工完、料尽、场地清。
12、在安装封闭封闭母线时应保持其内部洁净,不得损伤支持件及母线; 13、施工现场所用的临时电源布置应得当,电线不应在地上乱拉、乱放。电动工具使用完毕应及时切断电源。清理保管好电线及工具。
14、施工现场要有专人监护,必要时可设围栏,防止他人进入危险区域。 15、共箱封闭母线每段施工结束时,应核对所用的工具是否齐全,封母内不得留有任何杂物及工具。
八、强制性条文
杜绝安全事故的频繁发生,严格执行《工程建设标准强制性条文》电力工程部分-2011版中相关条文,具体如下:
《母线装置施工及验收规范》GB 50149-2010
3.5.7 耐张线夹压接前应对每种规格的导线取试件两件进行试压,并在试压合格后再施工。
九、应急预案
9.1、目的:
坚持“安全第一,预防为主”的方针,加强施工现场安全管理,加深员工对危害因素的认识,增强员工的安全防范能力,防止事故发生,消除或减小事故发生造成的危害。
9.2、应急领导小组:
1、职责
(1)组长:负责组织对员工进行事故应急的培训和演练;负责在事故发生时启动应急计划,指挥救援工作,并上报公司主管部门。
(2)副组长:协助组长安排现场救援的各项工作;负责实施应急计划的培训与演练。
(3)成员:负责实施现场救援的各项工作:事故现场的保护、无关人员的疏散、医疗机构的联系、伤员的运送。
2、应急领导小组
组 长: 易正红 副组长: 胡汉涛
成 员:张忠伟 刘居夫 文永祥 胡伟
9.3、应急领导小组职责
组长职责:
①、当接到发生紧急情况的报告之后,立即与就近的医疗机构取得联系,争取尽早将伤员送医院救治。
②、迅速了解大致情况,将大致情况报告上一级部门。 ③、组织现场抢救。
④、做好事故的善后处理,组织主持事故调查,提出对事故责任者的处理意见,将事故调查情况报上一级部门。
副组长职责:
①、协助组长组织现场抢救。
②、迅速进行事故调查,并将事故大致情况报告给组长。 ③、协助组长进行事故的善后处理,迅速恢复生产。 ④、参加事故调查分析,提出防止事故再次发生的技术措施。 小组成员职责:
①、监督参与现场紧急救护,对救护全程监督,防止因救护方法不当而加重伤情。 ②、在抢救伤员的同时,立刻与上一级部门联系,报告现场情况,寻求帮助;在不会导致伤情加重的前提下及早将伤员送医院救治。
③、做好现场恢复工作,尽快恢复生产。
9.4、应急联络部门电话
组长:易正红 [1**********] 副组长:胡汉涛 [1**********] 安监员:文永祥 [1**********] 办公室主任:张忠伟 [1**********] 值班司机:刘居夫 [1**********] 安全保卫部电话:[1**********]
安全保卫部主任:胡汉涛 [1**********] 医院:112
目 录
二、作业任务······························································1 三、作业准备及作业环境条件················································2 四、施工进度安排···························································4 五、作业方法及施工要求·····················································4 六、作业质量标准及检验要求················································8 七、职业安全卫生与环境管理················································8 八、强制性条文····························································11 九、应急预案······························································11
一、编制依据······························································1
离相封闭母线及设备安装作业指导书
一、编制依据
1、根据特变电工新疆硅业有限公司2×350MW 自备热电站工程,新疆电力设计院电气图册65-F102311S-D0401《发电机出线及封闭母线安装》;
2、《电气装置安装工程盘柜及二次回路接线施工及验收规范》 (GB50171—92) ; 3、《电气装置安装工程母线装置施工及验收规范》(GBJ 149-90);
4、《电气装置安装工程电力变压器、油浸电抗器、互感器施工及验收规范》(GBJ-148-90);
5、《电气装置安装工程质量检验及评定规程》(DL/T5161.1-17-2002); 6、设备厂家的出厂技术文件(阜新市新能电力设备厂); 7、《职业安全卫生与环境管理规程》;
8、《工程建设标准强制性条文》电力工程部分-2011版;
9、湖北省电力建设第二工程公司管理体系文件(2008版)及管理作业文件汇编(2008版);
10、电力建设安全工作规程(DL5009.1-2002)
二、作业任务
1、工程概况
发电机与主变压器之间的全连式离相封闭母线、中性点柜均布置在汽机房6.3米层,电压互感器及避雷器柜、励磁变由主回路封闭母线T 接布置在汽机房6.3米层。发电机封闭母线由主厂房6.3米平台引出汽机房A 列柱后与主变压器低压侧套管连接;厂用分支离相封闭母线在主厂房外由发电机封闭母线T 接引入高压厂用变压器高压侧套管,起/备变低压侧共箱母线引入汽机房,接入6KV 厂用配电装置进线柜;高厂变压器低压侧封闭母线沿汽机房A 排柱外布置引入主厂房,接入6KV 厂用配电装置进线柜。
2、特变电工新疆硅业有限公司2×350MW 自备热电站工程主要工程量
三、作业准备及作业环境条件
1、 作业人员的资格要求、劳动力组织
项目负责人 1人 作业组长 2人 技术员 1人 电气安装工 10人 辅助工 4人 试验人员 4人
2、施工机械及工器具准备
3、作业环境及应具备条件
1、施工技术准备
1、施工图纸应到齐,作业人员应认真学习图纸,理解设计要求。
2、技术人员应仔细审核电气图纸及土建相关图纸,及时联系设计人员进行交底并组织相关部门对图纸进行会审。
3、收集并认真学习设备制造厂资料,对制造厂的特殊要求尽早做好技术准备工作。 2、材料、设备准备
1、所有材料、设备和器材应符合国家现行技术规定,并有合格证、材质检验报告,设备有铭牌。
2、审核施工图纸,并按照现场条件及施工实际所需的材料准备到位。
3、核对到货设备的型号、数量及其附件,运至现场在施工区域开箱检查,并做好安装前的防护。
4、设备到现场后存放保管应有专人管理、统一规划。设备宜存放于室内或能避雨、雪、风、沙的干燥场所,有特殊要求的设备应按其要求进行保管。
5、根据工程量估算设备安装用的支撑铁件及垫铁、紧固件等辅助性材料的数量,及时采购、加工备用。
3、开始施工前对建筑工程的要求
1、基础、构架符合电气设备的设计要求,精确核对土建各埋件之间的尺寸。在土建施工时电气专业人员应与土建专业人员密切配合,保证埋件及构架表面平整,尺寸、开孔的数量、大小、位置应与设备承重点一致,保证设备的安装方向与土建埋件、构架的安装方向配合正确,保证埋件、构架的标高准确、中心线位置与设备安装要求相符。 在不能保证以上要求时,要求土建采取相应措施,以免导致设备无法安装。
2、屋顶、楼板施工完毕,不得渗漏;地面基层施工完毕,并标出标高;有可能损坏已经安装的母线装置或安装后不能再进行的装饰工作全部结束。
3、设备的土建基础及构架达到允许的安装强度,由土建专业精确放样,标出各基础的中心线及标高。
4、完成的建筑工程的质量,应符合国家现行的建筑工程施工及验收规范中的有关规定,经验收合格并办理建筑、安装中间交接验收签证书。
5、施工场所杂物应清理干净,施工用的通道畅通。 6、施工区域照明应充足。
7、施工场所临时用电应满足施工要求。用电设施应符合安全要求。
四、施工进度安排
根据总装配图. 逐段校对母线部件、相序、相序编号,然后逐段进行组装定位。安装顺序以从发电机出线箱开始为宜。每一段母线的头尾不能颠倒。
离相封闭母线的安装工序应为:
离相封闭母线吊装→离相封闭母线对口→离相封闭母线焊接
五、作业方法及施工要求
1、作业措施及方案
1.1、土建基础检查
a 、所有基础及预埋按设计要求进行施工. b 、测量发电机纵、横向中心线. c 、测量主变、厂变纵横向中心线. d 、测量PT 柜基础位置及标高. e 、核对墙上予留孔位置的尺寸. f 、画出封闭母线的中心线. 1.2、现场验收保管及搬运开箱检查
a 、封闭母线运到现场后, 应存放在干燥、通风、远离潮湿及含有腐蚀性气体的场所. 开箱验收前应提前通知制造厂人员到达现场共同验收。
b 、产品开箱后, 首先应检查箱内的产品有无因运输及其他原因发生的碰撞损坏现象,如有损坏现象,应做好记录. 双方验收人员在记录上签字。
c 、对于各箱零部件、应根据装箱清单仔细核对箱内零部件的名称、型号、数量。 d 、对于散部件、标准件,特别是镀银件验收后,应立即运往专用保管库,分类登记,按图样要求及施工进度发放零部件. 防止因存放在露天仓库造成受潮、腐蚀、损坏及丢失。
e 、PT 柜、中性点柜、微正压装置、空压机等设备验收后,应妥善保管。 f 、厂家图纸资料齐全. 资料包括:设备装箱清单、产品合格证、出厂试验报告、产品安装图和使用说明书。
g 、用吊车、汽车把封闭母线转运到安装现场附近,严禁碰撞和拖拉。 1.3、钢结构架安装
母线支持钢结构应预先在母线安装前焊接到母线土建的钢结构预埋件上,同时找好水平标高,以便母线安放。
a 、封闭母线支、吊架及固定螺栓均应采用热镀锌件。 b 、焊接处应及时涂刷油漆, 防止锈蚀。 1.4、穿墙板安装
穿墙板由封闭母线厂成套供货. 施工中应按厂家的图纸进行安装。 1.5、封闭母线安装
a 、母线按厂家分段表、相序、编号和标志正确安装放置. 每相外壳的纵向间隙应分配均匀。
b 、根据总装配图,校对母线部件、相序、顺序编号,然后逐段进行组装定位. 安装顺序以从发电机出线箱开始为宜。
c 、母线与外壳同心,两相邻母线及外壳应对准,连接后不应使母线及外壳受机械压力。
d 、每段母线组装后,检查母线对外壳绝缘,并做好记录。
e 、封闭母线安装组合时,要求现场清洁,严防杂物尘土进入封闭母线内部。 1.6 、PT 避雷器柜,中性点柜安装
a 、PT 柜、中性点柜应在母线安装前大致就位. 将盘临时就位在基础上,调正柜的位置,使其能和封闭母线连接合适. 并在PT 柜接地处与接地网可靠焊接。
b 、安装好柜内设备后,按图纸将柜与封闭母线连接。 1.7、母线连接
a 、调整母线支持绝缘子,使母线和外壳的同心度达到最佳的状态,同时校对段与段间的相互位置、距离及轴向同心位置尺寸。对于因运输、吊装可能产生的外壳的圆度变形应做圆度调整,对于现场焊接铝波纹管的接口处,外壳圆度更应做圆度调整。
b 、在封闭母线全部就位,并调整尺寸误差合格,以及绝缘子、盘式绝缘子和电流互感器经过试验合格后,用石棉布做好防护措施,同时应做好发电机出口母线、各段连接母线的防漏油、防淋雨、防土建施工泼水进入母线的防护措施。
c 、母线焊接前,对母线的焊接试验进行检查,检查合格后才能继续进行下阶段
的焊接工作,外壳包箍应紧固定位。
d 、首先进行导体抱瓦的焊接,焊接外壳前清扫母线导体、外壳内表面的积尘、
污物和清洁母线支持瓷瓶等。
e 、在导体金具与设备连接前,将外壳密封用橡胶密封圈及橡胶密封环、紧箍等套到外壳上,以便密封时使用。
f 、母线金具端子镀银搭接面,在吊装时严禁碰撞、划伤,不得任意挫磨。连接时拆下母线金具端子的护板包装,清洗端子镀银表面,清洗铜编织带接头的镀银表面,然后在全部镀银端子上涂以电力复合脂。
g 、贯穿螺栓应由下往上穿,螺栓长度宜露出螺母2~3扣。
h 、螺栓受力应均匀,不应使电器设备的接线端子受到额外的应力。 i 、使用力矩扳手拧紧螺栓,力矩值应符合下表规定.
j 、套上外壳用密封活动套筒及密封橡胶件,并用紧箍箍紧,以实现外壳的密封。 k 、检查并安装外壳接地装置等附件,并根据总装配图样检查母线及外壳固定和活动支点。
1.8、铝母线焊接,详见离相封闭母线焊接作业指导书。 1.9、焊后工作
全部工作完毕后, 清理母线、外壳及安装现场, 对由于运输、吊装时碰、划伤的表面漆膜进行补漆处理,在两端和中间适当部分涂相序色标环。
1.10、地线连接
所有封闭母线的支架、发电机出线箱、外壳的短路板、PT 柜、中性点柜均用扁钢与接地网焊接牢固,封闭母线接地点不得少于两点,焊接处涂防腐材料。
1.11、内部清扫、封闭
a 、封闭母线外壳、内壁、绝缘子表面,内部导体,均清洁无尘,严禁遗留杂物在封闭母线内部。
b 、由人进入封闭母线内部清扫时,应穿无扣工作服,穿绝缘鞋,进出内部的工具要清点并有记录,严防损坏内部绝缘子。
c 、封闭母线进行最后清扫检查,请甲方代表,监理工程师,厂家,公司质检,安全,保卫等有关部门参加检查认可签字。
d 、封闭母线最后进行全封闭工作。 1.12、附件安装
a 、按设计安装微正压装置,并连接管路。 b 、微正压装置的检查调试,按照厂家说明书进行。 1.13、封闭母线的密封检查及充气
a 、利用微正压装置为封闭母线内充气,用刷肥皂水等方法检查封闭母线密封情况。
b 、在密封良好的情况,封闭母线内即可充以制造厂规定的微正压,可投入运行。
2、工艺流程图
3、质量及工艺保证措施
1、由经过培训的有经验的施工人员持证上岗作业。
2、施工过程中使用的工、器具及量具必须经过检验并有标识;所用的材料、设备有合格证及检验报告。
3、每段母线安装后,必须经过有关的人员验收后方可进行下一道工序施工。 4、施工人员严格按设计图纸施工,未经有关单位批准不得随意改动;加强一级验收和过程控制,经多级验收合格签证后,方可投入运行。
5、封母支吊架及盘柜基础施工时,下料尺寸应准确、中间端头切割应平齐、端头上平面应平正,不应有毛刺、飞边;焊接部位应美观,不应有渣孔,整体油漆应均匀。
6、接地线布置应横平竖直,连接点应密实、服贴、焊接牢固。
7、封闭母线不得用裸钢丝绳起吊和绑扎,母线不得任意堆放和在地面上拖拉。 8、盘柜在搬运时应采取防止柜架变形和漆面受损等措施;严禁盘柜外侧焊接,内部焊接点应补刷防锈漆和面漆。
9、施工人员在封母及盘柜上作业时,应用木凳或木梯上下,不准用铁架等有损面漆的构架直接靠到封母及盘柜上,不准穿有泥沙或潮湿的鞋踩在电气设备上。
10、氩弧焊工艺要求详见铝母线焊接作业指导书。
六、作业质量标准及检验要求
在离相封闭母线、盘柜安装结束后,技术员应及时检查验收,根据《电气装置安装工程质量检验及评定规程》(DL/T5161.1-17-2002)规定,填写验收评定表,并由相关的质检员现场仔细验收,合格后参加人员应及时签证认可。
1、强制性条文
为保证工程质量、杜绝安全事故的频繁发生,建设部特颁布了《工程建设标准强制性条文电力部分2006年版》, 各条文内容直接涉及人民财产安全、人身健康、环境保护和其他公众利益,因此班组在施工过程中应当严格按照下列条文执行,以保证工程建设的质量。
与本工程相关的强制性条文如下所示:
《电气装置安装工程 母线装置施工及验收规范》 GBJ 149-1990 第2.4.9条 母线施焊前,焊工必须经过考试合格。
七、职业安全卫生与环境管理
1、发电机出线离相封闭母线安装主要危险辨识
2、发电机出线离相封闭母线安装主要环境因素辨识
3、安全文明施工措施及环境管理目标
1、电气作业人员应掌握《电力建设安全工作规程》的有关规定,并且考试合格;且必须经过安全技术交底。
2、进入施工现场的作业人员必须戴好安全帽;严禁酒后、带病作业。
3、施工中所需电源必须经漏电保护器,明确电压等级,回路正确接引。 4、使用电焊机、电动工具应先检查设备绝缘及接地是否良好,焊机所用的导线必须是良好的绝缘软导线,使用时应穿绝缘鞋戴绝缘手套。
5、搬运及吊装盘柜、变压器、封闭母线时,由起重人员指挥,注意相互间的配合,防止碰伤、挤伤手脚。
6、安装封闭母线时,使用的手动葫芦应找准吊点,防止母线倾斜、移动时砸伤、挤伤。
7、施工所用临时脚手架、板应架设牢固,绑扎结实,经过专业部门验收并挂牌。 8、登高作业,应扎好安全带,系在上方牢固处;高处行走,应注意通道的安全性。 9、在人字梯上施工时,人字梯应架设牢固,地面有专人监护,防止滑倒。
10、使用电火焊时,应配备相应的防护用具,并正确使用。 11、施工废料应及时清理干净,做到工完、料尽、场地清。
12、在安装封闭封闭母线时应保持其内部洁净,不得损伤支持件及母线; 13、施工现场所用的临时电源布置应得当,电线不应在地上乱拉、乱放。电动工具使用完毕应及时切断电源。清理保管好电线及工具。
14、施工现场要有专人监护,必要时可设围栏,防止他人进入危险区域。 15、共箱封闭母线每段施工结束时,应核对所用的工具是否齐全,封母内不得留有任何杂物及工具。
八、强制性条文
杜绝安全事故的频繁发生,严格执行《工程建设标准强制性条文》电力工程部分-2011版中相关条文,具体如下:
《母线装置施工及验收规范》GB 50149-2010
3.5.7 耐张线夹压接前应对每种规格的导线取试件两件进行试压,并在试压合格后再施工。
九、应急预案
9.1、目的:
坚持“安全第一,预防为主”的方针,加强施工现场安全管理,加深员工对危害因素的认识,增强员工的安全防范能力,防止事故发生,消除或减小事故发生造成的危害。
9.2、应急领导小组:
1、职责
(1)组长:负责组织对员工进行事故应急的培训和演练;负责在事故发生时启动应急计划,指挥救援工作,并上报公司主管部门。
(2)副组长:协助组长安排现场救援的各项工作;负责实施应急计划的培训与演练。
(3)成员:负责实施现场救援的各项工作:事故现场的保护、无关人员的疏散、医疗机构的联系、伤员的运送。
2、应急领导小组
组 长: 易正红 副组长: 胡汉涛
成 员:张忠伟 刘居夫 文永祥 胡伟
9.3、应急领导小组职责
组长职责:
①、当接到发生紧急情况的报告之后,立即与就近的医疗机构取得联系,争取尽早将伤员送医院救治。
②、迅速了解大致情况,将大致情况报告上一级部门。 ③、组织现场抢救。
④、做好事故的善后处理,组织主持事故调查,提出对事故责任者的处理意见,将事故调查情况报上一级部门。
副组长职责:
①、协助组长组织现场抢救。
②、迅速进行事故调查,并将事故大致情况报告给组长。 ③、协助组长进行事故的善后处理,迅速恢复生产。 ④、参加事故调查分析,提出防止事故再次发生的技术措施。 小组成员职责:
①、监督参与现场紧急救护,对救护全程监督,防止因救护方法不当而加重伤情。 ②、在抢救伤员的同时,立刻与上一级部门联系,报告现场情况,寻求帮助;在不会导致伤情加重的前提下及早将伤员送医院救治。
③、做好现场恢复工作,尽快恢复生产。
9.4、应急联络部门电话
组长:易正红 [1**********] 副组长:胡汉涛 [1**********] 安监员:文永祥 [1**********] 办公室主任:张忠伟 [1**********] 值班司机:刘居夫 [1**********] 安全保卫部电话:[1**********]
安全保卫部主任:胡汉涛 [1**********] 医院:112